Kizziar v. Dollar

Decision Date20 August 1959
Docket NumberNo. 5987.,5987.
Citation268 F.2d 914
PartiesO. Q. KIZZIAR and Mildred Kizziar, his wife, Appellants, v. B. L. DOLLAR, an individual doing business as B. L. Dollar Construction Company, Appellee.
CourtU.S. Court of Appeals — Tenth Circuit

C. E. Hall, Oklahoma City, Okl. (E. E. Gore and W. T. Gore, Altus, Okl., on the brief), for appellants.

Robert B. Harbison, Altus, Okl. (Ross Rutherford and Harbison & Whiteside, Altus, Okl., on the brief), for appellee.

Before MURRAH, PICKETT and BREITENSTEIN, Circuit Judges.

PICKETT, Circuit Judge.

On November 12, 1956 the plaintiff and the defendant, O. Q. Kizziar, entered into a written contract whereby the plaintiff agreed to construct a building on property owned by the defendant and his wife for an agreed price of $20,000. This action was brought to recover the full amount due on that contract and the additional sum of $2,863.50 alleged to be due on a subsequent oral contract for an enlargement of the building as originally planned. The plaintiff also sought the foreclosure of a mechanics' and materialmen's lien on the property and the recovery of a reasonable attorney fee for enforcing the lien. As a separate cause of action, plaintiff requested judgment for the balance which Kizziar allegedly owed him on a former contract. The case was tried without a jury, and the court found for the plaintiff on the written and oral contracts of the first cause of action, and entered judgment in the requested amounts less certain deductions. The court also ordered the lien foreclosed by sale of the property and allowed $2,500 for costs and attorney fees. Judgment was also entered in favor of the plaintiff for $902.60, the full amount alleged to be due on the former contract.

With regard to the first cause of action, the defendants urge that the written contract sued upon was entire and indivisible and that performance by the plaintiff was insufficient to permit recovery thereon. The law is settled in Oklahoma that when a contractor and builder has in good faith endeavored to comply with the terms of a contract, literal compliance in all details is not essential to recovery, especially where the owner has taken possession of the building. In Robinson v. Beaty, 75 Okl. 69, 181 P. 941, 942, the Oklahoma Supreme Court said:

"Since the rule of exact or literal performance has been relaxed, literal compliance with a building contract is not essential to a recovery thereon, but a performance thereof in all its material and substantial particulars is sufficient."

There is substantial performance when the builder has in good faith intended to perform his part of the contract and has done so in the sense that the building is substantially what is provided for, and there are no omissions or deviations from the general plan which cannot be remedied without difficulty. 3 Williston, Contracts, § 842 (Rev.Ed., 1936); Restatement, Contracts, § 275; 9 Am.Jur., Building and Construction Contracts, § 42; Vol. 40, Words and Phrases, Substantial Performance.

When there has been substantial performance, the measure of recovery is the amount stipulated in the agreement less the reasonable cost of remedying defects and omissions to make the building conform to the contract. Klein v. Moore, 202 Okl. 88, 210 P.2d 363; Busboom v. Smith, 199 Okl. 688, 191 P.2d 198, and cases there cited. In Lane v. F. S. Miller Lumber Co., 101 Okl. 14, 222 P. 968, 969, the court quoted with approval from Kelley v. Hamilton, 78 Okl. 179, 189 P. 535, as follows:

"A contractor and builder who has in good faith endeavored to perform all that is required of him by the terms of his contract for the construction of a building, and has in fact substantially performed the same, is ordinarily entitled to sue upon his contract and recover the contract price less proper deductions therefrom on account of omissions, deviations, and defects chargeable to him, especially where the owner occupies and uses such building."

See also 9 Am.Jur., Building and Construction Contracts, §§ 40, 43; Annotation 38 A.L.R. 1383; Annotation 65 A. L.R. 1297.

There is no indication of bad faith on the part of the plaintiff and, from an examination of the record, we are satisfied that there was substantial performance of the contract on his part. The building in question was constructed for use as a medical clinic and the defendants' lessee has occupied it since the first part of April, 1957.1 During construction numerous changes in the plans were made at the request of the lessee and the defendants.

The trial court found all of the deviations from the specifications except two were authorized by subsequent agreement of the parties. The two exceptions relate to the roof and the heating and airconditioning equipment. The plans and specifications required what was described as a "5-ply built-up roof". The roof installed was 4-ply and the court allowed a deduction of $150 which, according to the evidence, would be the reasonable cost of placing an additional ply on the roof. The specifications provided for a central heating and airconditioning system "ducted in". The system was to be Chrysler Air Temp, or its equal, with an air duct into each room, but the size of the unit was not specified. It is agreed that the type of heating and airconditioning unit installed was equal to the Chrysler product, but the court found that the system was inadequate to properly cool the building. The court also found that the deficiency could be overcome by the installation of window airconditioners at a cost of $750, and allowed that amount as a deduction from the contract price. There was evidence that Kizziar approved the use of the particular make of heating and cooling system which was installed, but that approval would not authorize the installation of a system which was of a different type than that specified or which was inadequate for its intended purpose. The defendants are paying for and are entitled to a central system with sufficient capacity to heat and cool the building in a reasonable manner, and the court should have determined and made allowance for the additional cost to provide such a system. Mitchell v. Spurrier Lumber Co., 31 Okl. 834, 124 P. 10.

We think the evidence sustains the finding that a number of the remaining variations, alterations and adjustments made during the course of the construction were authorized by subsequent agreement of the parties. There are, however, some items required by the contract specifications which were not completed or installed and which were not waived.2 For the contract price, the defendants are entitled to a completed building. Unless this failure resulted solely from defendants' conduct which prevented completion, there should have been an allowance for the necessary cost of completing the building as planned.

Complaint is made that the foundation did not meet the specifications and that the variance was not authorized. The evidence is without conflict that the foundation, although not equal to that specified, was standard and...

To continue reading

Request your trial
13 cases
  • Bergeson v. Dilworth, Civ. A. No. 87-1579-T.
    • United States
    • U.S. District Court — District of Kansas
    • May 25, 1990
    ...an award higher than that requested in plaintiff's pleadings, the complaint is considered amended to conform to proof. Kizziar v. Dollar, 268 F.2d 914, 918 (10th Cir.1959). Defendants also bring to the court's attention the absence of any evidence as to the defendants' net worth. Kansas law......
  • Nelson v. Hazel
    • United States
    • Idaho Supreme Court
    • October 25, 1967
    ...the contractor's costs, is reasonable and is in conformity with the directions of this Court in the first appeal. See Kizziar v. Dollar, C.A.10, 268 F.2d 914 (1959), certiorari denied 361 U.S. 914, 80 S.Ct. 258, 4 L.Ed.2d 184; Lindberg v. Brandt, 350 Ill.App. 317, 112 N.E.2d 746 (1953); 17A......
  • United Phosphorus, Ltd. v. Midland Fumigant, Inc.
    • United States
    • U.S. District Court — District of Kansas
    • July 7, 1998
    ...higher than requested award, however, may be sustained only if the evidence adduced at trial supports the verdict. See Kizziar v. Dollar, 268 F.2d 914, 918 (10th Cir.1959). Although plaintiffs introduced abundant evidence of Fox's fraudulent conduct, they explicitly conceded in the Final Pr......
  • SECURITIES AND EXCH. COM'N v. Glass Marine Industries, Inc.
    • United States
    • U.S. District Court — District of Delaware
    • August 31, 1962
    ...** The opinion herein incorporates the findings and conclusions required under Fed. R.Civ.P. 52, 28 U.S.C.A. 1 See, also, Kizziar v. Dollar, 10 Cir., 268 F.2d 914, 918; Williams v. Nichols, 4 Cir., 266 F.2d 389, 391; Kithcart v. Metropolitan Life Insurance Co., 8 Cir., 119 F.2d 497, 500; Ba......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT