JD Hedin Construction Co. v. FS Bowen Electric Co.

Decision Date08 October 1959
Docket NumberNo. 14971.,14971.
Citation106 US App. DC 386,273 F.2d 511
PartiesJ. D. HEDIN CONSTRUCTION COMPANY, Inc., Appellant, v. F. S. BOWEN ELECTRIC COMPANY, Inc., Appellee.
CourtU.S. Court of Appeals — District of Columbia Circuit

Mr. J. Roy Thompson, Jr., Washington, D. C., with whom Mr. Bernard J. Gallagher, Washington, D. C., was on the brief, for appellant.

Mr. Irwin Geiger, Washington, D. C., with whom Mr. Michael A. Schuchat, Washington, D. C., was on the brief, for appellee.

Before WILBUR K. MILLER, WASHINGTON and BASTIAN, Circuit Judges.

WASHINGTON, Circuit Judge.

This is a suit for breach of contract. The Hedin Company was general contractor for the construction of a new school building in Maryland. Hedin executed a written agreement in standard form with the Bowen firm, whereby Bowen was named as electrical sub-contractor for the project and agreed to do stated work for the total sum of $310,000. Some six weeks later, Hedin entered into an agreement for the same work with another firm (the A. G. Crunkleton Electric Co.), and notified Bowen that the contract had been "re-awarded." Bowen brought suit for breach of contract. The District Court, sitting without a jury, found for Bowen, and awarded damages.

On appeal, defendant-appellant Hedin urges chiefly that no enforceable contract with Bowen ever came into effect, saying that Bowen was never approved by the local Board of Education sponsoring the construction project, and that such approval was a prerequisite. The Bowen-Hedin contract does recognize that the Board — which was not a party to it — has "the right to accept or reject the use of any sub-contractor on the construction of the building." But the trial judge found as a fact, on the basis of fully adequate evidence, that the Board of Education "at no time rejected plaintiff but on the contrary expressed itself as fully satisfied with respect to plaintiff's ability to perform the contract and its financial responsibility." True, the record shows that the Board wanted the electrical work to go to Crunkleton, and that Hedin acted as it did in an effort to be obliging. Also, the Board later formally accepted Crunkleton at Hedin's request. But there is no showing that the Board then knew that Hedin had previously entered into a signed contract with Bowen, and we do not think the Board's action amounted to a rejection of Bowen in the contractual sense. Clearly Hedin cannot argue that the Board's unexercised right of rejection relieves Hedin from liability on the contract which it had theretofore executed with Bowen.1 Hedin is bound.

We are constrained, however, to reverse the judgment, by reason of error in the computation of damages by the District Court. The court made an award in the following terms in its findings of fact:

"13. On the basis of all the testimony and exhibits herein, the profits plaintiff could have fairly and reasonably anticipated had defendant permitted it to continue to perform under the aforesaid contract are at least Thirty Thousand Dollars ($30,000.00)."

In its conclusions of law the court said:

"4. Plaintiff has been damaged by defendant in the sum of Thirty Thousand Dollars ($30,000.00) and is entitled to judgment against defendant in that amount.
"Let judgment be entered accordingly."

At an earlier stage, the judge had reviewed with counsel for both parties the form and content of the draft findings and conclusions proposed by the plaintiff. When asked by defense counsel for an explanation of the amount awarded, the judge replied:

"The $30,000 was arrived at after a complete and thorough analysis of the testimony of the witness Phelps, in which I cut down his approximations. I did not believe that they were warranted. I think we arrived at $27,000, wasn\'t it, and then I merely added the $3,000 to make it an even number."

The action of the judge in adding $3,000 to the award "to make it an even number" was clearly improper. Litigants' funds are not to be dealt with so lightly. Further, the $27,000 figure does not appear to have any sound legal or evidentiary basis. The "witness Phelps," referred to by the judge, was an electrical contractor, offered as an expert by the defendant Hedin. Phelps testified that in his opinion the work would have cost $330,518, as against the contract price of $310,000, resulting in a loss of $20,518. How the court converted this into a profit of $27,000 is not clear. (Plaintiff claimed it would have made profits totaling $53,713 — almost exactly twice the figure of $27,000 arrived at by the court.) The "approximations" to which Phelps testified were his estimates of the probable cost of necessary labor and materials, viewed as of the date of the contract. Whether or not these "approximations" were accurate is not, of course, our task to say. But it does not appear...

To continue reading

Request your trial
10 cases
  • CR–RSC Tower I, LLC v. RSC Tower I, LLC
    • United States
    • Maryland Court of Appeals
    • November 27, 2012
    ...(applying the “time of breach” rule to determine the value of “bargained-for goods” under Texas law); J. D. Hedin Constr. Co. v. F. S. Bowen Electric Co., 273 F.2d 511, 513 (D.C.Cir.1959) (applying the “time of breach” rule to determine the value of the promised construction rights, calcula......
  • CR–RSC Tower I, LLC v. RSC Tower I, LLC
    • United States
    • Court of Special Appeals of Maryland
    • January 5, 2012
    ...of favorable post-breach market conditions is inadmissible to show increased direct lost profits. J.D. Hedin Constr. Co. v. F.S. Bowen Elec. Co., 273 F.2d 511, 513 (D.C.Cir.1960). J.D. Hedin concerned the breach of a sub-contract under a construction contract. Id. The trial court admitted p......
  • PETER KIEWIT SONS'CO. v. Summit Construction Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • November 26, 1969
    ...nearly as possible according to the circumstances as they exist at the time of the breach.20 J. D. Hedin Construction Co. v. F. S. Bowen Electric Co., 106 U.S.App.D.C. 386, 273 F.2d 511, 513 (1960). However, Kiewit contends that the trial court improperly applied this rule to the instant Ki......
  • Smith v. Andrews
    • United States
    • Georgia Court of Appeals
    • July 6, 1976
    ...F.2d 55 (5th Cir. 1955); Smallfield v. Home Ins. Co. of N.Y., 244 F.2d 337 (9th Cir. 1957); J. D. Hedin Construction Co. v. F. S. Bowen Electric Co., 106 U.S.App.D.C. 386, 273 F.2d 511 (1959). Although there is some evidence in the record which, if believed, would have supported a denial of......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT