Letourneau v. Citizens Utilities Co., 4-69

Decision Date07 October 1969
Docket NumberNo. 4-69,4-69
Citation128 Vt. 129,259 A.2d 21
CourtVermont Supreme Court
Parties, 82 P.U.R.3d 160 Petition of Paul LETOURNEAU et al., v. CITIZENS UTILITIES COMPANY.

Chester S. Ketcham, Middlebury, for the Public.

Clifton G. Parker, Morrisville, and Shea, Gallop, Climenko & Gould, New York, City, for defendant.

Before HOLDEN, C. J., and SHANGRAW, BARNEY, SMITH and KEYSER, JJ.

SHANGRAW, Justice.

This case is a rate proceeding which originally was heard on six days in October, November and December of 1963. The Public Service Board (hereafter called Board) filed its findings and final order on February 7, 1964, and certain amendments to the latter on March 4, 1964. Citizens Utilities Company (hereafter called Citizens) appealed to this Court which reversed the order of the Board and remanded the case for a hearing in accordance with the views expressed in its opinion. Petition of Paul Latourneau et al. v. Citizens Utilities Company, 125 Vt. 38, 209 A.2d 307 (April 6, 1965)

In its decision of February 7, 1964, the Board concluded that a 6.11 per cent rate of return for Citizens was reasonable and just. On this basis, the Board found that Citizens was entitled to a three per cent increase over its existing rates.

In the Latourneau case, supra, Citizens' appeal was directed to the exclusion of the Board of certain items submitted by Citizens as parts of the rate base. The utility also challenged the rate of return allowed by the commission.

This Court held in the above reported Latourneau case that the Board had erred in the following respects.

First, by adopting the figures of $95,000.00 as the net value of the so-called Prouty Rights acquired by Citizens in 1956 and so considered in the rate base by the Board. In this respect this Court observed that a later hearing would be required by the Board to properly determine the valuation of the Prouty Rights.

Second, in 1960 Citizens constructed an 115 KV-H frame transmission line from Highgate to Richford, Vermont, at a cost of $529,715. The Board eliminated from this part of the rate base the sum of $239,097. We held that the Board was in error in excluding this latter figure from the rate base.

Third, the elimination by the Board of a major portion of the salary of the president of Citizens from its Mutual Service Account.

In consideration of the foregoing a new determination would necessarily follow with respect to the rate base and rate of return. The Findings Re Test Year, of the Board, dated December 20, 1968, reveal that on two days in January and March 1966, hearings were held on the valuation of the so-called Prouty Rights. This was followed by findings and an interlocutory order on February 3, 1967. The latter was supplemented on March 3, 1967.

On September 28, 1967, Citizens petitioned the Board for redetermination of the outstanding statements from the Board to Citizens for reimbursable expenses in this rate case. The hearing on the petition was held on three days in November 1967 and February 1968. The Board filed its findings and a second interlocutory order on September 16, 1968.

A second prehearing conference after remand was held on September 4, 1968. A preliminary question was raised concerning the appropriate test year to be used in further hearings. Counsel for Citizens urged that 1962, which was used as the test year in the original proceeding in 1963, be used again. Counsel for the Public urged that 1967, the latest year for which complete data was available at the time of the conference, be used as the test year.

By the Board's findings relating to test year the Board determined that an interlocutory decision as to the appropriate test year 'will expedite disposition of the remaining issues in this rate case.'

The Board's findings continued by stating:

We are unable to find that use of the latest year for which complete data is available as the test year will unduly complicate disposition of this case. The two complex issues, determination of the rate base for the so-called Prouty Rights and determination of the rate base for the 115 KV-H frame line, already have been disposed of and are not affected by the choice of test year. Every year from 1964 through 1968 will have to be considered in the final disposition, regardless of the choice of the test year, to ascertain if there will be any recoupment of revenues relating to those years.

We find that the test year to be used on remand in this case should be the latest year for which complete data is available. Our third interlocutory order will be on the appropriate test year and will incorporate permission for an interlocutory appeal.

Then followed the Board's Third Interlocutory Order bearing date December 20, 1968 which reads:

IT IS HEREBY ORDERED that the test year to be used on remand in this case shall be the latest year for which complete data is available.

Permission is hereby granted to Citizens Utilities Company to take an appeal to the Supreme Court of the State of Vermont for determination of questions of law arising from our decision of the appropriate test year.

Pursuant to the foregoing order authorized under the provisions of 30 V.S.A. section 12 which incorporates 12 V.S.A. section 2386 by reference, the following question of law was certified by the Public Service Board to this Court for review.

Did the Public Service Board err by ruling that the test year to be used on remand in this rate case shall be the latest year for which complete data is available rather than 1962?

Citizens has duly appealed to this Court. Our only concern in the present posture of this case is limited to the question certified.

The ultimate object in this case is for the Board to determine a proper rate of return to Citizens and at a fair cost of electric energy to the public. This involves a balancing of the investor and consumer interests. A rate of return may be reasonable at one time, and become too high or too low by changes affecting opportunity for investment, the money market, and business conditions generally. In every rate case, there is left a reasonable margin of...

To continue reading

Request your trial
12 cases
  • Potomac Elec. Power Co. v. Public Serv. Com'n
    • United States
    • D.C. Court of Appeals
    • November 9, 1977
    ...in the test year will continue into the near future, when the prescribed rates will be in effect.9 See Letourneau v. Citizens Utilities Co., 128 Vt. 129, 259 A.2d 21, 24 (1969). Accordingly, a valid test period must be based upon the utility's most recent actual experience, with adjustments......
  • Central Vermont Public Service Corp., In re
    • United States
    • Vermont Supreme Court
    • January 13, 1984
    ...immediate future. In re Burlington Electric Light Department, 135 Vt. 114, 119, 373 A.2d 514, 518 (1977); Letourneau v. Citizens Utilities Co., 128 Vt. 129, 133, 259 A.2d 21, 23 (1969). As this Court has previously stated, "[r]ates are to be set for the future," id., i.e., "for the time per......
  • New England Tel. & Tel. Co., In re
    • United States
    • Vermont Supreme Court
    • November 8, 1977
    ...phone, and that the submissions unduly complicated the investigation in violation of the Letourneau rule. (Letourneau v. Citizens Utilities Co., 128 Vt. 129, 134, 259 A.2d 21 (1969).) of any finding or provision of this January 15, 1976, preliminary order that it considered clearly erroneou......
  • Petition of Green Mountain Power Corp.
    • United States
    • Vermont Supreme Court
    • April 26, 1973
    ...and have been consistently followed by many cases, in many jurisdictions, including Vermont. Petition of Letourneau v. Citizens Utilities Co., 128 Vt. 129, 133-134, 259 A.2d 21 (1969); Petition of New England Tel. & Tel. Co., 120 Vt. 181, 191, 136 A.2d 357 (1957); Petition of Central Vermon......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT