Kanmak Mills v. Society Brand Hat Company
Decision Date | 03 August 1956 |
Docket Number | 15438.,No. 15437,15437 |
Parties | KANMAK MILLS, Inc., Appellant, v. SOCIETY BRAND HAT COMPANY, Appellee. SOCIETY BRAND HAT COMPANY, Appellant, v. KANMAK MILLS, Inc., Appellee. |
Court | U.S. Court of Appeals — Eighth Circuit |
Marion S. Francis, St. Louis, Mo. (George W. Simpkins, Bryan, Cave, McPheeters & McRoberts, St. Louis, Mo., and Jerome G. Rosenhaus, New York City, were with him on the brief), for Kanmak Mills, Inc.
Murray Steinberg, St. Louis, Mo. (Richard Marx, St. Louis, Mo., was with him on the brief), for Society Brand Hat Co.
Before SANBORN, WOODROUGH and VOGEL, Circuit Judges.
These two appeals are taken from a final order of the District Court which affirmed a part and vacated and remanded to the arbitrators for rehearing a part of an arbitration award growing out of seven contracts for delivery of cloth in interstate commerce between Kanmak Mills, Inc. (Kanmak), a corporation engaged in New York in making and selling textile piece goods, as seller and Society Brand Hat Company (Society), a manufacturer of men's trousers in St. Louis, as buyer. The contracts were accepted orders for cloth of which six, numbered 139, 140, 141, 143, 144 and 156, for an aggregate of about 66,500 yards, were dated November 17, 1947, and one numbered 193 was dated April 28, 1948, and called for 100,000 yards. None of the contracts was carried out and bitter disputes ensued.
Each of the orders contained the following agreement to arbitrate printed on the back:
On delivery of 18,572 yards of cloth in the first shipment under the 1947 orders, Society examined the cloth and claimed it was in bad condition. Upon receipt of the claim, the seller (Kanmak) made demand on Society, as provided in the arbitration agreement, that Society forward such merchandise to the Mutual Adjustment Bureau of the Cloth and Garment Trades named in the contract, and Society complied. Mutual duly examined the goods and made report of its findings to Kanmak which forwarded the report to Society. Mutual found that only 3,9024/8 yards were normal goods and that 10,1252/8 yards were seconds.
On May 1, 1948, after the contract numbered 193 for 100,000 yards had been entered into on April 28, 1948, Society wrote Kanmak:
Kanmak replied by letter of May 3, 1948, that it was accepting and effecting cancellation of the remaining unshipped portions of all orders on file with them with the exception of contract 193.
Contract No. 193 for 100,000 yards of cloth provided for delivery of 20,000 yards monthly, May through September 1948, and Society was required and did pay $10,000 in advance, which was to be applied on the very last shipment, under the contract. The contract contained provision that shipments were to be R.O.M. (run of mill). It contained no specific reference to "free from foreign ends" but it specified percentages as to content of cloth, 50% cotton, 25% acetate, 25% wool.
On June 28, 1948, Society telegraphed Kanmak to ship 20,000 yards under contract No. 193 "free from foreign ends," to which Kanmak replied:
On July 6, 1948, Society telegraphed Kanmak that the materials sold to it on Contract 193 were warranted to be free from foreign ends; that tests were to have been made to eliminate pieces with foreign ends; that it would accept only goods free from foreign ends, and it insisted that 20,000 yards be shipped to its dyers "today" or it would purchase similar goods on open market and hold Kanmak for loss which was not speculative but probable. Notice was included that Society wished to refer entire matter to arbitration immediately. Kanmak wired on the same day maintaining its position that it would ship R.O.M., but not free from foreign ends. It stated it would submit to arbitration forthwith.
On the next day (July 7, 1948), Society wired Kanmak:
Kanmak, by its attorney, apparently answering the foregoing telegram, wrote Society on September 24, 1948:
Thereafter, on November 22, 1949, Society filed its Demand for Arbitration of all matters in dispute between it and Kanmak with the American Arbitration Association named in the contracts and referred to in the foregoing letter, and notice was given to Kanmak.
The Demand described each of the seven written contracts entered into between the parties with particularity, giving the kind and amount of cloth called for, when it was to be delivered and the terms of the sale. Also, the number of yards of goods that had been delivered on those of the contracts upon which some delivery was made, and the failure of Kanmak on demand to deliver according to the contracts. Society also alleged in the Demand that samples of the goods it ordered were delivered to it by Kanmak for the fabrication of sample trousers, and Society obtained firm orders and promised delivery based on the delivery dates of the contracts. On Kanmak's failure to deliver, Society attempted to obtain other piece goods to substitute, but was unable to do so, and as the result of Kanmak's failure to deliver the 165,000 yards of cloth as provided in the contracts, Society lost the profit on its sale. That 18,573¼ yards received from Kanmak was not according to contract and was unusable for the purpose sold. That as Society had deposited $10,000 in advance upon contract 193, on which Kanmak refused to deliver any goods, recovery of that amount was also sought. Society claimed damages from Kanmak in such sums as the arbitrators of the American Arbitration Association shall determine due it for the failure of Kanmak to make delivery of the piece goods ordered, and for further damages for delivery of piece goods not in accordance with samples, and for the $10,000 received and...
To continue reading
Request your trial-
Battle v. General Cellulose Co.
...111, 47 A.L.R.2d 1331 (6 Cir., 1953), certiorari denied, 346 U.S. 887, 74 S.Ct. 144, 98 L.Ed. 392 (1953); Kanmak Mills, Inc., v. Society Brand Hat Co., 236 F.2d 240 (8 Cir., 1956). See also International Brotherhood of Teamsters, etc. v. Shapiro, 138 Conn. 57, 82 A.2d 345 The New York statu......
-
Intern. Broth. v. Hope Elec. Corp.
...is available after-the-fact to a party who responds to a call to arbitrate with silence and inaction. See Kanmak Mills, Inc. v. Society Brand Hat Co., 236 F.2d 240, 252 (8th Cir.1956). IV. (C) Arbitrators' Turning to the merits of the substantive jurisdictional challenges, we first address ......
-
AMALGAMATED MEAT CUTTERS, ETC. v. Penobscot Poultry Co.
...F.2d 111, 47 A.L.R. 2d 1331 (6th Cir.1953), cert. denied, 346 U.S. 887, 74 S.Ct. 144, 98 L.Ed. 392 (1953); Kanmak Mills, Inc. v. Society Brand Hat Co., 236 F.2d 240 (8th Cir. 1956); Standard Magnesium Corp. v. Fuchs, 251 F.2d 455 (10th Cir.1957). In each of these cases the defendant had ref......
-
Corallo v. Merrick Cent. Carburetor, Inc.
...objecting party's absence. See Standard Magnesium Corp. v. Fuchs, 251 F.2d 455, 456-58 (10th Cir.1957); Kanmak Mills, Inc. v. Society Brand Hat Co., 236 F.2d 240, 250-52 (8th Cir.1956); Kentucky River Mills v. Jackson, 206 F.2d 111, 116-120 (6th Cir.), cert. denied, 346 U.S. 887, 74 S.Ct. 1......