J.P. Stravens Planning Associates, Inc. v. City of Wallace

Decision Date04 December 1996
Docket NumberNo. 22069,22069
Citation928 P.2d 46,129 Idaho 542
PartiesJ.P. STRAVENS PLANNING ASSOCIATES, INC., Plaintiff-Appellant, v. CITY OF WALLACE, Defendant-Respondent.
CourtIdaho Court of Appeals

Kenneth S. Bridgeman, Coeur d'Alene, for plaintiff-appellant.

Hollis J. Anderson, Wallace, for defendant-respondent.

LANSING, Judge.

J.P. Stravens Planning Associates, Inc. (Stravens) appeals from the district court's judgment in favor of the City of Wallace in Stravens' action for payments alleged to be due under a personal services contract. We affirm.

I. FACTS

In January 1990, Stravens entered into a written contract with the City of Wallace to render services related to the design of a proposed downtown revitalization project, the preparation of an application for a grant to finance the project, and the management of the project construction. The contract provided that Stravens was to bill the city "on a time and expense basis" with the first billing payable on submission of a grant application. In May 1990, Stravens submitted a grant application to the Idaho Department of Commerce (DOC) and began to bill the city. However, the grant request was rejected by the DOC because of inadequacies in the application. From May 1990 forward, Stravens sent monthly bills for its services to the city, but the city made no payments.

In August 1990, Stravens submitted a second grant application to the DOC which also was rejected. The city's mayor became concerned and contacted the DOC to inquire why the second application had not been approved. The program manager of the DOC's block grant program responded with a letter stating that the application was unacceptable on its face "because major sections of information were not addressed." The missing information included a "local economic analysis" of the city's downtown area, a "plan of action identifying the who, what, where, when and how to accomplish downtown revitalization" and a "list of accomplishments and the community's progress in implementing the plan." The city continued to refuse to pay amounts billed by Stravens for services rendered. After negotiations to settle the dispute failed, Stravens filed this action seeking damages for breach of contract.

The case was tried before the district court sitting without a jury. The court ruled in favor of the city on alternate grounds. The court first held that Stravens' claim for breach of contract was barred because Stravens did not give timely notice of its claim as required by I.C. §§ 6-906 and 50-219. In the alternative, the court held that the city was excused from its contractual obligation to pay for Stravens' services because Stravens had breached an implied warranty to perform the services called for by the contract in a workmanlike manner. On appeal, we find the second basis for the trial court's decision to be dispositive, and we therefore do not determine whether Stravens complied with the notice requirements of I.C. §§ 6-906 and 50-219.

II. ANALYSIS
A. Breach of Contract

The implied warranty of workmanlike performance was discussed in Hoffman v. Simplot Aviation, Inc., 97 Idaho 32, 36, 539 P.2d 584, 588 (1975), as follows:

In circumstances involving personal services ... the warranty is implied that the services will be performed in a workmanlike manner. The standard imposed may vary depending upon the expertise of the actor, either possessed or represented to be possessed, the nature of the services Stravens makes no argument that this standard does not apply to its performance under the contract. It asserts, however, that the trial court erred in finding that Stravens breached the warranty in this case. Specifically, Stravens contends that the grant applications it prepared were rejected due to factors that were beyond its control, including a lack of preparatory actions by, and commitment of funding from, the city itself.

and the known resultant danger to others from the actor's negligence or failure to perform.

When an action has been tried to a court sitting without a jury, appellate review is limited to ascertaining whether the evidence supports the trial court's findings of fact and whether these findings support the court's conclusions of law. Morris v. Frandsen, 101 Idaho 778, 780, 621 P.2d 394, 396 (1980). The findings of fact of the trial court will be accepted if they are supported by substantial, competent evidence, though that evidence may be controverted. Sun Valley Shamrock Resources, Inc., v. Travelers Leasing Corporation, 118 Idaho 116, 118, 794 P.2d 1389, 1391 (1990); Rueth v. State, 103 Idaho 74, 77, 644 P.2d 1333, 1336 (1982). The task of weighing evidence is within the province of the trial court, and we therefore accord great deference to the trial judge's opportunity to weigh conflicting testimony and to assess the credibility of witnesses. Rueth, supra; PFC, Inc. v. Rockland Telephone Co., Inc., 121 Idaho 1036, 1038, 829 P.2d 1385, 1387 (Ct.App.1992). It follows that this Court will view the evidence in the light most favorable to the prevailing party. Rueth, supra; Martsch v. Nelson, 109 Idaho 95, 100, 705 P.2d 1050, 1055 (Ct.App.1985).

In this case, the district court set out its findings and conclusions in a memorandum decision. The district court found that before contracting with Stravens the city wished to revitalize its downtown area, that the city knew that funding was available somewhere but knew nothing about how to obtain a grant, that Stravens held itself out to the city as a skilled "grant writer," and that the city thus contracted with Stravens to identify funding sources and to submit an application for a grant from these yet undetermined sources. Most importantly, the court found that although Stravens attempted to lay the blame for the rejection of the applications on a lack of commitment from the city, the responsibility for the inadequate applications ultimately lay with Stravens. In the words of the district court:

The City was not entitled to guarantee [sic] of successful application much less perfection. It was entitled, however, to expect that plaintiff, a professional grant writer, would be sufficiently versed with the applicable standards and rule [sic] of the craft so as to be able to advise the city as to what it needed to do, if indeed it needed to do anything, and in any event to do what was necessary to present an application that would at least meet minimum standards so as to entitle the city for [sic] mere consideration. The record shows that the application prepared by plaintiffs did not meet such standard. Plaintiff attempts to lay this off to some vaguely defined "lack of community commitment," but it was his responsibility under the obligation of the contract relating to "the design" of the revitalization project to manage the presentation in at least a sufficient manner to put the application on the table.

The essence of the district court's findings is that the city was relying upon Stravens' expertise for the project design and the coordination of the grant application process, and that if the grant from the DOC was dependant upon the commitment of funds from or action by the city or other sources, it was Stravens' duty to inform and advise the city of these facts so that the requisite action could be taken prior to the submission of grant applications. These findings are supported by evidence presented at trial, including the contract itself which specified that Stravens would "design" the revitalization project, "prepare preliminary scope of project," develop a "preliminary project program and identify funding sources," and "design the Local Improvement District."

In challenging the court's finding that Stravens failed to perform these obligations, Stravens relies upon the testimony of DOC's block grant program manager. This witness Stravens also argues that the district court erred in relieving the city of its obligation to pay Stravens because the city did not show that it was damaged by Stravens' breach of warranty or, if damaged, the amount of such damages. Stravens' argument evidences a misunderstanding of the city's position and of governing contract law. The city did not seek an affirmative recovery against Stravens; it sought only a judgment relieving the city of any obligation to pay Stravens' claimed fees. 1 Therefore, the city had no need to prove damages.

said that grant applications often go through a process of submittal, rejection, rewriting to satisfy any shortcomings noted by the DOC, and resubmittal before approval is given. However, the chief executive officer of Stravens admitted at trial that it was Stravens' obligation to inform the city of this common practice and that it had not done so. Moreover, even the second grant application submitted by Stravens was so incomplete that the DOC deemed it unworthy of any consideration. Trial evidence indicates that the city was essentially left uninformed and without advice as to what it should be doing, knowing only that its hired expert had submitted two grant applications that did not meet the minimum standards necessary even to merit consideration by the granting authority. The district court's findings regarding the scope of Stravens' contractual obligations and its breach of those obligations are supported by substantial and competent evidence.

The more appropriate inquiry is whether Stravens' failure to perform in a workmanlike manner was a "material" breach of the contract. If a breach of contract is material, the other party's performance is excused. Ervin Const. Co. v. Van Orden, 125 Idaho 695, 700, 874 P.2d 506, 511 (1993); Enterprise, Inc. v. Nampa City, 96 Idaho 734, 740, 536 P.2d 729, 735 (1975); Ujdur v. Thompson, 126 Idaho 6, 878 P.2d 180 (Ct.App.1994); Mountain Restaurant Corp. v. ParkCenter Mall Associates, 122 Idaho 261, 265, 833 P.2d 119, 123 (Ct.App.1992). "A substantial or material breach of contract is one which touches the fundamental purpose of...

To continue reading

Request your trial
14 cases
  • Horton v. Horton
    • United States
    • Virginia Supreme Court
    • June 6, 1997
    ...to the parties' agreement that it defeated an essential purpose of the contract. See, e.g., J.P. Stravens Planning Associates, Inc. v. City of Wallace, 129 Idaho 542, 928 P.2d 46, 49 (App.1996); Rogers v. Relyea, 184 Mont. 1, 601 P.2d 37, 40-41 (1979); Macon Mining & Manufacturing, Inc. v. ......
  • City of Meridian, an Idaho Mun. Corp. v. Petra Inc.
    • United States
    • Idaho Supreme Court
    • April 1, 2013
    ...Afton Energy, Inc. v. Idaho Power Co., 122 Idaho 333, 344, 834 P.2d 850, 861 (1992) ; J.P. Stravens Planning Associates, Inc. v. City of Wallace, 129 Idaho 542, 545, 928 P.2d 46, 49 (Ct.App.1996). The district court did not expressly address the City's claim that a material breach of the co......
  • State v. Chacon
    • United States
    • Idaho Court of Appeals
    • September 10, 2008
    ...breach. If a breach of contract is material, the other party's performance is excused. J. P. Stravens Planning Assoc., Inc. v. City of Wallace, 129 Idaho 542, 545, 928 P.2d 46, 49 (Ct.App.1996). This Court has defined a material breach of contract as follows: A material breach of contract i......
  • 1998 -NMCA- 155, Famiglietta v. Ivie-Miller Enterprises, Inc., IVIE-MILLER
    • United States
    • Court of Appeals of New Mexico
    • August 19, 1998
    ...central to the parties' agreement that it defeated an essential purpose of the contract"); J.P. Stravens Planning Assocs., Inc. v. City of Wallace, 129 Idaho 542, 928 P.2d 46, 49 (Idaho Ct.App.1996) (where nonbreaching party seeks to be relieved of his obligations under the contract he must......
  • Request a trial to view additional results
1 books & journal articles
  • Management of Contract Terminations from Multiple Perspectives
    • United States
    • ABA General Library The Construction Lawyer No. 42-1, January 2022
    • January 1, 2022
    ...2d 1170, 1178 (D. Wyo. 2000), aff’d, 6 F. App’x 828 (10th Cir. 2001). 4 See J.P. Stravens Planning Assocs., Inc. v. City of Wallace , 129 Idaho 542, 545, 928 P.2d 46, 49 (Ct. App. 1996); see also Cent. Arkansas Found. Homes, LLC v. Choate , 2011 Ark. App. 260, 10, 383 S.W.3d 418, 425 (2011)......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT