Laclede Construction Co. v. Tudor Iron Works
Decision Date | 18 June 1902 |
Citation | 69 S.W. 384,169 Mo. 137 |
Parties | LACLEDE CONSTRUCTION CO. v. TUDOR IRON WORKS. |
Court | Missouri Supreme Court |
Appeal from St. Louis circuit court; Franklin Ferris, Judge.
Action on contract by the Laclede Construction Company against the Tudor Iron Works. From a judgment for defendant, plaintiff appeals. Affirmed.
This is an action to recover $62,402, damages alleged to have been suffered by reason of an alleged breach of contract by the defendant. The contract pleaded in the petition is as follows:
— All f. o. b. cars Madison, Ill., less allowance of 5 cts. for freight to Pekin or elsewhere on your line. Terms: Cash on the 20th of the month following delivery. Deliveries as wanted during 1899, in car lots; all to be of first-class material and workmanship. Bolts to be of especially good fibrous iron, with high tensile strength. All subject to inspection. It is the intention of this contract to supply fastenings for such rails as you may buy or lay up to this amount, and it is binding only to that extent. We will furnish you fastenings also for repairs and for new sidings at the above prices in car lots; less than car lots at 5 cts. advance, excepting splices, on which special prices for less than car lots will be made according to the quantity. Your acceptance of the above on this sheet and duplicate will complete the contract between us. Yours truly, B. S. Adams, Sec.
"Accepted: Laclede Construction Co., by Wm. E. Guy, Prest."
The petition then contains the following further material averments:
The answer is lengthy, and need not be further analyzed than to say it sets up, inter alia, two defenses: First, that the contract pleaded is unilateral; and, second, that the plaintiff did not perform all the conditions precedent required by the contract to be performed by it before it was entitled to demand of the defendant a performance of its part of the contract.
Upon the trial the plaintiff introduced various correspondence between the parties hereto and the Republic Iron & Steel Company, to whom the defendant company sold out its plant and business on May 15, 1899, and also produced certain oral testimony. In condensed form, the substance of the correspondence is this: First. On January 18, 1899, the defendant wrote to the plaintiff as follows: Second. On March 11, 1899, the defendant wrote to the plaintiff as follows: Third. To this the plaintiff replied on March 15, 1899, saying it would not need any track fastenings of any consequence prior to June, 1899. Fourth. On May 15, 1899, the defendant wrote the plaintiff that it had sold out its plant and business to the Republic Iron & Steel Company, and asking, if the plaintiff desired any track fastenings made in June or even July, it should say so at once, as the works were fast filling up with orders that would take the whole summer. The plaintiff is not shown to have replied to this letter at all. Fifth. On June 27, 1899, the plaintiff wrote to the defendant (ignoring the sale to the Republic Iron & Steel Company), and demanded performance of the terms of the contract on its part, and delivery "at the very earliest possible moment" of "the balance of the angle bars due under said contract; also all the bolts, nuts, and spikes." Sixth. On June 29, 1899, the defendant acknowledged receipt of the plaintiff's letter of June 27th, and said it could not deliver any of the track fastenings before 60 days, and made some reference to the character of the spikes to be furnished, and asked if the plaintiff had ordered the splices. Seventh. On July 3, 1899, the plaintiff replied, saying that the defendant might consider its letter of June 27th "to be an order for the angle bars, bolts, nuts, and spikes to the entire amount due this company under the contract," and asked that they be delivered "at the very earliest possible date." Eighth. On August 15, 1899, the Republic Iron & Steel Company wrote to the plaintiff as follows: ...
To continue reading
Request your trial-
Lee & Boutell Co. v. Brockett Cement Co.
...v. Lange, 143 Mo. 100; Cosgrove v. Leonard, 175 Mo. 100; Coons v. St. Louis, 203 Mo. 227; Whipple v. Cooper, 55 Mo. App. 554; Laclede v. Tudor, 169 Mo. 137; Carpenter v. Reliance, 103 Mo. App. 480; State v. Ellison, 270 Mo. 645. (5) To establish equitable trust, evidence must be clear and c......
-
Prudential Ins. Co. of Am. v. Goldsmith
...et al. v. Dalton et al., 341 Mo. 454, 107 S.W. (2d) 1071; Gillen v. Bayfield, 329 Mo. 681, 46 S.W. (2d) 571; LaClede Construction Co. v. Tudor Iron Works, 169 Mo. 137, 69 S.W. 384; Cal Hirsch & Sons Iron & Rail Co. v. Paragrould & M.R. Co., 148 Mo. App. 173, 127 S.W. 623; Malloy v. Egyptian......
-
State ex rel. Prudential Ins. Co. of America v. Bland
... ... under the guise of construction. State ex rel. Prudential ... Ins. Co. v. Shain, 344 Mo ... Bayfield, 329 Mo ... 681, 46 S.W.2d 571; LaClede Construction Co. v. Tudor ... Iron Works, 169 Mo. 137, 69 ... ...
-
Great Eastern Oil Co. v. DeMert & Dougherty
... ... 1143; Scullin ... Steel Co. v. Mississippi Valley Iron Co., 308 Mo. 453; ... Cobb v. Whitsett, 51 Mo.App. 146; ... is estopped from denying the construction so placed upon the ... contract by its own contemporaneous ... v ... Kingman & Co., 42 Mo.App. 208; Laclede Const. Co. v ... Moss Tie Co., 185 Mo. 25, 84 S.W. 76; ... 25, 84 S.W. 76; ... Laclede Const. Co. v. Tudor Iron Works, 169 Mo. 137, ... 69 S.W. 384; 12 Am. Jur ... ...