Keith v. River Consulting, Inc.

Decision Date20 June 2005
Docket NumberNo. 4001.,4001.
Citation618 S.E.2d 302
PartiesHeyward O. KEITH, Plaintiff, v. RIVER CONSULTING, INC., A.J. Concrete Pumping, LLC, Edward Helman and Schwing America, Inc., Defendants. and A.J. Concrete Pumping, LLC, Appellant, v. Hightower Construction Company, Inc., Respondent.
CourtSouth Carolina Supreme Court

Timothy Alan Domin, of Charleston, for Appellant.

Michael S. Fahnestock, of Charleston, for Respondent.

WILLIAMS, J.:

A.J. Concrete Pumping, LLC (A.J.Concrete), appeals the grant of summary judgment to Hightower Construction Company, Inc. (Hightower Construction), arguing the circuit court erred in finding the case presented no factual issue for determination by a jury. A.J. Concrete also contends the circuit court erred in its alternative conclusion that the indemnification clause at issue was void as against public policy. We reverse and remand.

FACTS / PROCEDURAL HISTORY

Hightower Construction was hired to erect a building foundation in Georgetown, South Carolina. A portion of the construction project required the pouring of concrete into a large mold. To complete this task, Daniel Premo, the job superintendent and foreman, entered into an oral contract with A.J. Concrete on behalf of Hightower Construction for the lease of a concrete truck and boom pump operator to pump concrete into the foundation mold. Although this was the first time Hightower Construction contracted with A.J. Concrete, it previously leased a concrete pump truck from A.J. Concrete II, A.J. Concrete's sister company. Premo, while employed elsewhere, contracted with A.J. Concrete under similar circumstances on as many as thirty prior occasions.

On December 17, 1998, A.J. Concrete's truck and boom operator, Eddy Helman, arrived at the site. According to Helman, he and Premo discussed the presence of overhead electrical power lines before the pour began. Helman believed the safest way to conduct the job was to situate the boom pump in the closest safe position to the power lines and proceed with the pour by gradually moving away from the lines. After Helman situated the boom pump accordingly and poured about a yard of concrete, Premo motioned angrily at him to move the boom into the position farthest from the lines. This required that Helman move the boom pump closer and closer to the power lines during the course of the pour. Helman stated at his deposition that, although troubled by the change, he did not vocally object because Premo had previously stated that he and his workers would "keep an eye on the lines." He also stated that he understood his duty to be to "perform the concrete pump job to the requirements of my customer."

Premo initially stood inside the mold and guided the nozzle of the concrete pump while Helman guided the supporting boom with a radio control device. Premo later left to see to other business, assigning his task to Heyward Keith, another employee of Hightower Construction. Shortly thereafter, Keith directed Helman to move the boom. The boom came in contact with the nearby power lines, resulting in Keith being seriously injured from an electrical shock.

After Keith received the requisite medical attention, Helman and other Hightower Construction employees completed the job. Helman then presented Premo with a "job ticket," which listed the work performed, the applicable rate, and the amount owed for the job. The back of the ticket contained various contractual terms including terms of payment, limitation of warranties, and the following clause:

INDEMNIFICATION AND RISK OF LOSS: Lessor and Lessee agree that the leased equipment and all persons operating such equipment, including Lessor's employees, will be under Lessee's exclusive jurisdiction, supervision, and control during the time such equipment and operators are on Lessee's job site, the Lessee agrees to indemnify Lessor against all claims, actions, proceedings, costs, damages, and liabilities arising in any manner out of, connected with, or resulting from the operation or handling of the leased equipment on Lessee's job site, including without limitation, any injury, disability or death of workmen or other persons and any loss or damage to property, whether the liability, loss or damage is caused by or arises out of the negligence of Lessor's employees or otherwise.

Nothing on the front of the job ticket directs the reader to the back of the ticket. Premo signed the job ticket and later presented a copy to Hightower Construction's office staff. Hightower Construction paid the full amount A.J. Concrete charged for the job.

After successfully pursuing a workers' compensation claim against Hightower Construction, Keith commenced a civil lawsuit against several defendants, including A.J. Concrete, alleging that their negligence caused his injuries. A.J. Concrete filed a third-party complaint against Hightower Construction, asserting contractual indemnity as reflected by the terms listed on the back of the job ticket. Both parties to the third-party claim filed motions for summary judgment. Following a hearing on the motions, the circuit court granted Hightower Construction's motion, concluding that, as a matter of law, the indemnification clause was not part of the contract and, alternatively, was unenforceable because it was overly broad and violated public policy. This appeal followed.

STANDARD OF REVIEW

"The purpose of summary judgment is to expedite the disposition of cases which do not require the services of a fact finder." George v. Fabri, 345 S.C. 440, 452, 548 S.E.2d 868, 874 (2001). When reviewing the grant of a summary judgment motion, this court applies the same standard which governs the trial court under Rule 56(c), SCRCP: summary judgment is proper when there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Fleming v. Rose, 350 S.C. 488, 493, 567 S.E.2d 857, 860 (2002).

In determining whether a triable issue of fact exists, the evidence and all factual inferences drawn from it must be viewed in a light most favorable to the nonmoving party. Sauner v. Pub. Serv. Auth., 354 S.C. 397, 404, 581 S.E.2d 161, 165 (2003). Even if there is no dispute as to evidentiary facts, but only as to the conclusions or inferences to be drawn from them, summary judgment should be denied. Baugus v. Wessinger, 303 S.C. 412, 415, 401 S.E.2d 169, 171 (1991). Summary judgment is not appropriate when further inquiry into the facts of the case is desirable to clarify the application of law. Tupper v. Dorchester County, 326 S.C. 318, 325, 487 S.E.2d 187, 191 (1997).

LAW / ANALYSIS
I. The Indemnification Clause as Part of the Contract

The circuit court found, as a matter of law, that the indemnification clause was not part of the contract because 1) the undisputed facts fail to reflect a meeting of the minds between the parties and 2) the terms on the back of the job ticket are unenforceable due to lack of consideration. We address each finding in turn.

Meeting of the Minds

The circuit court's approval of Hightower Construction's motion for summary judgment was based largely on its finding that A.J. Concrete presented no evidence that the presence of the indemnification clause was "made known or ... from all the circumstances, should [have been] known" by the parties to the contract. Player v. Chandler, 299 S.C. 101, 105, 382 S.E.2d 891, 894 (1989). We disagree and find that A.J. Concrete presented a question of fact for determination by a jury.

This case concerns an oral contract to provide concrete pumping services. Although the disputed term of the contract was presented on the back of a job ticket and signed by Hightower Construction after completion of the pour, A.J. Concrete argues that the lessee's supervisory control and accompanying lessor indemnification are so common in the trade that they were understood by the parties upon entry into the contractual relationship.

The main concern of the court, when interpreting an oral contract, is to give effect to the intention of the parties. Columbia East Assoc. v. Bi-Lo, Inc., 299 S.C. 515, 519, 386 S.E.2d 259, 261 (1989). "The courts, in attempting to ascertain this intention, will endeavor to determine the situation of the parties, as well as their purposes, at the time the contract was entered." Id. When a contract is silent as to a particular matter, parol evidence is admissible to reveal the parties' true intent. Id. To this end, "it is necessary for enforceability that the essentials of the contract be agreed upon but all need not be expressed. They may be implied from custom and usual forms [trade usage] and former course of dealing." Carolina Aviation, Inc. v. Glens Falls Ins. Co., 214 S.C. 222, 230, 51 S.E.2d 757, 761 (1949) (emphasis added). While the use of uniform trade practices to reflect contractual intention has been statutorily codified in the U.C.C. and further refined as it applies to the sale of goods, a review of South Carolina case law reveals that the contractual efficacy of trade custom and usage is also applicable to...

To continue reading

Request your trial
6 cases
  • U.S. Bank Trust Nat. Ass'n v. Bell
    • United States
    • South Carolina Court of Appeals
    • August 31, 2009
    ...due. When interpreting an oral contract, a court must give effect to the intentions of the parties. Keith v. River Consulting, Inc., 365 S.C. 500, 506, 618 S.E.2d 302, 305 (Ct.App.2005) (citing Columbia E. Assoc. v. Bi-Lo, Inc., 299 S.C. 515, 519, 386 S.E.2d 259, 261 (1989)). The determinat......
  • Silver v. Aabstract Pools & Spas, Inc.
    • United States
    • South Carolina Court of Appeals
    • January 16, 2008
    ...the court does not look beyond the four corners to discern the parties intentions. See Keith v. River Consulting, Inc., 365 S.C. 500, 506, 618 S.E.2d 302, 305 (Ct.App.2005) (explaining parol evidence is admissible to discover the parties intentions when a contract is silent regarding a part......
  • Wactor v. Jackson Nat'l Life Ins. Co.
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • March 10, 2015
    ...policy. See id. (citing Carolina Aviation, Inc. v. Glens Falls Ins. Co., 51 S.E.2d 757, 761 (S.C. 1949); Keith v. River Consulting, Inc., 618 S.E.2d 302, 305 (S.C. Ct. App. 2005)). And, because the policy thereby contained a notice provision, the Edens decision applied, meaning that Jackson......
  • Diversified Colors Inc. v. Cranston Print Works Co.
    • United States
    • U.S. District Court — District of South Carolina
    • August 9, 2011
    ...when "a contract is silent as to a particular matter" or to the interpretation of an ambiguous contract. Keith v. River Consulting, Inc., 618 S.E.2d 302, 305 (S.C. Ct. App. 2005) ("[I]t is necessary for enforceability that the essentials of the contract be agreed upon but all need not be ex......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT