Loranger Const. Corp. v. E. F. Hauserman Co.

Decision Date05 December 1978
Citation384 N.E.2d 176,376 Mass. 757
PartiesLORANGER CONSTRUCTION CORPORATION v. E. F. HAUSERMAN COMPANY.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

James M. Cronin, New Bedford, for defendant.

Thomas Crotty, Bridgewater, for plaintiff.

Before HENNESSEY, C. J., and QUIRICO, BRAUCHER, WILKINS and ABRAMS, JJ.

BRAUCHER, Justice.

The plaintiff, a contractor, was preparing its bid for construction at the Cape Cod Community College. It received an "estimate" of $15,900 for movable steel partitions from the defendant, and used the estimate in preparing the bid it submitted. The construction contract was awarded to the plaintiff, the defendant refused to perform in accordance with its estimate, and the plaintiff engaged another company to supply and install the partitions for $23,000. The Appeals Court upheld an award of damages to the plaintiff, we allowed the defendant's petition for further appellate review, and we affirm the judgment for the plaintiff.

The action was filed in 1970. Demurrers to the declaration and to an amended declaration were sustained, and leave to file a second amended declaration was then denied, the judge "being of opinion there is no cause of action." The Appeals Court held that count 1 of the amended declaration did set out a cause of action, and reversed the order denying leave to amend. 1 Mass.App. 801, 294 N.E.2d 453 (1973). Thereafter the plaintiff filed an amended declaration containing four counts, the case was tried to a jury in October, 1974, and a verdict was returned for the plaintiff in the amount of $7,100. The Appeals Court held that the plaintiff was "foreclosed from recovery on any traditional contract theory," but could "recover on the theory of promissory estoppel, a basis for recovery not previously explicitly accepted in the courts of this Commonwealth." --- Mass.App. ---, --- A, 374 N.E.2d 306, 308 (1978). The defendant argues that "the adoption of this new theory of law is procedurally unfair, unwarranted by the facts in the case, and contrary to the statutory policy of the Commonwealth."

We summarize the evidence most favorable to the plaintiff. On May 20, 1968, the plaintiff was preparing its bid to become general contractor on the construction project. The specifications called for movable metal partitions from the defendant or one of two other suppliers, "or equal." About fifteen days earlier, a sales engineer employed by the defendant had prepared a "quotation" or "estimate" of $15,900 for supplying and installing the partitions. The figure was based on information received from the architect's office, and the engineer knew that the general contractor would submit a bid based on such estimates from subcontractors. The estimate was given to the plaintiff by telephone on May 20, 1968; it was also given to other general contractors. The engineer waited until shortly before bids were due on the general contract to prevent the general contractor from shopping for a lower price from other subcontractors. The plaintiff received no other quotations on the partitions, and used the defendant's quotation in preparing the bid on the general contract, submitted the same day.

The general contract was awarded to the plaintiff on June 21 or 26, 1968. Some time in August or September, the plaintiff informed the defendant that it was getting ready to award the partition contract and asked whether it had the defendant's lowest price. Thereafter, on September 12, 1968, the plaintiff sent the defendant an unsigned subcontract form based on the $15,900 figure. The defendant rejected the subcontract, and the plaintiff engaged another company to supply and install the partitions for $23,000. The partition work was not scheduled to begin until the summer of 1969; in fact, work began in the summer of 1970, and the last payment for it was made in 1972.

At the close of the plaintiff's evidence, it waived counts 2, 3 and 4 of the declaration. The defendant rested and moved for a directed verdict. The motion was denied. After verdict, the defendant moved for judgment notwithstanding the verdict, and that motion was denied. The questions argued to us relate to the question whether the evidence made a case for the jury.

1. The offer or promise. The defendant argues that the "quotation" or "estimate" made by its sales engineer was not an offer or promise, but merely an invitation to further negotiations, citing Cannavino & Shea, Inc. v. Water Works Supply Corp., 361 Mass. 363, 366, 280 N.E.2d 147 (1972). But the Cannavino case involved the circulation of a price list without specification of quantity. Here there was more; the defendant was to do a portion of the work called for by the plans and specifications. Of course, it was possible for the sales engineer to invite negotiations or offers. See Kuzmeskus v. Pickup Motor Co., 330 Mass. 490, 492-494, 115 N.E.2d 461 (1953). But it was also possible for him to make a commitment. His employer stated in answer to interrogatories that it was "unable to determine whether or not an employee of the defendant spoke with any of the plaintiff's employees on or about May 20, 1968," and the only direct evidence of the estimate was the testimony of the engineer. We think the jury were warranted in resolving ambiguities in his testimony against the defendant, and in finding that the estimate, in the circumstances, was an offer or promise. See Jaybe Constr. Co. v. Beco, Inc., 3 Conn.Cir.Ct. 406, 410-411, 216 A.2d 208 (1965).

2. Reliance on the promise. It seems clear enough, as the Appeals Court held, that the evidence made a case for the jury on the basis of the plaintiff's reliance on the defendant's promise. "An offer which the offeror should reasonably expect to induce action or forebearance of a substantial character on the part of the offeree before acceptance and which does induce such action or forebearance is binding as an option contract to the extent necessary to avoid injustice." Restatement (Second) of Contracts § 89B(2) and Illustration 6 (Tent. Drafts Nos. 1-7, 1973). This doctrine is not so novel as the defendant contends. In addition to the authorities cited by the Appeals Court, see Cannavino & Shea, Inc. v. Water Works Supply Corp., 361 Mass. 363, 365-366, 280 N.E.2d 147 (1972); Crane Co. v. Park Constr. Co., 356 Mass. 13, 17, 247 N.E.2d 591 (1969). 1 When a promise is enforceable in whole or in part by virtue of reliance, it is a "contract," and it is enforceable pursuant to a "traditional contract theory" antedating the modern doctrine of consideration. See Sullivan v. O'Connor, 363 Mass. 579, 588 n. 6, 296 N.E.2d 183 (1973); Restatement (Second) of Contracts § 90, Comment A (Tent. Drafts Nos. 1-7, 1973). We do not use the expression "promissory estoppel," since it tends to confusion rather than clarity.

3. Procedural unfairness. The defendant contends that the decision of the Appeals Court, resting on "the new theory of promissory estoppel," departed from the pleadings and from the theory on which the case was tried. So far as the pleadings are concerned, count 1 of the declaration alleged an exchange of promise for promise and also the submission of a bid by the plaintiff in reliance on the agreement between the parties. If either allegation was sustained by proof, the other could be treated as surplusage. The pleadings could have been amended to conform to the evidence, even after judgment; failure so to amend does not affect the result of the trial. Mass.R.Civ.P. 15(b), 365 Mass. 761 (1974). Janke Constr. Co. v. Vulcan Materials Co., 527 F.2d 772, 776 (7th Cir. 1976). Schafer v. Fraser, 206 Or. 446, 481, 290 P.2d 190 (1955). See Babler v. Roelli, 39 Wis.2d 566, 572-573, 159 N.W.2d 694 (1968). The record does not disclose any authorization by the judge for the pleadings to go to the jury. See Rule 7 of the Superior Court (1974).

In view of the defendant's claim of procedural unfairness, we requested and received a transcript of the judge's charge to the jury. The defendant does not assert any error with respect to the charge, and did not include the charge in its record appendix. We do not treat the charge as the "law of the case." See Commonwealth v. Krasner, 360 Mass. 848, 849, 274 N.E.2d 347 (1971), and cases cited. But we find that the case was presented to the jury on the basis of offer, acceptance and consideration; there was no reference in the charge to reliance on a promise. We therefore cannot attribute to the jury a finding that the offer or promise of the defendant induced action "of a substantial character" on the part of the plaintiff. We consider the case on the basis on which it was submitted to the jury. See Dalton v. Post Publishing Co., 328 Mass. 595, 598-599, 105 N.E.2d 385 (1952).

Pursuant to the charge and on the evidence before them, the jury might have found that the defendant's offer was accepted in any one of three ways. First, there might have been an exchange of promises in the plaintiff's telephone conversation with the defendant's engineer, before the plaintiff's bid was submitted. Second, the offer might have been accepted by the doing of an act, using the defendant's estimate in submitting the plaintiff's bid. Acceptance in this way might be complete without notification to the offeror. Bishop v. Eaton, 161 Mass. 496, 499, 37 N.E. 665 (1894). See Restatement (Second) of Contracts § 56(1), (2)(c) (Tent. Drafts Nos. 1-7, 1973). Finally, the offer might have remained outstanding, unrevoked, until September, 1968, or it might have been renewed or extended when the plaintiff asked whether...

To continue reading

Request your trial
158 cases
  • Guckenberger v. Boston University
    • United States
    • U.S. District Court — District of Massachusetts
    • August 15, 1997
    ...parties, a party reasonably relying on a promise may prevail under a theory of promissory estoppel. See Loranger Constr. Corp. v. E.F. Hauserman Co., 376 Mass. 757, 384 N.E.2d 176 (1978) (citing Restatement (Second) of Contracts, § 89B(2) (1973)). A claim in promissory estoppel is essential......
  • Trent Partners and Associates v. Digital Equip.
    • United States
    • U.S. District Court — District of Massachusetts
    • December 22, 1999
    ...Rhode Island Hosp. Trust Nat'l Bank v. Varadian, 419 Mass. 841, 850, 647 N.E.2d 1174 (1995); Loranger Constr. Corp. v. E.F. Hauserman Co., 376 Mass. 757, 761, 384 N.E.2d 176 (1978). In practice, however, this distinction has not altered the elements of such a claim from the traditional prom......
  • Brewster Wallcovering v. Blue Mountain
    • United States
    • Appeals Court of Massachusetts
    • April 6, 2007
    ...found to have existed between the parties, a finding we conclude was supported on the record. See Loranger Constr. Corp. v. E.F. Hauserman Co., 376 Mass. 757, 763, 384 N.E.2d 176 (1978). 34. We reject Brewster's argument that Blue Mountain waived its right to challenge the sufficiency of th......
  • Piantes v. Pepperidge Farm, Inc.
    • United States
    • U.S. District Court — District of Massachusetts
    • February 1, 1995
    ...relied to his detriment, and where injustice can be avoided only by enforcement of the promise. Loranger Construction Corp. v. E.F. Hauserman Co., 6 Mass.App.Ct. 152, 154, 374 N.E.2d 306 (1978) aff'd 376 Mass. 757, 384 N.E.2d 176 (1978). See also Cambridgeport Savings Bank v. Boersner, 413 ......
  • Request a trial to view additional results
2 books & journal articles
  • The Four Phases of Promissory Estoppel
    • United States
    • Seattle University School of Law Seattle University Law Review No. 20-01, September 1996
    • Invalid date
    ...use the expression "promissory estoppel," since it tends to confusion rather than clarity. Loranger Constr. Corp. v. E.F. Hauserman Co., 384 N.E.2d 176, 179 (Mass. 1978). The court in Greenstein v. Flatley, 474 N.E.2d 1130, 1134 (Mass. Ct. App. 1985), explains that Justice Braucher in Loran......
  • Post-award Bid Shopping in the Colorado Public Construction Industry
    • United States
    • Colorado Bar Association Colorado Lawyer No. 18-9, September 1989
    • Invalid date
    ...1963). 9. Restatement (Second) of Contracts§ 87(2), Illus. 6 (1981). 10. See, e.g., Loranger Construction Corp. v. E. F. Hauserman Co., 376 Mass. 757, 384 N.E.2d 176 (1978), n. 1 at 179, and authorities cited therein. See also, Restatement (Second) of Contracts§§ 87(2), Illus. 6 and 90 (198......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT