Lear, Inc. v. Eddy

Decision Date30 March 2000
Citation749 A.2d 971
PartiesLEAR INC., Appellee, v. Roger EDDY, Appellant.
CourtPennsylvania Superior Court

Peter E. Horne, New Castle, for appellant.

Matthew T. Mangino, New Castle, for appellee.

Before POPOVICH, ORIE MELVIN and HESTER, JJ.

POPOVICH, J.

¶ 1 This is an appeal from the order entered in the Court of Common Pleas of Lawrence County on June 29, 1998, that granted appellee's motion for a directed verdict against appellant. The trial court denied appellant's post-trial motions, and this timely appeal ensued. Upon review, we reverse the order of the trial court and remand for a new trial. Herein, appellant asks the following:

Whether the trial court erred in granting Appellee's motion for a directed verdict on the basis that Appellant failed to produce sufficient evidence to establish that a bailment existed between the parties hereto?

Appellant's brief, at iv.

¶ 2 When reviewing a motion for a directed verdict, our scope of review is limited to determining whether the trial court abused its discretion or committed an error of law that controlled the outcome of the case. Perkins v. Desipio, 736 A.2d 608, 609 (Pa.Super.1999)(citing Childers v. Power Line Equipment Rentals, Inc., 452 Pa.Super. 94, 681 A.2d 201 (1996), appeal denied, 547 Pa. 735, 690 A.2d 236 (1997)). "A directed verdict may be granted only where the facts are clear and there is no room for doubt." Id. (citations omitted). "In deciding whether to grant a motion for a directed verdict, the trial court must consider the facts in the light most favorable to the nonmoving party and must accept as true all evidence which supports that party's contention and reject all adverse testimony." Id. (citations omitted).

¶ 3 The record reveals the following: On July 31, 1995, appellant contacted appellee1 concerning the transportation of equipment used by appellant in the plastic industry. Appellee inspected the equipment and the parties orally agreed that the equipment would be transported by appellee in two separate shipments. Originally, both shipments were to be delivered to Ellwood City. However, after appellee delivered the first shipment, appellant instructed that the second shipment was to be sent to Canonsburg, and appellee adjusted the price accordingly. Appellant did not specify an exact destination within Canonsburg for the second shipment. Instead, appellant asked appellee to store his equipment on appellee's premises until appellant determined a destination for the equipment. Appellant informed appellee that he would determine the location within three or four days.

¶ 4 Appellant was unable to determine a destination for the second shipment, and he never provided appellee with any further instructions concerning the equipment. Appellee eventually began assessing storage fees for appellant's equipment. On April 8, 1996, appellee filed a complaint against appellant for the cost of transportation, loading and storage of appellant's equipment in the second shipment. Near the time that the complaint was filed, appellant viewed his equipment upon the premises of appellee and considered the equipment demolished and useless. Appellant filed a counterclaim based on breach of a bailment agreement due to the damage suffered by the equipment in the second shipment. A jury trial commenced on July 9, 1997, and the trial court granted appellee's motion for a directed verdict against appellant as to appellant's counterclaim.

¶ 5 We now address appellant's argument that he set forth sufficient evidence to present a viable claim that a bailment existed between the parties. "A bailment is a delivery of personalty for the accomplishment of some purpose upon a contract, express or implied, that after the purpose has been fulfilled, it shall be redelivered to the person who delivered it, otherwise dealt with it according to his directions or kept until he reclaims it." Price v. Brown, 545 Pa. 216, 221, 680 A.2d 1149, 1151-52 (1996) (citation omitted). "While a contract of bailment may be implied, such a contract can arise only when the natural and just interpretation of the acts of the parties warrants such a conclusion." Riggs v. Commonwealth, Dept. of Transp., 76 Pa.Cmwlth. 227, 463 A.2d 1219, 1220-21 (1983)(citing Sparrow v. Airport Parking Co. of America, 221 Pa.Super. 32, 289 A.2d 87 (1972)). The standard of care required of either the bailor or bailee depends upon the type of bailment involved. Ferrick Excavating and Grading Co. v. Senger Trucking Co., 506 Pa. 181, 192-193, 484 A.2d 744, 750 (1984). Where the allegations of a bailment indicate a bailment for mutual benefit, the bailee is required to exercise ordinary diligence and is responsible for ordinary neglect. Price, 680 A.2d at 1152 n. 2.

¶ 6 Although the record indicates that appellee did not normally store equipment and assume the role of bailee, the "natural and just interpretation" of the parties' conduct indicates the existence of an implied contract for bailment. See Riggs, supra. Initially, the agreement between the parties only contemplated the transport of appellant's equipment. After the first shipment was completed, the parties altered their agreement by changing the destination of the second shipment. Moreover, appellee accepted custody of the second shipment and agreed to store the second shipment upon its premises until appellant instructed appellee where to send it. Clearly, appellee's acceptance of the second shipment evidenced "a delivery of personalty for the accomplishment of some purpose upon a[n] [implied] contract." Price, 680 A.2d at 1151-52. The "purpose" to be accomplished was the finding of a specific destination for the second shipment in Canonsburg. After the purpose was to be fulfilled, appellee agreed to otherwise deal with the second shipment according to appellant's directions by shipping appellant's equipment to Canonsburg. See Id.

¶ 7 In addition, we view the following behavior of appellee indicative of a bailor-bailee relationship. During appellant's delay in providing instructions, the second shipment remained secured upon appellee's premises. Appellee made efforts to protect the second shipment from the elements and began assessing storage fees upon appellant. In fact, this case stems from appellant's complaint seeking, among other things, storage fees from appellant. Therefore, we find that appellant presented a viable claim for the existence of a bailment, and the trial court erred in removing said claim from the jury's consideration.2

¶ 8 We reject the...

To continue reading

Request your trial
21 cases
  • Conquest v. WMC Mortg. Corp.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • 30 Marzo 2017
    ...to the person who delivered it, otherwise dealt with it according to his directions or kept until he reclaims it. 749 A.2d 971, 973 (Pa. Super. Ct. 2000) (quoting Price v. Brown , 545 Pa. 216,680 A.2d 1149, 1151–52 (1996) ). Plaintiff asserts that the "Mortgage Defendants received the insur......
  • In re Cmty. Health Sys., Inc.
    • United States
    • U.S. District Court — Northern District of Alabama
    • 12 Septiembre 2016
    ...the special purpose for the bailment is accomplished, or, if the property is not returned, an accounting will occur); Lear Inc. v. Eddy, 749 A. 2d 971, 973 (Pa. 2000) (same); Jackson v. Metro. Gov't. of Nashville & Davidson Cnty., 483 S.W. 2d 92, 94-95 (Tenn. 1972) (same); Hoye v Like, 958 ......
  • Sixth Angel Shepherd Rescue Inc. v. Susan West
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • 3 Mayo 2011
    ...of a plaintiff's property is an element of both conversion and bailment claims under Pennsylvania law. See Lear Inc. v. Eddy, 749 A.2d 971, 973–74 (Pa.Super.Ct.2000) (describing elements of bailment); Eisenhauer v. Clock Towers Assocs., 399 Pa.Super. 238, 582 A.2d 33, 36 (1990) (describing ......
  • Berg v. Nationwide Mut. Ins. Co.
    • United States
    • Pennsylvania Superior Court
    • 29 Junio 2012
    ...“A directed verdict may be granted only where the facts are clear and there is no room for doubt.” Id. (quoting Lear, Inc. v. Eddy, 749 A.2d 971, 973 (Pa.Super.2000)). “In deciding whether to grant a motion for a directed verdict, the trial court must consider the facts in the light most fa......
  • Request a trial to view additional results