LOGISTICS SYSTEMS v. PROFESSIONAL TRANSP.

Decision Date11 July 2002
Citation803 A.2d 776
PartiesPITTSBURGH LOGISTICS SYSTEMS, INC., Appellee, v. PROFESSIONAL TRANSPORTATION AND LOGISTICS, INC., Appellant.
CourtPennsylvania Superior Court

Samuel H. Simon, Pittsburgh, for appellant.

W. David Slomski, Pittsburgh, for appellee.

Before FORD ELLIOTT, LALLY-GREEN, and HESTER, JJ.

LALLY-GREEN, J.

¶ 1 Appellant, Professional Transportation and Logistics, Inc., appeals the trial court order dated December 5, 2001, overruling, in part, its preliminary objections in the nature of a petition to compel arbitration. We reverse.

¶ 2 The facts as found by the trial court are as follows:

In 1999, the parties entered into an agreement under which [Appellant] was to provide services to [Pittsburgh Logistics Systems, Inc., (PLS)] relating to transportation services to [PLS'] customers. The agreement spelled out specific responsibilities of the parties and contained the following language pertinent to the issue before the court[.]

"All claims, disputes and other matters and questions arising out of or relating to this agreement, or the breach thereof, shall be resolved by means of arbitration in accordance with the commercial rules of the American Arbitration Association...."
Exhibit A to the Complaint, Paragraph 12.
On July 5, 2001, [PLS] initiated this action by filing a Complaint against [Appellant]. The Complaint sets forth four separate causes of action in four counts. Count 1 is for intentional interference with a prospective contractual relationship; Count 2 is for breach of contract; Count 3 is for breach of fiduciary and common law duties; and Count 4 is for misappropriation of trade secrets.
The gravamen of each cause of action is [that Appellant], while it [was] contractually obligated to assist [PLS] in securing new customers, used confidential and proprietary information of [PLS] to assist a competitor in securing Niagra LaSalle, Inc. as a customer instead of [PLS]. In Count 1, [PLS] alleges that the foregoing conduct of [Appellant] caused it to lose a financial opportunity and profits. In Count 2, [PLS] alleges that the foregoing conduct of [Appellant] constituted a breach of their contract resulting in unspecified damages. In Count 3, [PLS] alleges that [Appellant] had fiduciary duties to protect and hold confidential the trade secrets and proprietary information of [PLS] as a result of the contract between the parties and the foregoing conduct constituted a breach of those fiduciary duties. In Count 4, [PLS] alleges that the defendant wrongfully used [PLS'] trade secrets or disclosed them to others as a result of which [PLS] lost business and future potential business as well as other unknown damages.

Trial Court Opinion, 12/5/01, at 1-2.

¶ 3 Appellant filed preliminary objections to PLS' complaint, claiming that all counts contained therein are to be resolved by arbitration pursuant to the agreement to arbitrate contained in the parties' contract. The trial court overruled the preliminary objections as to Counts I, III, and IV, but sustained them as to Count II, dismissing that Count. This timely appeal followed.1 ¶ 4 Appellant presents one issue for our review:

I. Whether the Honorable Trial Judge abused his discretion and/or committed an error of law by failing to follow case precedent set forth by the Pennsylvania Supreme Court in Ambridge Borough Water Authority v. Columbia, 458 Pa. 546, 328 A.2d 498 (1974) and the Pennsylvania Superior Court in Shadduck v. Christopher J. Kaclik, Inc., 713 A.2d 635 (Pa.Super.1998) and thus, abused his discretion and/or erred by not holding that all claims filed in [PLS'] Complaint be submitted to compulsory arbitration as required in accordance with the agreement between the parties or by not dismissing the entire action.

Appellant's Brief at 4.

¶ 5 Our standard of review of a denial of preliminary objections in the nature of a petition to compel arbitration "is limited to determining whether the trial court's findings are supported by substantial evidence and whether the trial court abused its discretion in denying the petition." Midomo Co., Inc. v. Presbyterian Hous. Dev. Co., 739 A.2d 180, 186 (Pa.Super.1999).

¶ 6 Where a party to a civil action seeks to compel arbitration of that action, a two-part test is employed to determine if arbitration is required. First, the trial court must determine if a valid agreement to arbitrate exists between the parties. Id. Second, if the trial court determines that such an agreement does exist, it must then determine if the dispute involved is within the scope of the arbitration provision. Id. "The scope of arbitration is determined by the intention of the parties as ascertained in accordance with the rules governing contracts generally." Henning v. State Farm Mut. Automobile Ins. Co., 795 A.2d 994, 996 (Pa.Super.2002), citing, State Farm Mut. Automobile Ins. Co. v. Coviello, 233 F.3d 710, 716 (3rd Cir.2000).

¶ 7 Appellant argues that Ambridge, supra, and Shadduck, supra, require PLS to litigate all of its claims against Appellant in arbitration pursuant to the contract between the parties. The clause providing for arbitration of disputes states in pertinent part:

All claims, disputes and other matters and questions arising out of or relating to this Agreement, or the breach thereof, shall be resolved by means of arbitration in accordance with the commercial rules of the American Arbitration Association, unless the parties mutually agree otherwise.

Exhibit "A" to PLS' Complaint at 5.

¶ 8 Since neither party contests the existence or validity of the agreement to arbitrate, our review focuses on whether the claims are within the scope of the agreement to arbitrate. Thus, we first address Ambridge and Shadduck.

¶ 9 In Ambridge, our Supreme Court held that where a dispute arises between parties to a contract concerning the contract and the contract contains an unlimited arbitration clause, the parties must resolve their dispute through arbitration. Ambridge, 328 A.2d at 501-502. There, an employee claimed a right to payment under the contract and compensation for accrued vacation time. Id. at 499-500. The employer sought to have its employment contract with an employee declared null and void and sought to enjoin the employee from seeking arbitration. Id. at 499.

¶ 10 The Court first looked to the language of the arbitration clause which provided: "any controversy or claim arising out of or relating to this Agreement or the breach thereof shall be settled by arbitration in accordance with the rules or the American Arbitration Association...." Id. at 499. The Court held that a valid contract to arbitrate existed and that the dispute fell within the scope of the arbitration clause because the employee's claim went directly to obligations created under the contract. Id. at 501-502.

¶ 11 In Shadduck, this Court held that an agreement to arbitrate disputes arising from the contract encompasses tort claims where the facts which support a tort action also support a breach of contract action. Shadduck, 713 A.2d at 638-639. There, the homeowners contracted with the builder to construct a home. Id. at 636. The contract included a clause providing for arbitration of "[a]ll claims or disputes between the Contractor and the Owner arising out of, or relating to, this Contract or the breach thereof shall be decided by arbitration...." Id. at 637. After completion of the home, the homeowners sued the builder claiming that the builder did not construct the home in accordance with his oral promises and the contract specifications. Id. at 636, 638. The Shadduck Court noted that "a claim's substance, not its styling, is to control whether the complaining party must proceed to arbitration or may file in the court of common pleas." Id. at 637. The Court held that because the factual averments of the tort claims underlie the breach of contract claims, the claims were not temporally or factually distinct and all claims were covered by the arbitration agreement. Id. at 638-639.

¶ 12 The instant case is governed by both Ambridge and Shadduck. Here, the language of the arbitration clause is substantially similar to that found in Ambridge and Shadduck. Thus, we examine whether the disputes involved are within the scope of the arbitration provision. PLS alleges the following in its complaint:

* * *

3. [PLS] is a transportation logistics company possessing certain proprietary and confidential information, including, but not limited [to] technological information, performance data, financial information, procedures, customer lists, information and prospects, marketing studies and sales plans, proposals, costs and pricing information, and analysis of competitors, all of which have substantial value to [PLS] and which information [PLS] takes great care to maintain as confidential and proprietary information.

4. Sometime in 1995 or 1996, [PLS] and [Appellant] began a business relationship whereby [Appellant] would provide services to [PLS] for non-flatbed, less-than-truck-load transportation services which [PLS] provided and was to provide to its current and future customers.

5. On April 28, 1999, the parties entered into a formal relationship which inter alia detailed the services which [Appellant] was to provide to [PLS] and further defined the terms of the parties relationship. A true and correct copy of this contract is attached hereto, incorporated herewith and is marked Exhibit "A".

* * *

7. During the course of the parties[`] contractual relationship, [Appellant] learned of, was exposed to and had access to proprietary and confidential information of [PLS] as described in paragraph 3, ....

8. The Agreement between the parties, which is referenced as Exhibit "A" to this Complaint, contains a provision whereby the parties acknowledge the confidential nature of their relationship.

9. One of the agreed upon services [Appellant] was to provide to [PLS] was to assist [PLS] in the...

To continue reading

Request your trial
26 cases
  • Woods at Wayne Homeowners Ass'n v. Gambone Bros. Dev. Co.
    • United States
    • Pennsylvania Superior Court
    • 6 Septiembre 2013
    ...Ct. 2004); Flender Corp. v. Tippins Int'l, Inc., 830 A.2d 1279 (Pa. Super. Ct. 2003); Pittsburgh Logistics Sys., Inc. v. Prof'l Transp. & Logistics, Inc., 803 A.2d 776, 778 n.1 (Pa. Super. Ct. 2002); Henning v. State Farm Mut. Auto. Ins. Co., 795 A.2d 994 (Pa. Super. Ct. 2002); Levy v. Lene......
  • Taylor v. Extendicare Health Facilities, Inc.
    • United States
    • Pennsylvania Superior Court
    • 2 Abril 2015
    ...determine whether the trial court's findings are supported by substantial evidence. Pittsburgh Logistics Systems, Inc. v. Professional Transportation and Logistics, Inc., 803 A.2d 776, 779 (Pa.Super.2002). In doing so, we employ a two-part test to determine whether the trial court should ha......
  • Saltzman v. Thomas Jefferson Univ. Hosps., Inc.
    • United States
    • Pennsylvania Superior Court
    • 30 Junio 2017
    ...court to rule that the arbitration provision does not apply to the negligence claim."); Pittsburgh Logistics Sys., Inc. v. Prof'l Transp. and Logistics, Inc., 803 A.2d 776, 779 (Pa.Super. 2002) (holding that tort action for misappropriation of trade secrets, breach of common law fiduciary d......
  • Dale Supply Company v. York International Corp.
    • United States
    • Tennessee Court of Appeals
    • 9 Octubre 2003
    ...Agreement or the breach of any term of provision hereof." Id. at 1108-09. See also Pittsburgh Logistics Systems, Inc. v. Professional Transportation & Logistics, Inc.,803 A.2d 776, 779 (Pa. Super. Ct. 2002) (finding tortious interference claim within scope of agreement to arbitrate "all cla......
  • Request a trial to view additional results