KIAWAH PROPERTY v. THE PUBLIC SERVICE, 25782.
Citation | 593 S.E.2d 148,357 S.C. 232 |
Decision Date | 09 February 2004 |
Docket Number | No. 25782.,25782. |
Parties | KIAWAH PROPERTY OWNERS GROUP, Appellant, v. THE PUBLIC SERVICE COMMISSION OF SOUTH CAROLINA, Respondent, and Kiawah Island Utility, Inc., Intervenor-Respondent. |
Court | South Carolina Supreme Court |
Michael A. Molony and Lea Kerrison, both of Young, Clement, Rivers and Tisdale, of Charleston, for Appellant.
Fred David Butler, of Columbia, for Respondent S.C. Public Service Commission.
G. Trenholm Walker and Clay B. McCullough, of Pratt-Thomas, Epting and Walker, of Charleston, for Intervenor-Respondent, Kiawah Island Utility Company.
This is an appeal from an order of the Public Service Commission (PSC) approving a rate increase for Respondent, Kiawah Island Utility (Utility). In 1999, this Court reversed and remanded the matter in order for the PSC to set forth sufficient evidentiary detail supporting its conclusions. Kiawah Prop. Owners Group v. Pub. Serv. Comm'n, 338 S.C. 92, 525 S.E.2d 863 (1999)(KPOG I). On remand, the PSC affirmed its prior holdings. The circuit court affirmed, finding the PSC's order sufficiently complied with this Court's mandate. We affirm.
The pertinent facts are set forth in KPOG 1:
338 S.C. at 94, 525 S.E.2d at 864. In KPOG 1, we found the PSC had failed to set forth a sufficient evidentiary basis for its determinations.
ISSUES
This Court applies a deferential standard in reviewing decisions by the PSC and will affirm those decisions if supported by substantial evidence. Total Envtl. Solutions, Inc. v. South Carolina Pub. Serv. Comm'n, 351 S.C. 175, 568 S.E.2d 365 (2002); Heater of Seabrook, Inc. v. Pub. Serv. Comm'n of South Carolina, 324 S.C. 56, 478 S.E.2d 826 (1996). We will not substitute our judgment for that of the PSC where there is room for a difference of intelligent opinion. Id. The PSC's findings are presumptively correct, requiring the party challenging an order to show the decision is "clearly erroneous in view of the substantial evidence on the whole record." Id.
Normally, the expenses of a Utility are presumed to be reasonable when incurred in good faith. KPOG I, 338 S.C. at 95, 525 S.E.2d at 864, citing Hamm v. South Carolina Pub. Serv. Comm'n, 309 S.C. 282, 422 S.E.2d 110 (1992)
. However, when payments are made to an affiliate, a mere showing of actual payment does not establish a prima facie case of reasonableness. Hilton Head Plantation Utilities, Inc. v. Pub. Serv. Comm'n, 312 S.C. 448, 451, 441 S.E.2d 321, 323 (1994). The PSC must review and analyze intercompany dealings and determine if they are reasonable; if there is an absence of data and information from which the reasonableness and propriety of the services rendered and the reasonable cost of rendering such services can be ascertained, the allowance is properly refused. Id.
Owners assert that since Utility is a wholly-owned subsidiary of Developer, Developer should have a) donated numerous items to it (such as fire hydrants, transmission/distribution lines), or b) not have charged Utility for other items (such as management fees), and c) that Developer should be required to reimburse Utility for any expenses it claims were unreasonable.2 We agree with the PSC that it simply does not have authority to order the relief requested.
In its order on rehearing, the PSC ruled that since it had jurisdiction only over public utilities, it did not have authority to
The statute conferring authority on the PSC, S.C.Code Ann. § 58-5-210 (1976), states:
The [PSC] is ... vested with power and jurisdiction to supervise and regulate the rates and service of every public utility in this State, together with the power, after hearing, to ascertain and fix such just and reasonable standards, classifications, regulations, practices and measurements of service to be furnished, imposed, observed and followed by every public utility in this State and the State hereby asserts its rights to regulate the rates and services of every "public utility" as herein defined.
(Emphasis supplied). Notwithstanding Developer is not a "public utility,"3 Owners assert PSC does, in fact, have jurisdiction over Developer, pursuant to S.C.Code Ann. § 58-5-20 (1976). Section 58-5-20 provides:
Any corporation or person not engaged in business exclusively as a public utility shall be governed by the provisions of Articles 1, 3 and 5 of this chapter in respect only of the public utility owned, leased, operated or managed by it or him and not in respect to any other business or pursuit.
We find § 58-5-20 was simply intended to subject the provider to regulation by the PSC as a utility with respect to its activities in the provision of utility services; we do not believe it was intended, as Owners suggest, as authority for PSC to order a separate entity to donate land to its subsidiary, to rescind its land leases, to make payments to the Utility for certain assets, to donate fire hydrants to the utility, etc.
Moreover, we find it is simply unnecessary for PSC to exercise direct jurisdiction over Developer. To the extent a transaction is not done at "arms-length," or is found by the PSC to be unreasonable, it is properly excluded from the ratebase, thereby ensuring that improper or unreasonable transaction costs are not passed on to rate-payers. See generally Lee R. Russ, Annotation, Amount Paid By Public Utility to Affiliate for Goods or Services as Includable in Utility's Rate Base and Operating Expenses in Rate Proceeding, 16 A.L.R.4th 454 (1982)(recognizing public service commissions may scrutinize transactions between affiliates and adjust operating expenses accordingly). In fact, the PSC did exclude numerous items and amounts in the present case,4 and granted an increase to Utility's operating margin of only 3.55%, rather than the 5.43% operating margin requested. The PSC properly declined to exercise jurisdiction over Developer.
Pursuant to 23 S.C.Code Ann. Regs. § 103-541:
No utility shall execute or enter into any agreement or contract with any person, firm, partnership, or corporation or any agency of the Federal, State or local government which would impact, pertain to, or effect said utility's fitness, willingness, or ability to provide sewer service, including but not limited to the collection or treatment of said sewerage, without first submitting said contract in form to the Commission and obtaining approval of the Commission.
(Emphasis supplied). It is undisputed that Utility entered into two land leases with Developer without obtaining prior PSC approval. One of the leases is for a "down island storage facility" used for a one million gallon above ground storage tank for potable water, and the other is land next to Utility's wastewater treatment plant on which Utility built a holding pond for treated effluent. Although the PSC ruled the better practice would be for Utility to have prior approval of the lease agreements, it found the leased property was useful to, and used by, Utility. We agree.
Developer leased the land for the holding pond to Utility for an annual rental of $66,000. PSC approved a $33,000 annual expense for the leased premises for the holding pond. In its order, the PSC cited the testimony of Utility's engineer, Mr. Bohannon, which indicated that Utility needed additional storage capacity for treated effluent to serve the needs of all of its customers. The PSC also cited the testimony of Utility's CEO, Mr. Clarkson, to the effect that alternatives for increasing storage capacity would have cost much more money, that Utility would have had a hard time borrowing sufficient funds from a bank to purchase the property, and that an independent appraisal firm had determined the fair market rental value for the property. Owners do not contest the evidence cited by PSC in support of its decision; they simply contend that an independent utility would not have entered the leases. However, this Court refrains from substituting its judgment for that of the PSC where there is room for a difference of intelligent opinion. Heater of Seabrook, Inc. v. Pub. Serv. Comm'n of South Carolina, supra.
As noted by the PSC, Owners have at no time challenged the reasonable rental value...
To continue reading
Request your trial-
KIAWAH PROPERTY v. Public Service
...resulting in the opinion finding that the subsequent PSC order was supported by the evidence. Kiawah Prop. Owners Group v. Pub. Serv. Comm'n, 357 S.C. 232, 593 S.E.2d 148 (2004), (KPOG II). Upon this backdrop, another rate dispute began in 1999, when the Utility set out to raise its rates a......
-
Utilities Serv. of South Carolina Inc. v. the South Carolina Office of Regulatory Staff
...judgment for that of the PSC where there is room for a difference of intelligent opinion.” Kiawah Property Owners Group v. Public Service Comm'n of S.C., 357 S.C. 232, 237, 593 S.E.2d 148, 151 (2004). However, we “may reverse or modify the decision if substantial rights of the appellant hav......
-
Daufuskie Island Util. Co. v. S.C. Office of Regulatory Staff, Haig Point Club & Cmty. Ass'n, Inc.
...S.C., Inc. v. S.C. Off. of Reg. Staff , 392 S.C. 96, 103, 708 S.E.2d 755, 759 (2011) (quoting Kiawah Prop. Owners Group v. Pub. Serv. Comm'n of S.C. , 357 S.C. 232, 237, 593 S.E.2d 148, 151 (2004) ) [hereinafter Utilities Services ]. "The [Commission] is considered the ‘expert’ designated b......
-
Spivey ex rel. Spivey v. Car. Crawler
...Inc. v. Carolina Power Light Co., 279 S.C. 64, 66, 301 S.E.2d 761, 762 (1983); see also Kiawah Property Owners Group v. The Public Service Comm'n of South Carolina, 357 S.C. 232, 593 S.E.2d 148 (2004); Byrd v. Irmo High School, 321 S.C. 426, 468 S.E.2d 861 (1996). Accordingly, issues that a......