Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co.

Decision Date13 November 1992
Docket NumberNo. 1-91-2538,1-91-2538
Citation606 N.E.2d 463,238 Ill.App.3d 550,179 Ill.Dec. 631
Parties, 179 Ill.Dec. 631 JOSEPH T. RYERSON & SON, INC., a Delaware Corporation, Plaintiff-Appellant, v. MANULIFE REAL ESTATE COMPANY and E.W. Corrigan Construction Company, Defendants-Appellees (Crescent Corporation, Ford Motor Company and Unknown Owners and Record Claimants, Defendants).
CourtUnited States Appellate Court of Illinois

Burke, Wilson & McIlvaine, Chicago (Leonard S. Shifflett and Christopher C. Dickinson, of counsel), for plaintiff-appellant.

Rosenthal and Schanfield, P.C., Chicago (James M. Dash and Stephen P. Kikoler, of counsel), for defendants-appellees.

Presiding Justice EGAN delivered the opinion of the court:

This court reversed a judgment in favor of the plaintiff, Joseph T. Ryerson and Son, Inc. (Ryerson) on the ground that the plaintiff had failed to name a necessary party as a defendant. (Joseph T. Ryerson and Son, Inc. v. Manulife Real Estate Co. (1991), 207 Ill.App.3d 622, 152 Ill.Dec. 610, 566 N.E.2d 297.) The plaintiff then filed a complaint in the circuit court naming the same defendants that were named in the original complaint and the person we had said was a necessary party. The trial judge granted the defendant's motion to dismiss the complaint on the ground that our reversal was res judicata of the plaintiff's new complaint. The plaintiff contends that our reversal was not a final order which decided the case on the merits.

The defendant, Manulife Real Estate Company (Manulife) contracted with the defendant, E.W. Corrigan Construction Company (Corrigan) to act as a general contractor on the construction of a new office building on land owned by Manulife. Corrigan subcontracted out the fabrication and installation of a curtain wall to Crescent Corporation (Crescent). Crescent entered into a contract with Ryerson to obtain the necessary materials for carrying out the terms of Crescent's subcontract with Corrigan.

After a period of time, Crescent discontinued work under its subcontract with Corrigan and consequently stopped obtaining materials from Ryerson. Ryerson was never paid in full and claimed that Corrigan and/or Crescent owed over $55,000 for the materials which were used in the project.

On November 3, 1986, Ryerson filed an action to foreclose a mechanic's lien against Manulife and Corrigan, but did not join Crescent as a party. Both Manulife and Corrigan moved to strike the plaintiff's complaint alleging that Ryerson failed to join Crescent, a necessary party to such an action. Ryerson opposed the motion, and the trial judge denied it. The judge later granted Ryerson's motion for summary judgment against the defendants jointly and awarded Ryerson over $47,000. Manulife and Corrigan appealed.

This court reversed the order of summary judgment; the basis of the reversal was that Ryerson had failed to name Crescent as a party defendant.

Ryerson filed a petition for rehearing in this court alleging that count II of the complaint was an action for a money judgment against the defendants and, therefore, did not require that Crescent be named a necessary party. The petition further asked that the case be remanded to the circuit court for a hearing on the question of whether Crescent had become bankrupt. Ryerson did not ask for a clarification of the meaning of our order reversing the judgment.

We denied the petition for rehearing pointing out that count II specifically alleged that the plaintiff "claims a lien" and was not a claim for money damages pursuant to section 28 of the Mechanics' Lien Act. (Ill.Rev.Stat.1989, ch. 82, par. 28.) We also pointed out that section 28 provides that the plaintiff may either file a claim for a lien or file a complaint and enforce the lien or he may sue the owner and contractor jointly and acquire a personal judgment. Ryerson did not seek leave to appeal to the supreme court.

While the petition for rehearing was pending in this court, Ryerson filed a new complaint in the circuit court and named Crescent as a party along with Manulife and Corrigan. The new complaint was almost identical to the complaint in the original action, but included an additional count that sought recovery from Crescent and a count seeking money damages from Manulife and Corrigan.

Manulife and Corrigan moved for summary judgment, arguing that the new complaint was barred by res judicata. The trial judge granted the summary judgment motion, holding that this court's prior decision barred Ryerson's new claim.

It is necessary that we address the issues as they have been presented to us. But before we do, we wish to point out what has not been made an issue by Ryerson. Our reversal without remand of the order granting summary judgment was based on our holding that Ryerson could never recover on the complaint before the court as pleaded. (Cf. North Pier Terminal Co. v. Hoskins Coal and Dock Corp. (1949), 402 Ill. 192, 83 N.E.2d 748.) Ryerson did not argue in the trial court and does not argue in this court that our mandate ordering reversal was vague (Cf. Muhlke v. Muhlke (1918), 285 Ill. 325, 120 N.E. 770), and it does not argue that it should have been permitted to file an amended complaint. Indeed, Ryerson says that "no further proceedings are possible on the initial complaint."

After our reversal, Ryerson filed the complaint that is before us. The defendants filed a motion to dismiss pursuant to section 2-619 under the Code of Civil Procedure (Ill.Rev.Stat.1991, ch. 110, par. 2-619(a)) on the ground that the first complaint was still pending. We repeat that Ryerson never sought leave to amend the first complaint to name Crescent as an additional party.

We turn now to the issues that have been presented to us. Ryerson argues that this court's reversal of the summary judgment in its favor was not a final judgment and was not on the merits.

To establish res judicata a party must show: (1) that the former adjudication resulted in a final judgment on the merits; (2) that the former and current adjudication was between the same parties; (3) that the former adjudication involved the same cause of action and the same subject matter as the current case; and (4) that a court of competent jurisdiction rendered the first judgment. People ex rel. Scott v. Chicago Park District (1976), 66 Ill.2d 65, 4 Ill.Dec. 660, 360 N.E.2d 773; Best Coin-Op, Inc. v. Paul F. Ilg Supply Co. (1989), 189 Ill.App.3d 638, 136 Ill.Dec. 957, 545 N.E.2d 481.

Ryerson's entire claim of lack of finality is based on its interpretation of section 13-217 of the Code of Civil Procedure, which provides as follows:

"In the actions specified in Article XIII of this Act or any other act or contract where the time for commencing an action is limited, if judgment is entered for the plaintiff but reversed on appeal, * * * the plaintiff * * * may commence a new action within one year or within the remaining period of limitation, whichever is greater, after such judgment is reversed * * *." Ill.Rev.Stat.1989, ch. 110, par. 13-217.

Ryerson's argument is that our order was not final because section 13-217 grants it the absolute right to refile. Relief under section 13-217, however, is not available if the underlying case is decided on the merits. (Suslick v. Rothschild Securities Corp. (1989), 128 Ill.2d 314, 131 Ill.Dec. 178, 538 N.E.2d 553; Murphy v. Giardina (1979), 78 Ill.App.3d 896, 34 Ill.Dec. 173, 397 N.E.2d 845, aff'd (1980), 82 Ill.2d 529, 45 Ill.Dec. 921, 413 N.E.2d 399) (predecessor of section 13-217, sec. 24a of the Limitations Act, did not authorize the refiling of an action where the complaint in question was dismissed on the merits).)

Ryerson's argument, in essence, is that dismissal of a complaint for failure to name a necessary party is not an adjudication on the merits. Ryerson's argument begs the question, which is whether dismissal for failure to name a necessary party is, in fact, an adjudication on the merits. In support of its argument Ryerson refers to Supreme Court Rule 273 (134 Ill.2d R. 273):

"Unless the order of dismissal or a statute of this State otherwise specifies, an involuntary dismissal of an action, other than a dismissal for lack of jurisdiction, for improper venue, or for failure to join an indispensable party, operates as an adjudication upon the merits."

Ryerson is correct in stating that as a general rule the failure to join an indispensable party is not considered an adjudication on the merits under Rule 273. (In re Busse (1989), 183 Ill.App.3d 682, 132 Ill.Dec. 13, 539 N.E.2d 323.) The issue now becomes whether a statute of this state has specified that failure to join an indispensable party operates as an adjudication upon the merits.

Section 11 of the Mechanics' Lien Act (Ill.Rev.Stat.1989, ch. 82, par. 11) provides:

"The plaintiff shall make all parties interested, of whose interest he is notified or has knowledge, parties defendant, and summons shall issue and service thereof be had as in other civil actions; * * * and his failure to so act with regard to summons or notice shall be ground for judgment against him as upon the merits." (Emphasis added.)

We judge that the legislature has provided that a dismissal for failure to name a necessary party in a mechanics lien foreclosure action is an adjudication on the merits.

Ryerson relies principally on Kutnick v. Grant (1976), 65 Ill.2d 177, 2 Ill.Dec. 313, 357 N.E.2d 480, and O'Reilly v. Gerber (1981), 95 Ill.App.3d 947, 51 Ill.Dec. 11, 420 N.E.2d 425. In Kutnick a trial judge dismissed a case for want of prosecution; the plaintiff refiled; and another judge dismissed the refiled complaint holding that the first dismissal was an adjudication on the merits, relying on Rule 273. The predecessor act to section 13-217 provided that when an action is dismissed for want of prosecution the plaintiff may commence an action within one year. The defendant argued that the predecessor act was not a statute that "otherwise...

To continue reading

Request your trial
7 cases
  • In re Leigh
    • United States
    • United States Bankruptcy Courts. Seventh Circuit. U.S. Bankruptcy Court — Northern District of Illinois
    • January 31, 1994
    ...show what was determined by the prior judgment. Welch, 907 F.2d at 720; Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co., 238 Ill.App.3d 550, 553, 179 Ill.Dec. 631, 633, 606 N.E.2d 463, 465 (1st Dist.1992). It is undisputed that the Debtor and the Bank were both named parties in th......
  • Zurich Ins. Co. v. Amcast Indus. Corp.
    • United States
    • United States Appellate Court of Illinois
    • December 19, 2000
    ... ... Joseph T. Ryerson & Son v. Manulife Real Estate Company, ... decision of our supreme court in River Park, Inc. v. City of Highland Park, 184 Ill.2d 290, 234 ... ...
  • EFCO Corp. v. U.W. Marx, Inc.
    • United States
    • U.S. Court of Appeals — Second Circuit
    • September 3, 1997
    ...Place, Ltd., No. 92 C 1692, 1993 WL 462840, at * 6-7 (N.D.Ill. Nov.8, 1993); Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co., 238 Ill.App.3d 550, 179 Ill.Dec. 631, 634-35, 606 N.E.2d 463, 466-67 (1992); Thorleif Larsen and Son, Inc. v. PPG Indus., Inc., 177 Ill.App.3d 656, 126 Ill......
  • Heller Financial, Inc. v. Johns-Byrne Co.
    • United States
    • United States Appellate Court of Illinois
    • June 28, 1994
    ... ... deprived of jurisdiction over the real issues arising from the notice. Jewel Companies ... 788, 594 N.E.2d 1308; Estate of Healy v. Tierney (1985), 137 Ill.App.3d 406, ... (See Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT