Hussey Metal Division v. Lectromelt Furnace Division

Decision Date14 December 1972
Docket NumberNo. 71-1968.,71-1968.
Citation471 F.2d 556
PartiesHUSSEY METAL DIVISION OF COPPER RANGE COMPANY, a corporation, Appellant, v. LECTROMELT FURNACE DIVISION, McGRAW-EDISON COMPANY, a corporation, Appellee.
CourtU.S. Court of Appeals — Third Circuit

Frank J. Gaffney, Thorp, Reed & Armstrong, Pittsburgh, Pa., for appellant.

Alan Bruce Bowden, Buchanan, Ingersoll, Rodewald, Kyle & Buerger, Pittsburgh, Pa., for appellee.

Before SEITZ, Chief Judge, and FORMAN and HUNTER, Circuit Judges.

OPINION OF THE COURT

HUNTER, Circuit Judge.

Appellant Hussey Metals Division of Copper Range Company appeals under 28 U.S.C. § 1292(a) (1) from an order of the District Court staying proceedings in a breach of contract suit brought by appellant against appellee Lectromelt Furnace Division McGraw-Edison Company.

This is a diversity action, and we are thus bound by Pennsylvania law according to Erie Railroad Company v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938). The District Court's order is appealable under 28 U.S.C. § 1292(a) (1). Merritt-Chapman and Scott Corp. v. Pennsylvania Turnpike Commission, 387 F.2d 768, 770 (3 Cir., 1967). Under a series of documents, appellee sold, designed, and installed a furnace for appellant. The parties dispute whether these documents constitute one contract or several. There was a document, signed April 20, 1966 and revised May 25, 1966, which provided for the furnishing of a furnace by appellee. There was a document dated May 25, 1966 which provided for the design of the furnace, and a document signed September 7, 1966 which provided for construction and installation of this facility. The first document contained an arbitration clause1 while the other two did not. Appellee installed the furnace and appellant was not satisfied with its performance. Appellant refused to make the final payment due under the contract and eventually brought this suit. Appellee counterclaimed for the final payment and demanded that the suit be stayed pending arbitration. The District Court ordered the parties to arbitration. In doing so, the Court did not decide whether the arbitration clause was applicable to this dispute. Instead it permitted the arbitrator to decide whether the parties had agreed to arbitrate appellant's claims.

Appellant presents several arguments for reversal:

(1) The District Court should have determined whether the arbitration clause was applicable to this case;
(2) Under settled Pennsylvania law, the arbitration clause is inapplicable by its own terms;
(3) The third document, for installation of the furnace, was the sole agreement between the parties. Since it contained no arbitration clause, the District Court was incorrect in sending the contract to the arbitrator. But even if the arbitration clause did belong in the installation contract, it was improper for the District Court not to decide whether it applied to this dispute;
(4) Appellee failed to make a timely request for arbitration;
(5) This suit revoked the arbitration clause.

Appellee's basic argument is that this dispute arose under the document for sale of the furnace. This document contains the arbitration clause, and that clause is applicable to this dispute.

Initially, it was incorrect for the District Court not to determine whether this dispute was covered by the terms of the arbitration agreement. It is settled under both Federal and Pennsylvania law that the court must decide whether a party is bound to arbitrate and what issues he must arbitrate. Arbitration is a matter of contract, and a party cannot be forced to arbitrate something which he did not agree to. John Wiley & Sons v. Livingston, 376 U.S. 543, 546, 547, 84 S.Ct. 909, 11 L.Ed.2d 898 (1964); Atkinson v. Sinclair Refining Co., 370 U.S. 238, 241, 82 S.Ct. 1318, 8 L.Ed.2d 462 (1962); Strauss v. Silvercup Bakers, Inc., 353 F.2d 555 (2d Cir. 1965); Howard v. International Brotherhood of Electrical Workers, Local Union No. 570, 423 F.2d 164 (9th Cir. 1970); Women's Society for the Prevention of Cruelty to Animals of Pennsylvania v. Savage, 440 Pa. 34, 269 A.2d 888 (1970); Schoellhammer's Hatboro Manor, Inc. v. Local Joint Executive Board, 426 Pa. 53, 231 A.2d 160 (1967); United Steelworkers of America v. Westinghouse Electric Corp., 413 Pa. 358, 196 A.2d 857 (1964).

In view of the favorable policy towards arbitration, Mendelson v. Shrager, 432 Pa. 383, 248 A.2d 234 (1968), doubts as to whether an arbitration clause may be interpreted to cover the asserted dispute should be resolved in favor of arbitration unless a court can state with "positive assurance" that this dispute was not meant to be arbitrated. See United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U. S. 574, 582-583, 80 S.Ct. 1347, 4 L.Ed.2d 1409.

Because of the Pennsylvania Supreme Court decisions concerning similar arbitration clauses, we can state that the arbitration clause in this case was inapplicable by its own terms.

The clause in pertinent part reads:

"Any disputes, claims or questions, which may arise hereunder and are not disposed of by agreement between the parties shall be subject to arbitration . . .
"Work under the contract shall not be delayed during any arbitration proceedings except by agreement with the Purchaser.
"Notice of the demand for arbitration of a dispute shall be filed in writing with the other party to the contract. The demand for arbitration shall be made within a reasonable time after the dispute has arisen; in no case, however, shall the demand be made later than the time of final payment."

The time of final payment was to be the date of "acceptance of the apparatus, but in any event not later than 120 days after shipment."

Three times the Pennsylvania Supreme Court has held that similar language has meant that arbitration was required only while the work was in progress.

In Westmoreland Hospital Association v. Westmoreland Construction Company, 423 Pa. 255, 223 A.2d 681 (1966), the arbitration clause provided:

"7. Arbitration. (2) It is mutually agreed that all disputes arising in connection with this contract shall be submitted to arbitration. . . .
"(b) The work under this contract shall not be stopped or delayed in any way during the arbitration proceedings except by written mutual consent of both parties to the contract, and such mutual consent shall stipulate whether extension of the time for completion of the contract will be authorized by such stoppage or delay.
"(c) Demand for arbitration in connection with any dispute shall be filed in writing with the Architect and with the other party to the contract. Any demand for arbitration shall be made within thirty days after the dispute has arisen if practicable, but, in any event, no demand for arbitration shall be made after the date of final payment except in the case of a dispute arising in connection with any guarantee provisions of Contract Documents." Id. at 258, 223 A.2d at 682.

The Court held that these provisions made it clear that the purpose for providing arbitration was to insure that completion of the work would not be interrupted and that it "obviously was not meant to apply where the contract was completed." It held this despite the expansive language in the initial clause.

In Emmaus Municipal Authority v. Eltz, 416 Pa. 123, 204 A.2d 926 (1964), the Court held that similar language2 meant that arbitration was intended only for disputes that arose while the work was in progress.

"The reason we infer that the arbitration clause in this contract was not intended to survive this contract is contained in the sentence in Clause B: 408 of the contract which says that a demand for arbitration shall be filed in no case later than the time for final payment. This language indicates that the parties only intended the arbitration clause to be used during the life of the operation of the contract and not to extend after the contract had been terminated by performance, breach or otherwise. The arbitration clause also contains a sentence which says that the contractor shall not cause delay of the construction during any arbitration proceedings. This language also indicates that the parties intended the arbitration procedure to be utilized only during the life of the contract and not after the termination of the contract." Id. at 124, 204 A.2d at 927.

If appellant were to win on the merits of his suit, then there will have been a breach. If appellee were to defend successfully, then there will...

To continue reading

Request your trial
32 cases
  • Becker Autoradio U.S.A., Inc. v. Becker Autoradiowerk GmbH
    • United States
    • U.S. Court of Appeals — Third Circuit
    • July 17, 1978
    ... ... for Becker Electronics' avionics division in Paramus, New Jersey. Becker U.S.A. further ... dispute was not meant to be arbitrated." Hussey Metal Division v. Lectromelt Furnace ... ...
  • Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
    • United States
    • Court of Special Appeals of Maryland
    • May 21, 1974
    ...E. g., Federal Commerce & Navigation Co. v. Kanematsu-Gosho Ltd., 457 F.2d 387, 390 (2d Cir. 1972); Hussey Metal Division v. Lectromelt Furnace Division, 471 F.2d 556, 557-558 (3d Cir. 1972); Pioneer Indus. v. Gevyn Constr. Corp., 458 F.2d 582, 584 (1st Cir. 1972); Swift Indust., Inc. v. Bo......
  • Creative Telecommunications, Inc. v. Breeden
    • United States
    • U.S. District Court — District of Hawaii
    • October 4, 1999
    ...expressed intent not to arbitrate an issue before the issue can be ruled one for judicial determination. See Hussey Metal Division v. Lectromelt Furnace, 471 F.2d 556 (3d Cir. 1972); Singer Co. v. Tappan Co., 403 F.Supp. 322 (D.N.J.1975), aff'd 544 F.2d 513 (3d Cir.1976). The court therefor......
  • Gavlik Const. Co. v. HF Campbell Co.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • October 31, 1975
    ...the course of performance. Gavlik, in seeking authority for this position, relies upon our decision in Hussey Metal Division v. Lectromelt Furnace Division, 471 F.2d 556 (3d Cir. 1973), and the Pennsylvania cases cited therein. In Hussey this Court considered an arbitration clause consistin......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT