International Engineering Company v. Richardson

Decision Date24 October 1973
Docket NumberCiv. A. No. 927-73.
Citation367 F. Supp. 640
PartiesINTERNATIONAL ENGINEERING COMPANY, a Division of A-T-O, Inc., Plaintiff, v. Elliot L. RICHARDSON et al., Defendants.
CourtU.S. District Court — District of Columbia

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

vom Baur, Coburn, Simmons & Turtle by Robert H. Turtle, James M. McHale, Washington, D. C., for plaintiff.

Leonard W. Belter, Robert M. Werdig, Jr., Asst. U. S. Attys., for defendants.

MEMORANDUM OPINION

CHARLES R. RICHEY, District Judge.

Once again this case is before this Court on a Motion for a Preliminary Injunction filed by Plaintiff International Engineering Company (IEC).1 In order to understand the reasons advanced by Plaintiff in support of its Motion, and the Court's reasons for granting thereof, a review of the history of this case will be helpful. The Court will summarize only briefly the history prior to its earlier decision. See International Engineering Company v. Elliot L. Richardson, et al., 361 F.Supp. 818, D.D.C.1973.

I. HISTORY OF THE CASE

In late 1967, IEC conceived a system for guiding bombs or missiles with what is referred to by the parties as a LORAN C/D system. In February 1968, IEC submitted an unsolicited proposal to the Air Force that detailed the processes and the performance characteristics of the components as IEC had developed them at the time. This proposal, submitted with a restrictive legend that limited its distribution to Air Force personnel, resulted in the Government's award of a contract to IEC that called for Plaintiff to design and construct a "helicopter flyable breadboard LORAN Missile Guidance Subsystem." (See Plaintiff's Exhibit D, Defendant's Exhibit D). The system was to be constructed and furnished by IEC for the purposes of demonstration but was to remain the property of IEC; the information resulting from demonstration of the system was to be provided to the Government as set forth at Paragraph (b)4 of T-119 incorporated by reference into the DD1423 Test Report as follows:

"(4) Description of test articles, including test configuration identification and photographs as appropriate." Defendant's Exhibit E.

The contract provision central to the instant dispute is the Rights in Technical Data clause, an Armed Services Procurement Regulation (7-104.9) incorporated by reference into the contract. Paragraph (b) of the Regulation provides in pertinent part that:

"(1) The Government shall have unlimited rights in:
"(i) technical data resulting directly from performance of experimental, developmental or research work which was specified as an element of performance in this or any other Government contract or subcontract; . . .
"(ii) technical data necessary to enable manufacture of end-items, components and modifications, or to enable the performance of processes, when the end-items, components, modifications or processes have been, or are being developed under this or any other Government contract or subcontract in which experimental, developmental or research work is, or was specified as an element of contract performance, except technical data pertaining to items, components or processes developed at private expense." (emphasis added).
"(iv) technical data pertaining to end-items, components or processes which was prepared for the purpose of identifying sources, size, configuration, mating and attachment characteristics, functional characteristics and performance requirements ("form, fit and function" data, e. g., specification control drawings, catalog sheets, envelope drawings, etc.);" (emphasis added).
"(2) The government shall have limited rights in:
"(ii) technical data pertaining to items, components or processes developed at private expense, other than such data as may be included in the data referred to in (b)(1)(i), (iii), (iv), (v), and (vi); provided that each piece of data to which limited rights are to be asserted pursuant to (2)(i) and (ii) with the following legend in which is inserted the number of the prime contract under which the technical data is to be delivered and the name of the contractor or subcontractor by whom the technical data was furnished . . ."2

Paragraph (d) of the same regulation provides for the removal of unauthorized legends marked on data which the contractor delivers to the Government. The contract interpretation problem confronting the Court turns on the meaning attached to the term "substantiate" as it appears in paragraph (d) which is set forth as follows:

"(d) Removal of Unauthorized Markings. Notwithstanding any provisions of the contract concerning inspection and acceptance, the Government may modify, remove, obliterate or ignore any marking not authorized by the terms of this contract on any technical data furnished hereunder if—
"(i) the contractor fails to respond within sixty days to a written inquiry by the Government concerning the propriety of the use of the marking, or
"(ii) the Contractor's response fails to substantiate his contention that the use of the marking is authorized, in which case the Government shall give written notice to the Contractor." (emphasis added)

During the time frame for constructing the "Breadboard system" called for in the contract, January 1968 through June 1970, IEC developed an advanced circuitry LORAN C/D Navigation System, at what it alleges to be substantial private expense. As will be discussed in greater detail below, the Government disagrees on the material fact of whose money paid for the development of the Navigation System and argues that the system was developed through Government funding of the contract.3 The Government's position on the question of funding was made known after the original contract had been modified twice to incorporate the Navigation System into other parts of a LORAN guided bomb and to run simulated tests on a computer, and after IEC had submitted several technical reports which contained a detailed description of the internal operations in terms of mathematical and logic diagrams of IEC's precontract components that the Air Force Project Engineer, Mr. Rustenberg, requested in the belief that the information would be helpful to the Air Force in evaluating the test results. (See Contracting Officer's Statement of Reasons for Decision of 2 October 1972; Rustenberg Deposition, pages 29, 34-36). Between October 1970 and November 1970 IEC submitted technical reports which contained "limited rights" legends intended to prevent the release of components' specifications to IEC's competitors. The Air Force never challenged the restrictive legend on the first report, 71-05. However, the first Contracting Officer assigned to the IEC contract questioned the appropriateness of restrictive markings placed by IEC on the second Technical Report, 70-06-4, on the grounds that the restrictive legend was of the kind used for proposals and not contract reports. IEC offered to delete the material altogether and simply comply with the limited requirements of the contract. IEC also submitted an amended proprietary legend. In July 1971 the Contracting Officer decided to accept the amended markings without further question for the following reason:

"the issuance of P0006 (a contract modification) directing a continuation of the effort initiated under P0003 (an earlier contract modification) constituted a tacit acceptance by the Government." (Exhibit 1 to Harsfield deposition).

In so deciding, the Contracting Officer chose to reject the request of the Contract Engineer, Mr. Rustenberg, that the restrictive legend be ruled improper under the terms of the contract. It is noteworthy that Mr. Rustenberg as early as March 1971 requested the proprietary data to facilitate the Air Force's evaluation of the test results. (Rustenberg Deposition, page 29).

Sometime before the submission of the third report, a new Contracting Officer, Mr. Harsfield, began work on the contract. Mr. Rustenberg served as technical advisor to the new Contracting Officer and on his behalf reviewed the third report. (Rustenberg Deposition, page 31). That report was accepted as submitted without immediate objection.

It was in October and December 1971 respectively that the third technical report and the final report on the original contract and all modifications were submitted and, like the earlier reports, they contained the detailed descriptions of the components requested by Mr. Rustenberg and bore proprietary legends. At the end of December 1971 and almost nine months later in June 1972, the Contracting Officer sent letters to IEC recommending that IEC remove the proprietary markings or furnish substantiation to the contrary. IEC replied January 5, 1972 to the Contracting Officer's December 1971 correspondence but received no further response from the Government until a letter was received June 5, 1972, wherein the Contracting Officer stated that the IEC submission "fails to justify the use of their legend or show that any restriction is authorized." (See Plaintiff's Exhibit M). He further noted that the reports would be used with unlimited rights. IEC obtained an agreement on the part of the Air Force not to release the reports pending a meeting "to discuss the proprietary rights question." This meeting occurred June 26, 1972 and was conducted by Mr. Harsfield. During the course of the meeting, IEC submitted a three-page outline and made a two hour oral presentation which was deemed vague by the Contracting Officer who requested additional substantiation. At no time during the meeting did Mr. Harsfield question the IEC position. (Harsfield Deposition, pp. 76-77). Shortly thereafter, the Contracting Officer executed a final acceptance on the contract and final payment was made by the Air Force at the end of September 1972. The Contracting Officer received no further efforts at substantiation by IEC and, by letter dated October 2, 1972, informed the Contractor that the reports would be used by the Government with...

To continue reading

Request your trial
5 cases
  • Megapulse, Inc. v. Lewis
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 29 janvier 1982
    ...5 U.S.C. § 702 (1976).21 International Engineering Co. v. Richardson, 361 F.Supp. 818 (D.D.C.1973).22 International Engineering Co. v. Richardson, 367 F.Supp. 640 (D.D.C.1973).23 International Engineering, 512 F.2d at 581.24 Id. at 578.25 Id. at 580.26 Id., citing 5 U.S.C. § 704 (1970).27 A......
  • International Engineering Co., Div. of A-T-O, Inc. v. Richardson, A-T-
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 19 juin 1975
    ...relief as the Court of Claims and Armed Services Board of Contract Appeals could not grant such relief. In its second decision, 367 F.Supp. 640, the court began from the premise that even if it possessed jurisdiction, the decision to grant judicial relief was discretionary. Id. at 647-48; s......
  • Collins & Co., General Contractors v. Claytor
    • United States
    • U.S. District Court — Northern District of Georgia
    • 19 septembre 1979
    ...regulations. Scanwell Laboratories, Inc. v. Shaffer, 137 U.S.App.D.C. 371, 424 F.2d 859 (D.C. Cir. 1970); International Engineering Co. v. Richardson, 367 F.Supp. 640 (D.D.C.1973); General Electric Co. v. Seamans, 340 F.Supp. 636 Additionally, the Fifth Circuit has recognized the need for a......
  • Valley Const. Co. v. Hoffman, CV476-145.
    • United States
    • U.S. District Court — Southern District of Georgia
    • 23 juillet 1976
    ...348 F.Supp. 911 (M.D., Fla.); M. Steinthal & Co. v. Seamans, 147 U.S.App.D.C. 221, 455 F.2d 1289; International Engineering Company v. Richardson, 367 F.Supp. 640, 650-51 (D.C.). The plaintiff bears the "heavy burden of proving that a procurement officer's decision was genuinely arbitrary a......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT