Laird v. Hudson Engineering Corporation

Decision Date28 October 1971
Docket NumberNo. 30676.,30676.
Citation449 F.2d 216
PartiesShirley Roberts LAIRD, Individually and for and on behalf of the minors Michael Gray Laird and Johnny Mark Laird, Plaintiff-Appellee, v. HUDSON ENGINEERING CORPORATION, Defendant-Appellee, and United States Steel Corporation, Defendant-Appellant.
CourtU.S. Court of Appeals — Fifth Circuit

Leon Sarpy, Paul A. Nalty and James R. Nieset, New Orleans, La., for U.S. Steel Corp.; Chaffe, McCall, Phillips, Burke, Toler & Sarpy, New Orleans, La., of counsel.

Joseph L. Waitz, Waitz & St. Martin, Michael St. Martin, Houma, La., for Laird.

Philip J. McMahon, Houma, La., James H. Drury, New Orleans, La., Edmund McCollam, Borowski, Lofaso, McMahon & McCollam, Houma, La., for Hudson

Eng. Corp.; Drury, Lozes, Young & Curry, New Orleans, La., of counsel.

Before O'SULLIVAN,* THORNBERRY and INGRAHAM, Circuit Judges.

PER CURIAM.

In this appeal from a jury verdict below finding the appellant U. S. Steel liable for the wrongful death of plaintiff Laird's husband, U. S. Steel raises some fourteen points of error. The first five points of error attack in one form or another the sufficiency of the evidence to support the jury verdict.

After a review of the Record, we conclude that the evidence was sufficient to support the jury verdict, and satisfies the "sufficiency" standard under which we review jury findings. Stockton v. Altman, 5th Cir. 1970, 432 F.2d 946. In its sixth point of error, U. S. Steel complains that interest on the judgment should not have been allowed from the date of judicial demand pursuant to 13 L.S.A.-R.S. 4203, because an award of prejudgment interest violates the appellant's Seventh Amendment right to a jury trial. There is no merit to this contention. This Circuit has recognized in several cases Louisiana's rule on awarding interest from the date of judicial demand, and has upheld the right to such interest. See, e. g., Texaco Inc. v. Lirette, 5th Cir. 1969, 410 F.2d 1064. Appellant's remaining eight points of error attack various discretionary decisions and evidentiary rulings of the trial judge.

We have reviewed each of these contentions and find they all lack merit. Only two of them require comment. U. S. Steel complains of the trial judge's refusal to relax his pre-trial order to allow an additional expert witness to testify for U. S. Steel at the last minute. This was clearly within the trial court's discretion, and we see no abuse of discretion in his refusal to relax the pre-trial order in this instance. Moreover, it appears that the additional expert's testimony would have been cumulative.

U. S. Steel also complains about the trial court's refusal to grant a remittitur as to $238,000.00 in damages awarded the plaintiff for loss of support for herself and her two children. The evidence presented to the jury amply supported this award, and certainly does not warrant any interference by this Court in the trial judge's discretionary decision to deny remittitur. No other point of error as to damages is raised by the appellant.

Affirmed.

O'SULLIVAN, Senior Circuit Judge (dissenting):

I respectfully dissent. I do so because the size of the recovery impelled me to consider whether the trial procedures visited any unfairness upon appellant United States Steel. As set out hereinafter, I am persuaded that such did occur.

Because the majority opinion is silent as to the facts which brought about this lawsuit, I recite those necessary to an exposition of my own views. The amount of $238,000, the figure mentioned in the majority opinion, was awarded for loss of support. Additional amounts allowed for decedent's pain and suffering for loss of companionship, and for some miscellaneous expenses brought the total recovery to $415,287.85.

Plaintiff's decedent, Malcolm Gray Laird, then 37 years of age, received fatal burns when an explosion occurred in a pipeline located at the premises of Shell Oil Company near Gibson, Louisiana. The catastrophe occurred on December 17, 1968. Malcolm Laird died on December 28, following. He suffered very great pain during the days that intervened. On the date of the explosion, the deceased, a night shift foreman in the employ of Shell, was earning $800 per month. He was survived by his widow and two minor children, Michael Gray Laird and Johnny Mark Laird, aged 13 and 9, respectively.

This lawsuit was started in the United States District Court for the Eastern District of Louisiana on March 6, 1969, naming as defendants United Gas Industries, Inc., United Pipeline Company and Pennzoil United, Inc. The case against these defendants was dismissed when it was disclosed that they had nothing to do with the installation or operation of the pipeline. On May 2, 1969, an amended complaint was filed naming Hudson Engineering Corporation as defendant and charging it with negligence in the design, construction and fabrication of the gas transmission line and its connection with a gas transmission line owned by Shell Oil Company leading into the latter's plant. The explosion occurred at the place of this connection, and it was established that such connection had been made by Hudson Engineering under contract with Shell Oil Company some four or five years before the explosion. The appellant United States Steel was not named or accused of any wrongdoing in the first amended complaint filed some five months after the fatal accident.

On August 26, 1969, another amended complaint was filed — this time adding the United States Steel as a defendant, charging that Steel had manufactured and furnished the 30" pipe that made up the main gas line that led to the "connection." This complaint then charged that U. S. Steel and Hudson were negligent because of "improper and faulty design, construction, fabrication and manufacture" of the main pipeline and the "connection." Thereafter, Hudson filed a cross-claim against U. S. Steel, its allegations casting the entire blame for the accident upon Steel.

The stage for this disaster was set in 1964 when, pursuant to a contract with Shell Oil, Hudson Engineering constructed a gas processing plant at the site in question. Supplemental to this original contract, Hudson agreed to extend a 30" gas line to the plant at a depth of five feet below the ground from a flange on a previously installed 30" gas transmission line coming in from the Gulf Tidelands. Another gas transmission line, 12¾" in diameter and owned by Shell, would intersect with the 30" line at a point some distance from the plant. The 12" line approached the 30" in a perpendicular direction, three feet above the ground, with a valve several feet from the 30". Hudson connected the 12" into the 30" by using a "Weldolet," a device which required cutting a hole in the 30" pipe and welding this Weldolet to the two lines. Except for the explosion on December 17, 1968, there was no evidence of any difficulty with the performance of the 30" pipe which had been furnished by U. S. Steel. It continues in use at the Shell Oil plant.

The case came on for trial to a jury on June 8, 1970, Hudson charging that the inferior quality of the 30" pipe which had been furnished by Steel was the sole cause of the explosion, and Steel charging that carelessness of Hudson in designing and making the connection was the cause of it. Resolution of the issue of proximate and responsible fault became primarily a contest of experts hired by the antagonists, although Steel produced some of its own people. Hudson produced none of its people who had designed and carried on the work of making the involved connection. Its vice-president, one Battershell, who had been Hudson's project engineer on the job — listed in a pretrial order as a witness it would produce at trial — had gone to Australia at the time of trial and Hudson was allowed to provide a substitute for him. The witness, however, was not called by Hudson but by plaintiffs, whose counsel enjoyed the advantage of cross-examining him as an adverse witness. As discussed later, Steel charges error in this allowed change of witnesses. None of the persons listed at pretrial as those employees of Hudson who had made the installation where the explosion occurred was produced. Shell Oil Company was allowed to intervene as a party plaintiff to seek recovery for the cost of fulfilling its Workmen's Compensation obligations to the widow of the decedent. It charged that the death of its employee resulted from negligence of Hudson Engineering and U. S. Steel. The evidence showed that promptly after the explosion, with the consequent death of its employee and damage to its plant, Shell began an investigation of the scene of the explosion. It used men from its engineering staff, some of whom qualified as experts in the relevant field. The investigating team totalled some six men. They made a written report of their findings which was ambivalent as to fixing the blame for the casualty. This staff-written report contained the following conclusions:

"Preliminary conclusions based on visual inspection of the ruptured pipe are that the rupture originated from a brittle crack in the base metal of the 30-inch pipe at the toe of the weld attaching the 30 × 12 Weld-O-Let to the pipe. It appears that the brittle crack was formed some time prior to the failure and resulted from residual stresses developed during the fabrication or from the combination of these residual stresses and subsequent mechanical damage. It is further concluded that damage to the existing plant would have been lessened by different design of certain plant components."

It will be noted that this conclusion did not fix the total blame upon the U. S. Steel pipe, nor forecast the opinions that would be expressed by the experts hired by plaintiffs and Hudson.

None of these Shell investigators, however, was produced by the plaintiffs, by Shell, or by Hudson. The defendant called some of these men, but was denied the...

To continue reading

Request your trial
8 cases
  • Younis Bros. & Co., Inc. v. CIGNA Worldwide Ins. Co.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • November 16, 1994
    ...interest is an equitable remedy not implicated by the Seventh Amendment. See Defendant's Memorandum at 41; Laird v. Hudson Engineering Corp., 449 F.2d 216, 217 (5th Cir. 1971), cert. denied, United States Steel Corp. v. Laird, 405 U.S. 955, 92 S.Ct. 1177, 31 L.Ed.2d 232 (1972). Similarly, b......
  • Olsen Engineering Corp. v. Hudson Engineering Corp.
    • United States
    • Court of Appeal of Louisiana — District of US
    • December 17, 1973
    ...of U.S. Steel. Hudson alleged that the pipe was improperly designed constructed and manufactured by U.S. Steel. Prior to trial of the Laird case in the federal court, the present suits seeking property damage were filed in state court. In the state court suits U.S. Steel filed a third-party......
  • Herrera v. Springer Corp.
    • United States
    • Court of Appeals of New Mexico
    • February 3, 1976
    ...85 N.M. 431, 512 P.2d 1267 (Ct.App.1973); Cantrell v. Dendahl, 83 N.M. 583, 494 P.2d 1400 (Ct.App.1972); Laird v. Hudson Engineering Corporution, 449 F.2d 216 (5th Cir. 1971); Napolitano v. Compania Sud Americana De Vapores, 421 F.2d 382 (2d Cir. 1970); Heilig v. Studebaker Corporation, 347......
  • Webster v. M/V Moolchand, Sethia Liners, Ltd., 83-3056
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • April 30, 1984
    ...diversity of citizenship. Under Louisiana law, interest is awarded from the date of judicial demand. See Laird v. Hudson Engineering Corp., 449 F.2d 216, 217 (5th Cir.1971), cert. denied sub nom. United States Steel Corp. v. Laird, 405 U.S. 955, 92 S.Ct. 1177, 31 L.Ed.2d 232 (1972). Althoug......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT