J.I. Hass Co., Inc. v. Gilbane Bldg. Co.

Citation881 F.2d 89
Decision Date18 October 1989
Docket NumberNo. 88-5523,88-5523,Nos. 88-5465,No. 88-5465,88-5465,s. 88-5465
PartiesJ.I. HASS CO., INC., v. GILBANE BUILDING COMPANY, a corp. in the State of Rhode Island. Appeal of GILBANE BUILDING COMPANY, inJ.I. HASS CO., INC., Appellant in, v. GILBANE BUILDING COMPANY, a corp. in the State of Rhode Island.
CourtUnited States Courts of Appeals. United States Court of Appeals (3rd Circuit)

Milton M. Breitman (argued), Greenberg, Margolis, Ziegler, Schwartz, Dratch, Fishman, Franzblau & Falkin, P.C., Roseland, N.J., for appellant-cross appellee (Hass).

Richard L. Abramson (argued), Peckar & Abramson, P.C., River Edge, N.J., for appellee-cross appellant (Gilbane).

Before HIGGINBOTHAM, STAPLETON and COWEN, Circuit Judges.

OPINION OF THE COURT

A. LEON HIGGINBOTHAM, Jr., Circuit Judge.

This is both an appeal and a cross-appeal from the judgment of the district court awarding the plaintiff-appellant quantum meruit compensation pursuant to a jury verdict. The plaintiff-appellant contends that the district court erred in its determination of the prejudgment interest due under the award. The defendant-cross-appellant appeals from the district court's judgment on the merits of this case, contending that the district court misapplied the law and committed reversible trial errors. Upon our review of the record before us and the legal precepts involved, we find for the cross-appellant. Accordingly, we will reverse the district court's judgment and remand for a new trial.

I.

This action arises out of a contractual dispute between a prime contractor and subcontractor, both of whom were involved in the construction of a brewery for the Miller Brewing Company ("Miller") in Trenton, Ohio. The Gilbane Building Company of Rhode Island ("Gilbane"), one of Miller's prime contractors, entered into a subcontract with the J.I. Hass Company, Inc. of New Jersey ("Hass"), a painting contractor. This subcontract, dated March 24, 1981, was written and executed by both parties and required Hass to perform painting work in certain buildings in the construction project. 1 The subcontract also contained language, standard in the construction trade, allowing Gilbane to direct Hass to perform extra work through the issuance of change orders that increased the subcontract's scope. Under these change orders, Hass was to receive additional compensation in exchange.

Section 7(b) of the parties' subcontract provided for the performance of extra work and the payment thereof as follows:

(b) No changes shall be made in the work except upon the written order of the Contractor; the amount to be paid by the Contractor or allowed by the Subcontractor by virtue of said changes to be stated in said orders. In the event of any additions, the amount of compensation to be paid, as so ordered, shall be determined as follows:

(1) By such applicable unit prices as set forth in the contract, or

(2) If no such unit prices are set forth, then by a lump sum mutually agreed upon by the Architect, General Contractor and Subcontractor, or

(3) If no such unit prices are set forth, and if the parties cannot agree upon a lump sum, then by the actual net cost in money to the Subcontractor of materials and labor ... plus compensation of 5% for overhead and 10% for profit.

Appendix ("App.") at 3378.

Pursuant to Sec. 7(b), change order no. 1 was entered on June 1, 1981. Under that change order, Hass agreed to paint more facilities for an additional $753,000. App. at 3466. After Hass had begun performing under change order no. 1, however, a dispute arose between Gilbane and Hass as to whether certain painting of the buildings' "mechanical systems" 2 fell within the change order's scope. Gilbane directed Hass to perform the work that was disputed. Hass subsequently performed some of the work under protest, submitting a claim for compensation pursuant to the extra work provisions of the subcontract. Gilbane adhered, however, to its interpretation of change order no. 1 as providing Hass with full compensation for the extra work, and rejected Hass' claim for additional compensation.

On May 13, 1983, Hass commenced this action against Gilbane in the United States District Court for New Jersey, which had diversity jurisdiction pursuant to 28 U.S.C. Sec. 1332(a)(1) (1982). Hass not only advanced a claim for compensation for the contested extra work, but also sought, in the first count of its complaint, rescission of the base subcontract on the ground that no contract had formed between the parties. The matter proceeded to trial, and was submitted to the jury upon instructions and written interrogatories. The first interrogatory put to the jury asked:

1. Has plaintiff proven that there was no contract between plaintiff Hass and defendant Gilbane?

App. at 159.

At the end of the first day of deliberations, the jury submitted the following communication to the district court:

Re[garding] question number 1. We agree that the base contract existed and we agree that there was no meeting of the minds on change order number 1. Confusion arises as to the wording of question number 1. Based on what we agree on, is the answer yes or no to question number 1?

App. at 3239.

Over Gilbane's objection, the district court responded to the jury's question as follows:

Considering the evidence and the Court's instructions as a whole and considering all of the work together, you must determine as a whole whether Hass has proven that there was no contract between the plaintiff Hass and the defendant Gilbane.

App. at 3251-52.

Thereafter, the jury returned with a verdict answering the first interrogatory in the affirmative--i.e., that there was no contract between Hass and Gilbane. Consequently, the jury awarded Hass $1,461,872.63 in quantum meruit compensation, the amount owed on Hass' total cost claim, 3 including a 21% mark-up for overhead and profit. The jury also found that Gilbane was entitled to a credit of $242,251 against Hass for a "fair allowance for any defects or omissions in ... Hass' performance of the work." App. at 161.

Gilbane subsequently moved for judgment notwithstanding the verdict and, alternatively, for a new trial, remittitur, or reduction in the money judgment. The court denied Gilbane's first three motions but granted a $31,000 reduction in the award of damages. On May 25, 1988, the court entered judgment nunc pro tunc against Gilbane in the amount of $1,188,621.63 plus $291,908 in pre-judgment interest for a total sum of $1,480,529.63.

On June 9, 1988, Gilbane filed its notice of appeal as to the final judgment of the district court, and on June 22, 1988, Hass filed its notice of appeal as to the district court's determination of pre-judgment interest due under the award. In addition, we granted leave on January 17, 1989 for the Building Contractors Association of New Jersey ("BCA") to file a brief in this appeal as an amicus curiae. We have jurisdiction pursuant to 28 U.S.C. Sec. 1291 (1982).

II.

Gilbane's principal argument on appeal is that there was a valid subcontract between the parties as a matter of law, irrespective of the dispute as to the scope of work under change order no. 1. On that basis, Gilbane contends that the district court erred in denying its motion for a directed verdict dismissing the first count of Hass' complaint and its motion for a judgment notwithstanding the verdict or, alternatively, for a new trial. Gilbane also contends that the district court erred in denying its motion for a new trial on the basis that the district court, through its supplemental jury instruction, had erroneously rejected the jury's initial determination of the existence of a contract. 4 Gilbane is joined in its contentions by the BCA.

The applicable standards of review are well settled. In reviewing a district court's denial of a directed verdict, "[w]e must determine whether, as a matter of law, the record is critically deficient of that minimum quantum of evidence from which a jury might reasonably afford relief.... [I]f the evidence is of such character that reasonable [persons], in the impartial exercise of their judgment may reach different conclusions, the [count] should be submitted to the jury." Patzig v. O'Neil, 577 F.2d 841, 846 (3d Cir.1978).

Next, when reviewing a district court's denial of a judgment n.o.v., we are required to review the record in this case in the light most favorable to the non-moving party. We will affirm the district court's denial of the motion "unless the record is 'critically deficient of that minimum quantity of evidence from which the jury might reasonably afford relief.' " Link v. Mercedes-Benz of North America, Inc., 788 F.2d 918, 921 (3d Cir.1986) (citation omitted).

Given that the district court's denial of the motion for a new trial was based on its application of a legal precept, our review is plenary. Honeywell v. American Standards Testing Bureau, 851 F.2d 652, 655 (3d Cir.1988), cert. denied, --- U.S. ----, 109 S.Ct. 795, 102 L.Ed.2d 787 (1989).

Finally, we review the district court's supplemental jury instruction to determine "whether, viewed in light of the evidence, the charge as a whole fairly and adequately submits the issues in this case to the jury." Bennis v. Gable, 823 F.2d 723, 727 (3d Cir.1987). We will reverse the district court " 'only if the instruction was capable of confusing and thereby misleading the jury.' " Id. (citation omitted).

III.

Our first task upon review is to ascertain whether, as a matter of law, a contract existed between Gilbane and Hass, regardless of their dispute as to the scope of work encompassed by change order no. 1. Since this case arises under diversity jurisdiction, we look to the substantive law of New Jersey, where the district court sits, for guidance. Erie Railroad Co. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 822, 82 L.Ed. 1188 (1938).

Under the law of New Jersey, the central query in the construction of...

To continue reading

Request your trial
27 cases
  • Virgin Island Mar. Serv., Inc. v. Puerto Rico Mar. Shipping Auth.
    • United States
    • U.S. District Court — Virgin Islands
    • 24 Junio 1997
    ...can be but one reasonable conclusion on the verdict.); Williams v. Guzzardi, 875 F.2d 46, 50 (3d Cir.1989); J.I. Hass Co. v. Gilbane Building Co., 881 F.2d 89, 91 (3d Cir.1989). The United States Supreme Court has made clear that judges are no longer required to submit a question to a jury ......
  • Lithuanian Commerce Corp. v. Sara Lee Hosiery
    • United States
    • U.S. District Court — District of New Jersey
    • 30 Julio 2002
    ...of their judgment may reach different conclusions, the case should be submitted to the jury.'" Id. (quoting J.I. Hass Co., Inc. v. Gilbane Bldg. Co., 881 F.2d 89, 92 (3d Cir.1989)). "By such direction of the trial the result is saved from the mischance of speculation over legally unfounded ......
  • DR BY MR v. East Brunswick Bd. of Educ.
    • United States
    • U.S. District Court — District of New Jersey
    • 23 Noviembre 1993
    ...the parties' true intent, but the intent as expressed or apparent in the writing that controls." J.I. Hass Co., Inc. v. Gilbane Building Co., 881 F.2d 89, 92 (3d Cir.1989); see also Dome Petro. Ltd. v. Employers Mutual Liability Ins. Co., 767 F.2d 43, 47 (3d The Agreement is clear and unamb......
  • Air Master Sales Co. v. Northbridge Park Co-Op, Inc.
    • United States
    • U.S. District Court — District of New Jersey
    • 19 Septiembre 1990
    ...the parties' true intent, but the intent as expressed or apparent in the writing, that controls." J.I. Hass Co., Inc. v. Gilbane Building Co., 881 F.2d 89, 92 (3d Cir.1989). "A contract must be sufficiently definite in its terms to ascertain with reasonable certainty the performance to be r......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT