Industrial Works v. Mitchell

CourtMichigan Supreme Court
Writing for the CourtMONTGOMERY, J.
CitationIndustrial Works v. Mitchell, 114 Mich. 29, 72 N.W. 25 (Mich. 1897)
Decision Date16 July 1897
PartiesINDUSTRIAL WORKS v. MITCHELL ET AL.

Error to circuit court, Saginaw county; Eugene Wilber, Judge.

Action by the Industrial Works against John A. Mitchell and Chauncey E. Mitchell for the price of certain machinery. From a judgment in favor of plaintiff, defendants bring error. Modified.

James B. McMahon, for appellants.

H. H Hatch, for appellee.

MONTGOMERY J.

In the month of December, 1890, defendants had a contract for dredging for the government at Sand Beach, Mich. It became necessary for them to build a dredge to be used in performing their contract. They entered into a contract with the plaintiff, by the terms of which the plaintiff agreed to furnish and deliver the machinery necessary to be used in the dredge as early as March 1, 1891, at an agreed price. Plaintiff brought this action to recover upon notes given in renewal of notes previously given for the purchase price. Defendants sought to recoup damages occasioned by delay in not furnishing the machinery within the time prescribed, and for further delay resulting from defects in the machinery. The cause was tried before a referee, who made a special finding of facts and of law, and whose finding was affirmed by the circuit court. From the decision of the circuit court defendants appeal. The finding shows that no part of the machinery was delivered to the defendants until the 31st of March, 1891, and that, when the machinery was delivered, it was so badly constructed that it required 14 days longer to set it up than it would have required had it been constructed in a workmanlike manner. There was a further delay of 3 days after the machinery was set up, because of improper construction of the dipper-handle machinery, and 9 days' delay because of other latent defects in the machinery. Altogether, a delay of 56 days occurred, and the referee finds that the net profit the defendants would have made during each of these 56 days would have amounted to $54.80, had they been able to use the dredge. The referee further finds that before the making of the contract defendants informed the plaintiff that they had a government contract for excavating at Sand Beach, and needed a dredge stronger than the one they then had with which to do the excavating under said contract; and to questions propounded by defendants' counsel answers were returned as follows "Was the plaintiff informed that defendants had a government contract at Sand Beach, for which they desired to use their dredge? A. Yes." "Was plaintiff informed of the character of the digging or work intended to be done by the dredge? A. No, except that they wanted a stronger dredge than the one they had."

The principal question involved in this case is whether the defendants are entitled to recoup the loss of profits which the referee finds that they have suffered by reason of the delay in furnishing the machinery, and the further delay occasioned by furnishing defective machinery. A preliminary question arises as to whether defendants had waived their right to claim damages for the delay. In answer to a question by the plaintiff, the referee found that before the giving of the notes in suit defendants had accepted and appropriated to their own use all the machinery manufactured and delivered under the contract, and it is contended that their acceptance and retention of the machinery, not having reserved any right to complain of a nondelivery on time, amounts to a waiver of all right to recover for the damages which they claim. The referee finds further upon this subject that "By the terms of the contract there was a cash payment to be made on March 1st, and on the same day notes were to be given for the remainder of the purchase price. This was the same day provided for the delivery of the machinery at the hull of the dredge in Port Huron. This fact shows that the parties, when they made this contract, did not contemplate that the defendants were to have an opportunity to examine or test this machinery before making payment, and the payments were made without regard to the actual delivery of the machinery. The $2,000 cash payment was made on March 4th, about thirty days before the machinery was actually delivered. The plaintiff, by its Exhibit 79, on April 25th, almost thirty days before Streng had completed placing the machinery, made demand for the note under contract, and the note was given without reference to the actual condition of the machinery." The acceptance of the machinery under the circumstances of this case as disclosed by the finding was practically an acceptance under compulsion. As was said by the court in Ramsey v. Tully, 12 Ill.App. 463: "To say that an acceptance, after the time for delivery had passed, under such circumstances, was voluntary in such sense as to evince an intention to waive their right to claim damages for the delay, would be a perversion of language. They did the best they could in the situation in which they found themselves placed." See, also, Haven v. Wakefield, 39 Ill. 509; Hansen v. Kirtley, 11 Iowa, 565; Flannery v. Rohrmayer, 46 Conn. 558; Ruff v. Rinaldo, 55 N.Y. 664. The giving of the note under such circumstances is not conclusive of an intention to waive the claim for damages. See Waterman v. Clark, 76 Ill. 428; Wheelock v. Berkley, 38 Ill.App. 518. See, also, Bodurtha v. Phelon, 13 Gray, 413. Plaintiff, however, contends that the inference from the circumstances found by the referee is that there was an intention to waive the claim for damages. But we think the findings as a whole do not sustain this view, and that the defendants are entitled to recoup such damages as they have shown in this case.

The case presents the vexed question as to when the profits lost by the party defeated of his contract by the wrongful act of another may be the basis for damages. The briefs of counsel on both sides in this case are full, and ably present the two different views which may be taken of the question, as applied to the facts in this case. The case of Hadley v. Baxendale, 9 Exch. 354, has been approved by most of the American courts, and by this court in Hopkins v. Sanford, 38 Mich. 611. The rule as stated in that case is that, where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally; i. e. according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it; and that, if the special circumstances under which the contract was actually made were communicated, and thus known to both parties, the damages...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex