Kinkella v. Baugh

Citation660 P.2d 233
Decision Date07 March 1983
Docket NumberNo. 17967,17967
PartiesJoseph M. KINKELLA, Plaintiff and Appellant, v. H.L. (Jim) BAUGH and Dan Baugh, Defendants and Respondents.
CourtSupreme Court of Utah

W. Scott Barrett, Logan, for plaintiff and appellant.

N. George Daines, Logan, for defendants and respondents.

STEWART, Justice:

This is an action for damages on a cost plus 10 percent contract for the remodeling of a home. Plaintiff contended at trial that defendants had inflated their costs and that they were not entitled to rely on the contract because they were not licensed as general contractors. The trial court ruled that the evidence did not support plaintiff's allegations and held for defendants. We affirm.

Pursuant to a contract between plaintiff Joseph Kinkella and defendant Jim Baugh, Baugh agreed to act as general contractor for an extensive remodeling of plaintiff's residence. Plaintiff knew at the signing that Jim Baugh did not have a contractor's license, but both parties agreed that Jim Baugh's son Dan, whose possession of a contractor's license was disputed at trial by plaintiff, would represent Jim in supervising the details of the construction. The parties agreed that Jim Baugh's compensation would be computed at 10 percent of the costs of the construction; they did not, however, specify the manner in which he was to be paid his compensation. The usual practice of the parties was for the plaintiff to make periodic advance payments to Jim Baugh to cover costs, and Jim would retain 10 percent of each payment. By that method Jim received approximately $9,000 of his compensation. On a few occasions he had the subcontractors add 10 percent to their invoices for the cost of materials and labor. When the invoices were paid by plaintiff, Jim would either retain 10 percent prior to remitting the proper sum to the subcontractor or receive that amount back from the subcontractor. Jim received approximately $3,400 by first adding his 10 percent to subcontractor invoices.

The construction went generally as planned, but with some disputes along the way. The total cost of the construction, excluding Jim Baugh's compensation, was approximately $135,000. Compensation received by Jim Baugh totalled $12,400, just under 10 percent of total costs.

Plaintiff alleged at trial that defendants breached the contract by (1) overcharging him approximately $10,000 for labor and $9,000 for materials; and (2) by taking $3,400 in "secret kickbacks," referring to the compensation Jim Baugh received through the subcontractors' invoices. Plaintiff also argued that neither defendants' records nor a post-construction audit supported defendants' cost figures, that defendants should not be allowed to enforce the contract because they were unlicensed, and that defendants' compensation, if any, should be limited to $9,000.

Following a nonjury trial and submission of detailed audits by both parties, the trial court found (1) that although neither party had kept good records, the evidence adduced tended to support defendants' cost figures; and (2) that the $3,400 deducted from payments to subcontractors was properly retained by Jim Baugh as part of the compensation owed him. The trial court made no finding as to whether either of the defendants possessed a license at the time of the construction. On these findings the trial court held for defendants.

On appeal, plaintiff contends that (1) the findings of fact and conclusions of law were improperly adopted because the trial court did not afford plaintiff an opportunity to object to them; (2) the findings of fact are contrary to the evidence and no finding was made as to whether either defendant was licensed; (3) the defendants cannot enforce the contract because they are unlicensed; (4) defendants' retention of the $3,400 constituted an improper award of affirmative relief not based on a counterclaim; and (5) the burden of keeping records of the cost of labor and materials was improperly placed on plaintiff rather than on defendants. We address those allegations in that same order.

Rule 2.9(b), Rules of Practice in the District and Circuit Courts, requires that copies of proposed findings of fact and conclusions of law be served on opposing counsel before being presented to the court for signature. The requirement of service on the losing counsel is for the purpose of permitting him to make objections and propose amendments. In the present case, the trial court signed the findings and conclusions prepared by defendants on the same day that plaintiff received his copy, thereby precluding plaintiff from responding before they were signed. However, within a few days plaintiff submitted objections, and the trial court, after reviewing them, allowed the findings and conclusions to stand as originally signed. Despite the failure of defendants to comply with the rule, we think the trial court must be deemed to have considered the objections and to have rejected them. On the facts of this case, there was substantial compliance with Rule 2.9(b).

Plaintiff argues that he presented irrefutable evidence that defendants inflated the labor and material costs. Plaintiff also claims that the trial court attached insufficient weight to the testimony of plaintiff's expert. The trial court heard the witnesses of both parties first-hand, evaluated detailed written audits by both sides, and concluded that plaintiff's evidence was not as convincing as defendants' evidence. On appeal we do not retry the facts and will not overturn the trial court's findings of fact if they are supported by substantial evidence. E.g., Piacitelli v. Southern Utah State College, Utah, 636 P.2d 1063, 1067 (1981). The evidence adequately supports the findings.

Plaintiff also...

To continue reading

Request your trial
38 cases
  • Govert Copier Painting v. Van Leeuwen
    • United States
    • Utah Court of Appeals
    • November 8, 1990
    ...by avoiding payment, and the unlicensed contractor's unlicensed status was the result of a good faith mistake); Kinkella v. Baugh, 660 P.2d 233, 236 (Utah 1983) (because the unlicensed contractor's son was licensed and supervised the project, the plaintiff received the protection of the lic......
  • State v. Ramirez
    • United States
    • Utah Supreme Court
    • April 23, 1991
    ...are 'clear, uncontroverted, and capable of supporting only a finding in favor of the judgment.' " Id. at 999 (quoting Kinkella v. Baugh, 660 P.2d 233, 236 (Utah 1983)). The court of appeals apparently relied on this statement of the standard in its recent decision in State v. Harrison, 805 ......
  • Utah State Road Com'n v. Friberg
    • United States
    • Utah Supreme Court
    • May 1, 1984
    ...is a sufficient basis for determining that the delay caused by the litigation was not the Fribergs' fault. See footnote 3.1 Kinkella v. Baugh, Utah, 660 P.2d 233 (1983).2 No. C-225-73 (D.Utah Jan. 11, 1974).3 Cottonwood, Inc. v. Hurley, No. C-79-0081 (D.Utah Nov. 29, 1979).4 U.C.A., 1953, §......
  • State v. Harrison
    • United States
    • Utah Court of Appeals
    • January 14, 1991
    ...the facts in the record "are clear, uncontroverted, and capable of supporting only a finding in favor of the judgment." Kinkella v. Baugh, 660 P.2d 233, 236 (Utah 1983). Because the Utah Supreme Court had not issued its Arroyo opinion while Harrison's case was before the trial court, it may......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT