Lord Const. Co. v. United States

Decision Date20 September 1928
Docket NumberNo. 3643.,3643.
Citation28 F.2d 340
PartiesLORD CONST. CO. et al. v. UNITED STATES, to Use of W. E. SEXTON CO., Inc.
CourtU.S. Court of Appeals — Third Circuit

Edwards & Smith, of Jersey City, N. J. (Edwin F. Smith, of Jersey City, N. J., of counsel), for plaintiffs in error.

George W. C. McCarter, of Newark, N. J., for defendant in error.

Before BUFFINGTON, WOOLLEY, and DAVIS, Circuit Judges.

DAVIS, Circuit Judge.

This case was brought here for the review of a judgment against the defendants, Lord Construction Company and Globe Indemnity Company, in the sum of $39,601.73.

The United States, acting through the Navy Department, was engaged in constructing the naval hangar at Lakehurst, N. J. On March 19, 1921, it entered into a contract with the Lord Construction Company to do certain work in erecting the hangar and upon the grounds surrounding it. The Globe Indemnity Company became surety on the bond given by the Lord Construction Company to the United States for the faithful performance of the contract, and was joined as defendant because of the liability it thus assumed.

On April 2, 1921, the Lord Company entered into a contract with the W. E. Sexton Company, plaintiff below, wherein it was agreed that the Sexton Company should perform certain parts of the work included in the contract between the Lord Company and the United States. After some of the work had been done, difficulties arose between the plaintiff and defendant Lord Company, and on July 23, 1921, they entered into another contract covering the same work which was included in the old contract, but it was stated with greater detail and formality.

The Sexton Company then began to perform the work specified in the contract and continued it until February 3, 1922, when difficulties again arose and the Lord Company terminated the contract.

The Sexton Company thereupon brought suit against the defendants under the authority of the Act of August 13, 1894, as amended February 24, 1905 (40 USCA § 270), in the name of the United States to its use. It alleged that it had performed all the work "and all conditions and things by it to be performed and done to entitle it to be paid for the said labor and materials." In short, it sued for the balance due it under the contract, for the value of certain work alleged to be extra and for damages it claimed to have sustained by reason of delays occasioned by the Lord Company. The Lord Company, in answer, alleged that the plaintiff defaulted in performing its contract; that it became necessary to terminate the contract, as it could do under the terms thereof, and to complete the work itself, which it did at a cost exceeding the contract price. It denied liability for the extra work, and filed a counterclaim for the excess cost of finishing the work. At the trial, the plaintiff withdrew the claim for damages occasioned by delay. The jury found for the plaintiff on its complaint and against the defendant on its counterclaim.

From the assignments of error, two questions arise: (1) Did the court err in refusing to withdraw four items for extra work from the consideration of the jury? (2) Did the court err in admitting in evidence a letter written by the Public Works officer to the Bureau of Yards and Docks?

The four items of extra work which the court refused to withdraw are: (1) Grading north side of hangar, $6,140.75; (2) excavation north side of hangar, $1,206.80; (3) 31 barrels of cement, $105.40; (4) 914 feet of sewer pipe, $1,096.80."

Defendants say that these charges were admittedly for extra work, and should not therefore have been submitted to the consideration of the jury because the work was not "authorized in writing by the contractor to the subcontractor" as required by the contract, and consequently the plaintiff may not receive compensation for the work done or materials furnished. The plaintiff admits that there was no written order given for the work by the contractor to the subcontractor, but says there was a parol agreement between the parties that the work should be done and the written authorization was thereby waived.

A written contract may be waived by a parol agreement, but the evidence establishing it must (1) be clear and of a satisfactory character; (2) clearly show a distinct agreement by the parties that the work shall be deemed extra work; (3) show a definite agreement by the owner or contractor to pay extra for the extra work. Headley v. Cavileer, 82 N. J. Law, 635, 82 A. 908, 48 L. R. A. (N. S.) 564.

This was a New Jersey contract, and is to be controlled by the law of New Jersey. If, however, it be contended that it is not a New Jersey contract, then it is controlled by federal decisions, and they are to the same effect. The Sappho, 94 F. 545 (C. C. A. 4); Jefferson Hotel v. Brumbaugh, 168 F. 867 (C. C. A. 4); United Steel Co. v. Casey (C. C. A.) 262 F. 889. In the case of Riverside Township v. Stewart (C. C. A.) 211 F. 873 (a New Jersey case), we said:

"The next question concerns the right of the plaintiff to recover for extras not covered by the contract and for which the plaintiff produced no written order signed by the engineer and the township committee. In that regard the contract provided that the plaintiff should not be entitled `to receive payment for any extra work as extra work unless such bill for extras be accompanied by an order in writing from the engineer and said township committee, who shall fix the price for such work.' The court admitted proof which tended to show that at regular meetings of the township committee and acting as such the committee, the engineer and the plaintiff fully discussed and considered such extra items and work, and the plaintiff was then directed to proceed with them; they saying `their word was as good as their contract.' That a contract requirement such as here provided may be subsequently waived by the parties is established by the authorities. Headley...

To continue reading

Request your trial
4 cases
  • Campbell Building Co. v. State Road Commission
    • United States
    • Utah Supreme Court
    • August 3, 1937
    ... ... v ... Kansas City Bridge Co. (C.C.A.) 81 F.2d ... 689; United Contracting Co. v. Duby , 134 ... Ore. 1, 292 P. 309. In an action ... waiving immunity from suit, as in some states ... Arkansas [95 Utah 252] State Highway Comm ... v. Nelson ... Co. v ... Lentz , 40 Ariz. 46, 9 P.2d 408; Lord Const ... Co. v. United States (C.C.A. 3) 28 F.2d 340 ... ...
  • Ross Engineering Co. v. Pace
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • January 8, 1946
    ...McHugh Sons, Inc. v. United States, 99 Ct.Cl. 414; Feuchtwanger v. Manitowoc Malting Co., 7 Cir., 187 F. 713; Lord Construction Co. v. United States, 3 Cir., 28 F.2d 340; Kelly v. St. Michael's Roman Catholic Church, 148 App.Div. 767, 133 N.Y.S. 328; Stokes Bros. Inc. v. Drefs, 244 App.Div.......
  • United States v. Henke Const. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • July 18, 1946
    ...was applicable, compliance with the provision was waived. In support of this contention they cite Lord Const. Co. v. United States, to Use of W. E. Sexton Co., 3 Cir., 28 F.2d 340. Our attention is called to numerous letters and telegrams relating to both brick and tile controversies but in......
  • Ferber Company v. Ondrick
    • United States
    • U.S. Court of Appeals — First Circuit
    • November 28, 1962
    ...of course, rudimentary that a contractual requirement that agreements be in writing may be waived. Lord Constr. Co. v. United States ex rel. W. E. Sexton Co., 3 Cir., 1928, 28 F.2d 340; Zarthar v. Saliba, 1933, 282 Mass. 558, 185 N.E. 367. The fact, however, that Cristello may have possesse......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT