Jefferson Parish School Bd. v. Rowley Co., Inc.

Decision Date30 December 1974
Docket NumberNo. 6460,6460
Citation305 So.2d 658
PartiesJEFFERSON PARISH SCHOOL BOARD v. ROWLEY COMPANY, INC., and Louisiana Joint Underwriters of the Audubon Insurance Co.
CourtCourt of Appeal of Louisiana — District of US

Jack A. Grant, Gretna, for Jefferson Parish School Board, plaintiff-appellant.

Rene R. Nicaud, Nicaud, Justrabo & Rousset, New Orleans, for Rowley Co Inc., defendant-appellee; Hugh H . Brister, New Orleans, of counsel.

William A. Porteous, III, William W. Miles, Porteous, Toledano, Hainkel & Johnson, New Orleans, for Louisiana Joint Underwriters of the Audubon Ins. Co., defendant-appellant.

Before SAMUEL, REDMANN and BOUTALL, JJ.

BOUTALL, Judge.

The Jefferson Parish School Board brought suit against Rowley Co., Inc. under terms of a contract wherein Rowley was to furnish and install science equipment in West Jefferson High School. After the equipment was delivered, but before it was installed, a fire destroyed a portion of the equipment worth $36,148.15. The School Board seeks recovery of this amount alleging that Rowley has refused to replace the damaged science equipment at no cost to plaintiff, and that Rowley failed to provide any builder's risk and fire insurance, all as provided for in the contract between them. Alternatively, the School Board sues to recover the amount from Louisiana Joint Underwriters of the Audubon Insurance Company, the fire insurer of the School Board under a policy covering the buildings and contents of all of the schools in Jefferson Parish. Both defendants answered denying liability, and additionally Rowley Co., Inc. sought a judgment in reconventional demand against the School Board for the balance due it under the contract as well as for other equipment sold by it to the School Board unrelated to this matter, for which the School Board withheld payment. These sums withheld equal the amount sought by plaintiff.

Each of the three parties have filed motions for summary judgment, and all of the motions were taken up at the same time. The School Board sought summary judgment against both Rowley and Audubon; Rowley sought judgment against the School Board dismissing its suit and granting Rowley's reconventional demand; Audubon sought dismissal of the School Board's suit. The trial court granted summary judgment to the School Board against Audubon for the amount prayed, and also granted summary judgment to Rowley against the School Board dismissing plaintiff's suit and awarding Rowley the sum prayed for in reconventional demand. The motion for summary judgment (together with an exception of no right or cause of action on the same basis) of Audubon was dismissed. The decree does not make specific adjudication of the School Board's motion for summary judgment against Rowley although the Reasons for Judgment indicate that it was intended that that motion should be dismissed. Suspensive appeals were subsequently taken by the School Board and by Audubon.

Under the procedural posture in which this appeal reaches us, we cannot arrive at a final adjudication of the rights of the parties. Although we are informed by all of the parties that there is no dispute as to essential facts, we find a serious dispute as to essential facts in this record and conclude that summary judgment is not appropriate herein.

The undisputed facts are these. The Jefferson Parish School Board was in the process of making alterations at West Jefferson High School, and in accordance with these intentions advertised publicly for bids as required by R.S. 38:2211 for the furnishing and installation of certain science equipment specified for certain science laboratory classrooms. Both detailed and general specifications were provided. Three bids were received. The lowest was the Hamilton Manufacturing Company whose bid was rejected because it qualified the delivery dates required. The next lowest bid of Rowley was accepted. The bid of Rowley was as follows:

'BASE BID:

'For all Science Equipment, and Furnishings for West Jefferson High School, Complete, in accord with the DRAWINGS, SPECIFICATIONS, and CONTRACT DOCUMENTS for the LUMP SUM of Sixty-Nine thousand, eight hundred two and 00/100 DOLLARS ($69,802.00) Drexel as specified.

Although the contract documents furnished include a formal contract proposed to be signed, no contract was signed. Instead, the School Board issued a signed Purchase Order to Rowley containing the following inscriptions:

'Science Equipment and Furnishings as per bid of June 19, 1972. $69,802.00

*Completion of all work required between September 1, 1972 and September 15, 1972.'

Thereafter Rowley delivered the equipment and was in the process of installing the equipment in the school. On November 15, 1972, it forwarded its invoice of $52,820.00 to the School Board as its first request for payment on the contract. On November 17, 1972, there was a fire in the school, the cause of which is unknown, and some of the equipment furnished was damaged and destroyed. For some unexplained reason, the School Board later paid the invoice in question. This suit followed.

It is apparent that the plaintiff School Board is entitled to recover the amount of its loss, either from the defendant Rowley or from the defendant Audubon Insurance Company, or perhaps both. Audubon had in full force and effect a policy of fire insurance covering all of the contents of West Jefferson High School, as well as other schools, and if it is determined that the School Board is indeed the owner of the equipment delivered therein by Rowley, then Audubon must pay under its policy provisions. On the other hand, the contract documents require Rowley to bear the risk of loss.

The trial court accepted the contention of Rowley, and the alternate contention of the School Board, that the contract between Rowley and the School Board was a contract of sale, hence the title to the property had passed to the School Board upon its delivery by Rowley to the School Building. L.C.C. Art. 2456. However, we do not consider that the labeling of the agreement between the parties as that of a sale or that of a construction contract or other contract is the controlling issue between the parties. The controlling issue is that, whatever it may be called, if there was a binding contract between the parties, did that contract provide for risk of loss in the factual circumstances here?

It has been argued to us that the general law pertaining to sales provides that under the factual circumstances related above, the School Board became the owner and thus bore the risk of loss. Louisiana Civil Code Articles 2467, 2468, 2475, 2477, 2478, 1908; Hunt v. Suares, 9 La. 434 (1836); Vico Concrete Company, Inc. v. Antley, 283 So.2d 830 (La.App.2d Cir. 1973). As opposed to this the appellants contend that this is a contract of construction and thus governed under the provisions of L.C.C. Arts. 2756, 2757, 2758, with the risk of loss being borne by the contractor. Kegler's, Inc. v. Levy, 239 So.2d 450 (La.App.4th Cir. 1970). See also S & W Investment Co. v. Otis W. Sharp & Son, Inc., 247 La. 158, 170 So.2d 360 (1964). We do not attempt in our consideration to decide which of these two principles should be applied here because of the procedural status.

This matter comes before us on appeal from motion for summary judgment. While the facts mentioned above are not in dispute and would bring us to a consideration of the legal principles involved herein, we may not do so because we find there is a serious issue of contested fact herein and we cannot reach the consideration necessary to such a determination.

The record herein consists mainly of depositions of various witnesses produced by the parties. These depositions were taken for purposes of discovery and consist of examination by all of the attorneys, and it is noted that all objections except those as to form of the questions asked were reserved until the time of the trial of the cause. Basically the witnesses of the School Board testified that the proposed project consisted not only of a sale of certain equipment, but also the installation of that equipment in a particular place and in a particular fashion as specified in the specifications. The project was advertised under the public bidding law (R.S. 38:2211) and it was proposed that a contract be entered into between the successful bidder and the School Board. The proposal upon which the bids were made consisted of general conditions, supplemental general conditions and precise specifications. The bidder was required to consider all of these documents in its bid and perform in accordance therewith. These documents were introduced into evidence in the deposition subject to the objections of Rowley.

Rowley's position is, and the testimony elicited in its behalf shows, that the School Board issued only a purchase agreement. Rowley's General Manager testified that because of this failure to enter into a formal contract, because of past dealings with the School Board in similar fashion, and because of failure to insist on performance bond and other requirements, the School Board waived the requirements imposed upon Rowley by the contract documents. The School Board representative testified that no waiver of these documents was intended or made, but that the School Board considered that the simple awarding of the bid to Rowley by the School Board's acceptance and issuance of a purchase order signed by one of its representatives was sufficient to form a binding contract under the provisions of R.S. 38:2213 and none of these conditions were waived.

The conditions which are most pertinent in the documents are as follows:

'GENERAL CONDITIONS, SECTION 13

'13. PROTECTION OF WORK AND PROPERTY-EMERGENCY:

'Contractor shall at all times safely guard Owner's property from injury or...

To continue reading

Request your trial
17 cases
  • Nunez v. Superior Oil Co.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (5th Circuit)
    • 12 Mayo 1978
    ...1965, 380 U.S. 460, 85 S.Ct. 1136, 14 L.Ed.2d 8. For the comparable standards under Louisiana law, see Jefferson Parish School Board v. Rowley Co., Inc., La.App.1974, 305 So.2d 658; Moreaux v. American Mutual Ins. Co., La.App.1974, 302 So.2d 686; Lachney v. Employers Cas. Co., La.App.1973, ......
  • 95-2388 La.App. 4 Cir. 8/21/96, Gordon v. Southern United Fire Ins. Co.
    • United States
    • Court of Appeal of Louisiana (US)
    • 21 Agosto 1996
    ...... Dibos v. Bill Watson Ford, Inc., 622 So.2d 677, 680 (La.App. 4 Cir.1993); Vermilion Corp. ... Jefferson Parish School Bd. v. Rowley Co., Inc., 305 So.2d 658, 663 ......
  • 95-2766 La.App. 4 Cir. 5/29/96, Osborne v. Vulcan Foundry, Inc.
    • United States
    • Court of Appeal of Louisiana (US)
    • 29 Mayo 1996
    ...... Jefferson Parish School Bd. v. Rowley Co., Inc., 305 So.2d 658, 663 ......
  • Hare v. Ganaway Const. Co.
    • United States
    • Court of Appeal of Louisiana (US)
    • 14 Diciembre 1988
    ...... Mayer v. Valentine Sugars, Inc., 444 So.2d 618 (La.1984). Plaintiff's petition alleges ...2d Cir.1983). See also Jefferson...2d Cir.1983). See also Jefferson Parish...2d Cir.1983). See also Jefferson Parish School... See also Jefferson Parish School Bd. v. Rowley......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT