In re Evergreen Valley Project Litigation, 122.

Decision Date15 August 1977
Docket NumberNo. 122.,122.
Citation435 F. Supp. 923
PartiesIn re EVERGREEN VALLEY PROJECT LITIGATION. Louis Lenzer, et al. v. Glore Forgan, et al., D. Massachusetts, Civil Action No. 74-2641-M
CourtJudicial Panel on Multidistrict Litigation

Before JOHN MINOR WISDOM, Chairman, and EDWARD WEINFELD, EDWIN A. ROBSON, JOSEPH S. LORD, III*, STANLEY A. WEIGEL, ANDREW A. CAFFREY and ROY W. HARPER*, Judges of the Panel.

OPINION AND ORDER

PER CURIAM.

On November 6, 1973, pursuant to 28 U.S.C. § 1407, the Panel transferred an action (Lenzer) from the Southern District of New York to the District of Massachusetts for coordinated or consolidated pretrial proceedings with three actions pending there. In re Evergreen Valley Project Litigation, 366 F.Supp. 510 (Jud.Pan.Mult.Lit. 1973). These actions are currently assigned to the Honorable Hugh H. Bownes of the District of New Hampshire, sitting in the District of Massachusetts by designation pursuant to 28 U.S.C. § 292(b).

This litigation involves the financing for the construction of a resort complex in the State of Maine. The corporation developing the complex issued two classes of municipal bonds, Series A and Series B, which were secured by similar collateral. The resort projected faltered, construction stopped, and the bonds went into default. Lenzer was brought as a class action on behalf of purchasers of Series B bonds, whereas the other three actions were brought by or on behalf of purchasers of Series A bonds. Defendants in the four actions are the issuing development corporation, the bond rating company, the bond underwriter, its successors and certain individuals. Plaintiffs allege that these defendants violated the federal securities laws, inter alia, in connection with the offering of the two classes of bonds.

Upon the suggestion of the transferee court, the Panel conditionally remanded Lenzer to the Southern District of New York for further proceedings. See Rule 11(f), R.P.J.P.M.L., 65 F.R.D. 253, 262 (1975). Only a defendant in that action, Charles W. Barnes, opposes remand. We find that remand of Lenzer is appropriate at this time and, accordingly, we order that action remanded to the Southern District of New York for further proceedings.

Judge Bownes has found that because of the pendency of related actions in the state courts of Maine and New York, further pretrial discovery in federal court concerning the Series A bondholders is unnecessary. Therefore, he concluded, Lenzer, which concerns only Series B bondholders, will no longer benefit from multidistrict treatment with the three actions concerning only Series A bondholders.

Defendant Barnes requests that Lenzer not be remanded until Judge Bownes rules on defendant Barnes' motion to dismiss which is pending in Lenzer. We see no reason to delay remand pending the disposition of that motion. It can easily be presented to and determined by the transferor court.

The governing statute states that each action transferred by the Panel "shall be remanded by the Panel at or before the conclusion of such coordinated or consolidated pretrial proceedings to the district from which it was transferred unless it shall have been previously terminated." 28 U.S.C. § 1407(a). It is not contemplated...

To continue reading

Request your trial
36 cases
  • In re Lipitor (Atorvastatin Calcium) Mktg., Sales Practices & Prods. Liab. Litig.
    • United States
    • U.S. District Court — District of South Carolina
    • January 3, 2017
    ...MDL courts have the discretion to suggest remand prior to resolving case-specific issues.15 See In re Evergreen Valley Project Litig ., 435 F.Supp. 923, 924 (J.P.M.L. 1977) ("It is not contemplated that a Section 1407 transferee judge will necessarily complete all pretrial proceedings in al......
  • U.S. ex rel. Hockett v. Columbia/Hca Healthcare
    • United States
    • U.S. District Court — District of Columbia
    • July 17, 2007
    ...("To be coordinated, it is not necessary that common issues are being contemporaneously addressed."); In re Evergreen Valley Project Litig., 435 F.Supp. 923, 924 (Jud.Pan.Mult.Lit.1977) (statute contemplates that transferee judge "in his discretion will conduct the common pretrial proceedin......
  • In re Lipitor (Atorvastatin Calcium) Mktg., Sales Practices & Prods. Liab. Litig.
    • United States
    • U.S. District Court — District of South Carolina
    • January 3, 2017
    ...cumbersome, MDL courts have the discretion to suggest remand prior to resolving case-specific issues.31 SeeIn re Evergreen Valley Project Litig ., 435 F.Supp. 923, 924 (J.P.M.L. 1977) ("It is not contemplated that a Section 1407 transferee judge will necessarily complete all pretrial procee......
  • In re Equifax, Inc. Customer Data Sec. Breach Litig.
    • United States
    • U.S. District Court — Northern District of Georgia
    • April 13, 2022
    ... ... RE EQUIFAX, INC., CUSTOMER DATA SECURITY BREACH LITIGATION MDL No. 2800 No. 1:17-md-2800-TWT United States District ... to him by the Panel[.]” In re Evergreen Valley ... Project Litig. , 435 F.Supp. 923, 924 ... ...