Lake v. Shenango Furnace Co.

Decision Date14 March 1908
Docket Number2,614.
PartiesLAKE v. SHENANGO FURNACE CO.
CourtU.S. Court of Appeals — Eighth Circuit

This is an action for damages that resulted from the death of John K Laurila, which the plaintiff below alleged was caused by the negligence of the defendant company, his master, in that it employed only two when it should have hired three servants to operate the drum used at its shaft No. 2 to lower timber into its mine. The defenses were that the defendant was not negligent, that the deceased assumed the risk of operating the drum with two men, and that he was guilty of negligence which contributed to his injury. At the close of the evidence the court instructed the jury to return a verdict for the defendant, on the grounds that the deceased assumed the risk of the work in which he was engaged, and that he was guilty of contributory negligence. This and many other rulings are specified as errors. The evidence relative to the place and circumstances of the accident was practically without contradiction, and it disclosed this condition of things:

The accident happened while Laurila and his companion, Tikka were preparing to let a load of lagging down into the shaft during the afternoon of January 17, 1906. Laurila had been engaged in this work during the afternoons since about the middle of December, 1905, but prior to this day he had been one of three men operating the drum to lower the timber into this shaft, while on the day of the accident he was one of two. The shaft was about 6 feet by 8 feet, 137 feet deep planked inside, and it had a crib or collar of timber which extended up above the ground a few inches. It was known as shaft No. 2. A tripod made of three posts rose over the shaft, and from it a bolt depended directly over the center of the shaft and about 19 feet above its mouth, to which a pulley was attached, over which the rope ran that was used to lower the timber. A small chain which was used to fasten the timber together and to hold it as it descended into the shaft was fastened to the end of this rope which hung from the pulley over the shaft, and the other end of the rope was secured to a drum which stood upon posts about three feet above the ground on one side of the shaft and about four feet distant from it.

This drum was about 7 feet long and 16 inches in diameter where the rope wound about it. Upon one end of this drum was a friction brake operated by a lever five or six feet long, which rested upon the drum, and was made effective by pressing the outer end of it down. When the drum was used to wind up the rope, this lever was held above it by hand or by a stick placed under it, and, when a load was about to be lowered, the support was removed, the lever placed the brake upon the drum, and the descent of the load was controlled by an operator who pressed down upon the outer end of the lever. There was an adjustable iron crank about 18 inches long upon each end of the drum which was used to wind up the rope and to prepare the loads of timber for their descent, but which was removed before these loads were let down into the mine. Treating the apparatus from the station of a person standing on the side of the shaft opposite the drum and facing the latter, there was a stick of timber about six feet long and four inches thick which lay parallel to the collar on the right side of the shaft. The load to be lowered at the time of the accident was about two feet square, and it consisted then, and the loads were generally made up of posts and lagging from six to nine feet long which were laid across the collar of the shaft and the stick of timber so that they projected over the collar about a foot and rested upon the timber and upon the collar which was somewhat worn away, or upon the ice or snow which had gathered between the collar and the stick, so that the chain could be readily passed around each of the ends of the loads without raising them. It was winter, and some ice and snow had gathered about the shaft and upon the posts and lagging, and the surface where the load was placed sloped at the rate of about six inches to eight feet toward the shaft. The load which caused the accident weighed from 750 to 1,500 pounds. The loads lowered into this and other like shafts were generally so heavy that two workmen at the cranks could not hold one of them up after it swung over the shaft, and the only means of controlling its descent was the friction brake . When three men operated the drum, the first held up and upon a signal from the chainman applied the brake, the second adjusted the chain first around the end of the load in the mouth of the shaft, and next around the other end, and then held on to it with his hand until the third man, who operated one of the cranks, took the slack out of the rope and drew it taut by winding it upon the drum. When the rope was thus drawn sufficiently taut, upon a signal from the chainman, the first man pressed down upon his lever, and held the load, the third man removed his crank, the chainman let the rope go, went behind the load, and by lifting its rear end slid or pushed it into the shaft, and the first man then lowered it and controlled its descent by operating the brake. When two men used it, the brake lever was held up by a stick beneath it. One of the men adjusted the chain about the ends of the load, then held on to the rope or chain to steady it with one hand and on to one of the cranks with the other until under his direction the second man had wound the rope sufficiently taut by the use of the other crank. Then, upon a signal from the chainman, the second man removed his crank, removed the stick beneath the lever, seized the lever, and held the load with it until the chainman removed his crank, and slid or pushed the load into the shaft, when the second workman controlled and lowered it by the manipulation of the brake lever.

At the time of the accident the brake was held off the drum by a stick beneath the lever. Tikka and Laurila had lowered six or seven loads down the shaft without the aid of any third workman, with Tikka at the chain and Laurila at the crank, when Tikka took the crank and Laurila adjusted the chain and held onto it with one hand to steady it and onto the crank on his end of the drum with the other until the rope was wound up on the drum to some extent when Tikka inquired of Laurila if it was good, or in other words, if the rope was sufficiently taut, and Laurila replied: 'No; wind it a little more. ' Tikka did so, the load slid into the shaft, the drum and the cranks escaped from the workmen as the load descended, one of the revolving cranks struck Laurila, threw him into the shaft, and killed him.

Theodore Hollister (John R. Heino, on the brief), for plaintiff in error.

H. H. Grace (George B. Hudnall, on the brief), for defendant in error.

Before SANBORN, HOOK, and ADAMS, Circuit Judges.

SANBORN Circuit Judge (after stating the facts as above).

The evidence in this case conclusively proved that there was one and only one indispensable condition of safety in the doing of the specific act in the performance of which Laurila lost his life in the lowering of the loads of timber into the shaft, and that condition was that the load should not be slid, or pushed, or swung into or over the shaft until the brake was applied to the drum by means of its lever. If the load went into the shaft before the brake was applied, it would as certainly descend and produce danger of injury and death when three as when two men were operating it, for the law of gravity is uniform and incessant in its work. The loads differed in size and weight, but both at this and at other shafts where similar devices were used they were generally, if not universally, so heavy that they could not be held up by the cranks upon the drums after they swung over the shafts, and this fact was well known to all the workmen about them, and was clearly proved to the jury. This was the reason why the friction brake was provided and used.

The evidence was uncontradicted that it was necessary before the load was swung over the shaft and after the chain had been thrown around its ends that the rope should be wound up so that it was taut, to the end that the timber might be drawn together in a compact body before it started to descend, so that sticks of it would not slip out of the chain and fall down the shaft. The evidence was clear and undisputed that it was the duty of the chainman to steady the chain with his hand as the rope was wound up, to determine when the tension upon it was sufficient to hold the timber together, and insufficient to slide, or tip, or swing the load into the shaft, and then to give the signal to take off the crank and put on the brake, and, after that was done, to push or slide the load into the shaft. This entire duty devolved upon the chainman whether there were two or three men at the shaft, and, in the discharge of this duty, was the one place where the exercise of judgment conditioned the safety of the operation. If the chainman failed to give the signal that the chain was sufficiently taut until the tension became so great that the load slid or swung into the shaft, immediate danger of injury was produced, and that danger was greater when but two men were operating than when there were three, because, if there was a third man at the lever, it was possible that he might catch and hold the load after it swung into the shaft, although he did not receive any signal to apply the brake.

The apparatus was simple. It was nothing but a windlass with a crank and a rope attached, the latter of which ran over a pulley above. No workman of intelligence sufficient to use the simplest tools could have assisted in operating this windlass with two laborers...

To continue reading

Request your trial
29 cases
  • Canadian Northern Ry. Co. v. Senske
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • December 24, 1912
    ... ... 235; H. D. Williams Cooperage Co. v. Headrick, 159 ... F. 680, 682, 86 C.C.A. 548, 550; Lake v. Shenango Furnace ... Co., 160 F. 887, 895, 88 C.C.A. 69, 77; Cryder v ... Chic. R.I. & Pac ... ...
  • Haverland v. Potlatch Lumber Co.
    • United States
    • Idaho Supreme Court
    • July 29, 1921
    ...120 P. 157; Smith v. Potlatch Lumber Co., 22 Idaho 782, 128 P. 546; Bohn Mfg. Co. v. Erickson, 55 F. 943, 5 C. C. A. 341; Lake v. Shenango Furnace Co., 160 F. 887, 88 C. A. 69; Chicago etc. Ry. Co. v. Shalstrom, 195 F. 725, 115 C. C. A. 515, 45 L. R. A., N. S., 387; Utah Co. v. Bateman, 176......
  • United States Smelting Co. v. Parry
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • January 6, 1909
    ... ... attempt to tow a disabled vessel out of a port of repair and ... safety and across Lake Erie; and this when that was the ... ultimate question to be decided by the jury ... 155; National Biscuit Co. v ... Nolan, 70 C.C.A. 436, 138 F. 6; Lake v. Shenango ... Furnace Co. (C.C.A.) 160 F. 887, 894 ... Applying ... the true test to the ... ...
  • Chicago, B. & Q.R. Co. v. Shalstrom
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • March 22, 1912
    ... ... 96; ... Burke v. Union Coal & Coke Co., 157 F. 178, 181, 84 ... C.C.A. 626, 629; Lake v. Shenango Furnace Co., 160 ... F. 887, 892, 88 C.C.A. 69, 74) ... When a ... defect ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT