John Day Co. v. Alvine & Associates, Inc.

CourtNebraska Court of Appeals
Writing for the CourtCONNOLLY
CitationJohn Day Co. v. Alvine & Associates, Inc., 510 N.W.2d 462, 1 Neb.App. 954 (Neb. App. 1993)
Decision Date06 July 1993
Docket NumberNo. A-91-1187,A-91-1187
PartiesJOHN DAY COMPANY, a Nebraska Corporation, Appellant, v. ALVINE & ASSOCIATES, INC., a Nebraska Corporation, Appellee.

James D. Buser, of Gaines, Mullen, Pansing & Hogan, Omaha, for appellant.

Thomas J. Guilfoyle, of Frost, Meyers, Guilfoyle & Govier, Omaha, for appellee.

CONNOLLY, HANNON, and MILLER-LERMAN, JJ.

CONNOLLY, Judge.

This appeal arises from the dismissal of the petition of the John Day Company (John Day), the appellant, seeking damages in contract and in tort from Alvine and Associates, Inc. (Alvine), the appellee. John Day had contracted with an architectural firm for the construction of a building, and the architectural firm had subcontracted with Alvine for mechanical engineering design services. John Day sued Alvine for damages resulting from a problem that developed after completion of the building in the heating, ventilating, and air-conditioning system designed by Alvine. John Day sued in contract on the theory that it was a third-party beneficiary of the subcontract between the architectural firm and Alvine, and in tort on the theory that it was a third party to whom Alvine owed, and breached, a duty of care. The trial court sustained Alvine's demurrer on grounds that John Day had failed to state a cause of action in either contract or tort. We affirm.

I. FACTS

John Day contracted with How-Nelsen Associates (How-Nelsen) to provide architectural services for the design and construction of John Day's building at 6263 Abbott Drive, Omaha, Douglas County, Nebraska. How-Nelsen subcontracted with Alvine to provide mechanical engineering design services in connection with the construction of the John Day building. Alvine prepared the specifications for the design and construction of the building's heating, ventilating, and air-conditioning system (HVAC system), a "once through cooling system" in which well water would be pumped from the source, circulated through the system, and then injected into the ground after one pass through the system. Alvine's design specifications called for the use of carbon steel piping to carry the well water through the system.

Almost 1 year after the completion of the John Day building, it was discovered that the carbon steel pipes used in the HVAC system were corroding. A test of the well water used in the system revealed that the water had an excessively high chloride content. A metallurgical consulting service determined that the high chloride content of the well water was a major factor contributing to the corrosion of the entire carbon steel piping system. On the recommendation of the consulting service, John Day replaced the carbon steel piping with heavy plastic piping at a cost of $22,828.83.

John Day filed a petition claiming relief in both contract and tort. In claiming breach of contract, John Day alleged that it was the third-party beneficiary of the subcontract between How-Nelsen and Alvine and that Alvine's failure to test the well water for corrosive agents before ordering the use of carbon steel piping constituted a breach of its duty to John Day to provide proper, workmanlike, and professional mechanical engineering design services. In claiming professional negligence, the term used in the petition, John Day alleged that the failure of Alvine, a professional mechanical engineering firm, to conduct chemical tests of the well water in the process of designing the HVAC system constituted a breach of its duty to John Day to use the skill and knowledge ordinarily possessed by other professional mechanical engineers in good standing in Douglas County. John Day sought $22,828.83 in damages, plus "other damages," interest, attorney fees, and costs.

Alvine filed a demurrer in which it asserted that John Day had failed to state a cause of action because Alvine was not in privity of contract with John Day and did not owe John Day any legal duty.

The order of the trial court stated that

both Counts are based upon negligence: Count I is negligent performance of the contract, and Count II is [a] straight negligence action. Since there is no privity [of] contract, there is no duty on the part of [Alvine] to [John Day]. [John Day's] petition does not state a cause of action against [Alvine], and therefore [John Day's] petition should be dismissed.

The trial court sustained Alvine's demurrer and dismissed John Day's petition.

II. ASSIGNMENTS OF ERROR

John Day assigns two errors which we summarize as follows: (1) The trial court erred in holding that both of John Day's claims against Alvine were based on negligence, and (2) the trial court erred in holding that under a theory of professional negligence, a duty of care ran from Alvine to John Day only if there was privity of contract between those two parties.

III. STANDARD OF REVIEW

In ruling on a demurrer, the petition is to be construed liberally; if as so construed the petition states a cause of action, the demurrer is to be overruled. Matheson v. Stork, 239 Neb. 547, 477 N.W.2d 156 (1991).

IV. ANALYSIS

" 'If from the facts stated in the petition it appears that the plaintiff is entitled to any relief, a general demurrer will not lie.' " Central Nebraska Public Power and Irrigation District v. Walston, 140 Neb. 190, 202, 299 N.W. 609, 615 (1941). "[W]hen a petition contains more than one count, and a general demurrer is directed against the entire pleading, and is not limited to a particular count, if any count states a cause of action, such demurrer must be overruled." Alexander v. Thacker, 30 Neb. 614, 618, 46 N.W. 825, 826 (1890). Thus, if either of John Day's claims for relief stated a cause of action, then the trial court erred in sustaining Alvine's demurrer.

1. THIRD-PARTY BENEFICIARY

In finding that both of John Day's claims for relief sounded in tort, the trial court rejected John Day's argument that it was a third-party beneficiary to the subcontract between How-Nelsen and Alvine.

In School District v. Thomas, 51 Neb. 740, 71 N.W. 731 (1897), the Nebraska Supreme Court was confronted with the following scenario: The school district of Beatrice hired W.C. Smith to build two schoolhouses. Smith abandoned the contract and absconded. Completion of the project was assumed by his sureties. The project was completed, and Thomas, a subcontractor on the project, asserted that he was a third-party beneficiary of the contract between the school district and the general contractor. Accordingly, he sued the school district for sums due him for his work on the project. The Supreme Court rejected Thomas' argument:

It is also argued that the rule "Where a party makes a promise to another for the benefit of a third person, such third person may avail himself of the promise and bring an action thereon ..." is applicable and may be invoked by [Thomas] as against the school district. There were no portions or elements of the contract between Smith, the original contractor, and the district which ... contain any promise by the district, made for the benefit of the subcontractor, on which he would be entitled to institute a suit against the district; hence the doctrine to which reference has been made is of no force here.

Id. at 743, 71 N.W. at 732.

The Supreme Court recently reiterated and elaborated on the proposition that one is a third-party beneficiary of a contract only if the other parties entered into the contract for the purpose of benefiting the third party. In order for those not named as parties to the contract to recover thereunder as third-party beneficiaries, it must appear by express stipulation or by reasonable intendment that the rights and interests of such unnamed parties were contemplated and provision was made for them. See Properties Inv. Group v. Applied Communications, 242 Neb. 464, 495 N.W.2d 483 (1993). The rights of a third-party beneficiary depend upon, and are measured by, the terms of the contract between the promisor and the promisee. Id. The right of a third party benefited by a contract to sue thereon rests upon the liability of the promisor, which must affirmatively appear from the language of the instrument when properly interpreted or construed, and liability so appearing cannot be extended or enlarged on the ground alone that the situation and circumstances of the parties justify or demand...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
6 cases
  • Hawkins Constr. Co. v. Peterson Contractors, Inc.
    • United States
    • U.S. District Court — District of Nebraska
    • September 4, 2013
    ...are not liable in negligence to third parties with whom they are not in privity of contract.” John Day Co. v. Alvine & Assoc., Inc., 1 Neb.App. 954, 961, 510 N.W.2d 462, 466 (1993). There was a layer of subcontractors between Hawkins and GIE. Thus, argues GIE, there is no basis upon which H......
  • John v. John
    • United States
    • Nebraska Court of Appeals
    • July 6, 1993
  • Missionary Benedictine Sisters, Inc. v. Hoffman, LLC
    • United States
    • U.S. District Court — District of Nebraska
    • May 4, 2015
    ...are not liable in negligence to third parties with whom they are not in privity of contract." John Day Co. v. Alvine & Associates, Inc., 510 N.W.2d 462, 466 (Neb.App. 1993). Robinson does not claim to be a "professional." Robinson next states that "a party cannot seek indemnity from another......
  • Jisa Farms, Inc. v. Farmland Industries, Inc., 4:99CV3294 (D. Neb. 1/2/2001), 4:99CV3294
    • United States
    • U.S. District Court — District of Nebraska
    • January 2, 2001
    ...A party cannot judicially admit conclusions of law in the pleadings-pleadings admit only facts"). But see John Day Co. v. Alvine & Assocs., Inc., 510 N.W.2d 462, 466 (Neb. 1993) (considering the plaintiff's admission that the defendant was a professional in determining that a mechanical eng......
  • Get Started for Free
1 books & journal articles
  • Section 11.15 Definition
    • United States
    • The Missouri Bar Practice Books Construction Law Deskbook Chapter 11 Liability of Design Professionals
    • Invalid date
    ...Constr. Co. v. Henningson, Durham & Richardson, Inc., 716 F. Supp. 1466 (N.D. Ga. 1989)) ? Nebraska ( John Day Co. v. Alvine & Assocs., 510 N.W.2d 462 (Neb. App. 1993)) ? New York ( Briar Contracting Corp. v. City of New York, 550 N.Y.S.2d 717 (N.Y. App. 1989)) ? Ohio ( Floor Craft Floor Co......