INTERNATIONAL U. OF OP. ENG., LOC. 150 v. Flair Builders, Inc.

Decision Date12 April 1971
Docket NumberNo. 18334.,18334.
Citation440 F.2d 557
PartiesINTERNATIONAL UNION OF OPERATING ENGINEERS, LOCAL 150, AFL-CIO, Plaintiff-Appellant, v. FLAIR BUILDERS, INC., Defendant-Appellee.
CourtU.S. Court of Appeals — Seventh Circuit

Bernard M. Baum, Daniel S. Shulman, Robert H. Baum, Chicago, Ill., for plaintiff-appellant.

J. Robert Murphy, Aurora, Ill., Edward J. Griffin, Chicago, Ill., for defendant-appellee; Murphy, Griffin & Dixon, Aurora, Ill., and DeFrees, Fiske, Voland, Alberts & Hoffman, Chicago, Ill., of counsel.

Before SWYGERT, Chief Judge, DUFFY, Senior Circuit Judge, and STEVENS, Circuit Judge.

SWYGERT, Chief Judge.

The primary question in this appeal is whether a court may properly dismiss the complaint on the basis of laches resulting from dilatory notification of the existence of a dispute in a suit brought to compel arbitration with regard to the dispute.

This action was brought in November 1968 by the International Union of Operating Engineers, Local 150, AFL-CIO, under section 301 of the Labor Management Relations Act of 1947, 29 U.S.C. § 185(a), against Flair Builders, Inc., a construction company located in Sugar Grove, Illinois.

Initially, the union sought specific performance of an alleged bargaining agreement between the parties. Upon Flair's motion the district court dismissed the complaint for failure to state a claim. At the time of the dismissal the district judge, having observed that an "additional issue" had been suggested by the parties, namely, whether a "memorandum agreement" executed by the parties constituted a binding collective bargaining agreement, suggested that this issue be submitted to arbitration. Thereafter, the union demanded arbitration of "the issues pending before the court concerning the applicability of the contract and the subsequent issues of possible violations." After Flair refused to arbitrate, the union filed an amended complaint seeking to compel arbitration.

The company filed a motion to dismiss the amended complaint, contending that the action was barred by laches. The motion was denied, and the cause was set for an evidentiary hearing to determine which issues, if any, the employer agreed to arbitrate. After hearing evidence, the court filed its order and memorandum opinion dismissing the action. A summary of the evidence submitted to the district court follows.

The union represents laborers who operate heavy equipment, such as cranes, in the construction industry and negotiates master collective bargaining agreements with contractor associations in various parts of Illinois. The union also negotiates individual memoranda of agreement with contractors who are not members of the contractor associations, such as Flair. These memoranda adopt and bind the nonmember contractor to the terms of the master agreements.

On June 1, 1963, the union entered into a master agreement with a number of contractor associations in northern Illinois. This agreement terminated on May 31, 1966. On May 12, 1964, the union and Flair signed a memorandum of agreement which specifically adopted the terms of the then existing master agreement. Flair also agreed to adopt any additional master agreements entered into between the union and the contractor associations.

At the time of execution of the memorandum in 1964, the company had one employee covered by the agreement. Upon the insistence of the union this employee joined the union, but left his employment about two weeks later. Other nonunion employees continued from time to time to operate Flair's single piece of equipment. In 1965, the company added a second piece of heavy equipment, in 1966 a third, and in 1967 a fourth, all of which were operated by company employees who were nonunion. Yet during all this period of time, from May 1964 until the summer of 1968, the company was not contacted by the union.

In the meantime, in 1966, the union and the contractor associations entered into a new master agreement which contained a stipulation that "should any difference arise between the parties hereto which cannot be settled by their representatives, within 48 hours of the occurrence, such difference shall be submitted to arbitration." It was further stipulated that the arbitrators should meet within six days after it was determined that the dispute could not be settled.

In June 1968, the union business agent visited the company's job site and discovered a nonunion employee operating a piece of equipment. Shortly thereafter, the employee joined the union; however, the company refused to pay the union wage scale.1 Subsequently the union filed the instant suit.

In dismissing the action the district court ruled that the union had been guilty of laches by its unjustified delay in the enforcement of its contract with the company. In the course of his memorandum opinion the district judge said:

To require Flair to respond, through arbitration, to general charges of noncompliance with contract provisions allegedly beginning more than two years before this suit was filed would impose an extreme burden on its defense efforts. Especially is this so when, as demonstrated at the hearing, Flair understandably considered the contract to have been abandoned soon after its inception. Plaintiff has offered no explanation for its delay in enforcement; yet to compel arbitration would reward plaintiff for its own inaction and subject defendant to the risk of liability because of actions taken or not taken in reliance on plaintiff\'s apparent abandonment.

The district judge also found that there had been no contact whatsoever between the union and Flair from the date of the signing of the memorandum of agreement in 1964 until the summer of 1968. This determination was made after the district judge had heard conflicting testimony and concluded that the testimony of Flair's witness was more credible than that of the union's business agent because of inconsistencies in the latter's testimony. Such findings of fact based on the credibility of witnesses are entitled to great weight on review. The record reveals no justification for overturning the trial court's findings. Moreover, when the trial judge requested that "the union by letter to this court within ten days should specify in some detail what violations of the purported agreement it seeks to arbitrate, and the time of their occurrence * * *," the union's response was devoid of specificity and amounted to nothing more than the concluding statement of its letter that it sought "to arbitrate the total violation of the entire agreement in question since * * * June 1, 1966."

The factual context of this appeal thus narrows the issue before us to the question of whether a party to a collective bargaining agreement which contains an arbitration clause may be so dilatory in making the existence of vaguely delineated disputes known to the other party that a court is justified in refusing to compel the submission of such disputes to arbitration. The district court found for Flair and dismissed the complaint on the ground of laches. We affirm.

The union contends that the question of whether its dilatory notification of the existence of a dispute should operate to bar this suit to force the employer to arbitration is a question of procedural timeliness which courts are required to leave to the...

To continue reading

Request your trial
11 cases
  • Singer Company v. Tappan Company
    • United States
    • U.S. District Court — District of New Jersey
    • 20 October 1975
    ...of laches under Section 4. Worthy of note is the Halcon court's distinguishing of its earlier decision in Operating Engineers v. Flair Builders, Inc., 440 F.2d 557 (7th Cir. 1971), on the basis of Flair having arisen under Section 301 of the Labor Management Relations Act (29 U.S.C. § 185),......
  • Tobacco Wkrs. Int. U., Local 317 v. Lorillard Corporation
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • 16 September 1971
    ...bargaining agreement where delay in presenting the grievance has prejudiced the defendant. International Union of Operating Engineers Local 150 v. Flair Builders, Inc., 440 F.2d 557 (7th Cir. 1971); Amalgamated Clothing Workers of America v. Ironall Factories Co., 386 F.2d 586 (6th Cir. 196......
  • Washington Hosp. Center v. Service Employees Intern. Union Local 722, AFL-CIO, AFL-CIO
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 26 October 1984
    ...Union of Operating Engineers Local 150 v. Flair Builders, Inc., 406 U.S. 487, 92 S.Ct. 1710, 32 L.Ed.2d 248 (1972), rev'g, 440 F.2d 557 (7th Cir.1971), the Union did not enforce the contract for more than two years. The company signed on to a master agreement in 1964, two weeks before its o......
  • Controlled Sanitation Corp. v. District 128 of Intern. Ass'n of Machinists and Aerospace Workers, AFL-CIO
    • United States
    • U.S. Court of Appeals — Third Circuit
    • 23 February 1976
    ...period 1964-68, but that the Union was barred by laches. The Court of Appeals affirmed, Operating Engineers Loca. 150 v. Flair Builders, Inc., 440 F.2d 557 (7th Cir.1971). The Supreme Court, however, reversed, holding as we read the opinion that the court's duty was limited to deciding whet......
  • Request a trial to view additional results
1 books & journal articles
  • Should the Supreme Court stop inviting amici curiae to defend abandoned lower court decisions?
    • United States
    • Stanford Law Review Vol. 63 No. 4, April 2011
    • 1 April 2011
    ...(on file with the Earl Warren Papers, Library of Congress). Compare Int'l Union of Operating Eng'rs, Local 150 v. Flair Builders, Inc., 440 F.2d 557, 557 (7th Cir. 1971) ("J. Robert Murphy ... for defendant-appellee"), with Flair Builders, 406 U.S. at 487 (1972) ("J. Robert Murphy.... as am......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT