Luick v. Graybar Electric Company, Inc.

Decision Date13 February 1973
Docket Number72-1217.,No. 72-1216,72-1216
Citation473 F.2d 1360
PartiesDale LUICK, doing business as Luick Construction Company, Plaintiff-Appellant, v. GRAYBAR ELECTRIC COMPANY, INC., Defendant-Appellee. GRAYBAR ELECTRIC COMPANY, INC., a corporation, Plaintiff-Appellee, v. NATIONAL SURETY CORPORATION, Defendant-Appellant.
CourtU.S. Court of Appeals — Eighth Circuit

Bruce E. Bohlman, Fargo, N. D., for appellants.

Michael L. Culhane, Minneapolis, Minn., for appellee.

Before MATTHES, Chief Judge, and GIBSON and HEANEY, Circuit Judges.

GIBSON, Circuit Judge.

This appeal concerns two separately filed actions, one in North Dakota and the other in Minnesota. The cases involve the same parties with the exception that the surety was sued in the Minnesota case. The Minnesota case subsequently was transferred to North Dakota and the cases although not consolidated were discussed together at a pretrial hearing and disposed of separately in a single unpublished memorandum by the late Judge George S. Register. They involve common questions of law and fact and will be considered together in this opinion. The cases concern an alleged breach of contract for late delivery of materials by a seller and the refusal of the buyer to pay for the unpaid balance due on the purchase.

In May 1968, Dale Luick, doing business as Luick Construction Company, contracted with Graybar Electric Company to purchase underground cable for $142,514 to be shipped the second week of July 1968 to Badger, Minnesota, for a job with Wickstrom Telephone Company. Graybar, unable to get delivery from its suppliers, did not deliver the cable to Luick in substantial amounts until November 1968. Luick, who was supposed to complete the Wickstrom installation by the end of 1968, did not complete the work until spring 1969.

In June 1969, Luick and Graybar again contracted for Graybar to sell $214,000 of cable to be delivered on or before August 1, 1969, to Underwood, Minnesota, for a job with Park Region Telephone Company, which was scheduled to be completed by the end of 1969. Graybar could not deliver the cable in substantial amounts until late October 1969. Luick completed the Park Region installation in spring 1970.

In October 1970, Luick filed suit in the North Dakota state court against Graybar for lost profits, the rental value of his idle equipment, and added construction costs for the Wickstrom and Park Region installations in the approximate amount of $230,000. On Graybar's motion, the case was removed to the Federal District Court of North Dakota.1 Graybar answered denying that it was liable for late delivery damages due to exculpatory clauses allegedly contained in contracts for both installations and counterclaimed for the value of the unpaid materials, $85,864.49. While Luick's suit was pending, Graybar filed suit against National Surety Corporation, Luick's bonding company, in Minnesota Federal District Court in December 1970 for the value of the unpaid materials and interest. National Surety answered alleging Luick's same claim for late delivery damages. This case was transferred to North Dakota on April 1, 1971.2

On July 23, 1971, Graybar, as plaintiff, moved for a summary judgment against National Surety in case No. 72-1217. On March 2, 1972, the District Court, in its unpublished memorandum and order, granted Graybar's motion for summary judgment and dismissed National Surety's counterclaim. On the same day and in the same order, the District Court, on its own motion, dismissed Luick's complaint (No. 72-1216) for failure to state a cause of action.

Since National Surety did not respond to Graybar's requests for admissions, the validity of Graybar's claim for materials furnished stands admitted. No real issue has been raised on the delivery or value of the materials furnished. Applying the summary judgment provision of Rule 56(c), Fed.R.Civ.P., the District Court found that there was "no genuine issue as to any material fact." In making this conclusion, the District Court found that National Surety did not respond to Graybar's requests for admissions under Fed.R.Civ.P. 36(a) and therefore admitted all matters contained in the requests. Graybar had requested that National Surety admit that the materials had been delivered for the Park Region job and that Luick owed $85,864.49, as a fair value for the delivered and unpaid materials. These requests were the basis of the Graybar complaint and its counterclaim in Luick's suit.

Unanswered requests for admissions render the matter requested conclusively established for the purpose of that suit. Fed.R.Civ.P. 36(a) and (b). See Moore's Fed.Prac. § 36.01(7). Also a summary judgment may be based on admitted matter. Moosman v. Joseph P. Blitz, Inc., 358 F.2d 686, 688 (2d Cir. 1966). We agree with the District Court's determination on the contract amount owed by Luick to Graybar.

This leaves for consideration the question of whether the late delivery of the materials gave rise to an actionable claim for damages by Luick. We think Luick's suit for damages raises substantial factual issues that are not properly susceptible of determination in a summary judgment proceeding.

Graybar contends that an exculpatory clause3 in the alleged contracts exonerated Graybar from any liability for damages due to late delivery, and further that this exclusion-of-remedies clause is valid and enforceable under Minn.Stat.Ann. § 336.2-719 (1965) (a provision of the Uniform Commercial Code in Minnesota).4 The District Court held that the exculpatory clauses in the alleged contracts were enforceable, that the late delivery damages were special or consequential under Minnesota law, and, therefore, that Graybar was not liable for the damages attributable to late delivery. This well may be but we don't think that conclusion can be reached in a summary judgment proceeding.

The question of whether these exculpatory clauses are enforceable raises genuine factual issues, since Luick argues that there is a dispute whether these exculpatory clauses were included within the terms and conditions of the purchase contracts. The District Court assumed they were, and, again well they might be, as the exculpatory clauses are in each contract as No. 6 of the printed form on Terms and Conditions of Sale. However, Luick contends otherwise, and from the available record it is unclear exactly what written documents constituted the parties' contracts. In addition, Luick raises the issue of "unconscionability" of the exculpatory clauses. Since Luick has not admitted through any failure to answer a request for admissions that these exculpatory clauses were included in the contracts, he should be allowed to introduce evidence concerning the formation of the two contracts and the issue of unconscionability.

We, therefore, think Luick's complaint raises factual issues which preclude the issuance of a summary judgment. Parmelee v. Chicago Eye Shield Co., 157 F.2d 582, 586-587 (8th Cir. 1946). Because of the drastic nature of the summary judgment entry, the right to that judgment must be shown "with such clarity as to leave no room for controversy . . . and the other party must not be entitled to recover under any discernible circumstances." Traylor v. Black, Sivalls & Bryson, Inc., 189 F.2d 213, 216 (8th Cir. 1951); accord, Cervantes v. Times, Inc., 464 F.2d 986, 993 (8th Cir. 1972). In order for us to hold that the summary judgment procedure disposing of Luick's claim was proper, we would have to rule on the basis of...

To continue reading

Request your trial
45 cases
  • J. A. Jones Const. Co. v. City of Dover
    • United States
    • Delaware Superior Court
    • February 28, 1977
    ...Dow Corning Corporation v. Capitol Aviation, Inc., supra; Jones & McKnight v. Birdsboro Corporation, supra; Luick v. Graybar Electric Company, Inc., 8 Cir., 473 F.2d 1360 (1973). Moreover, it is general law in this State that summary judgment will not be granted (1) if there is a dispute as......
  • Frank's Maintenance & Engineering, Inc. v. C. A. Roberts Co.
    • United States
    • United States Appellate Court of Illinois
    • July 24, 1980
    ...full hearing on the issue is required. Reynolds v. Preferred Mutual Insurance Co. (1972), 49 Mass.App.Dec. 97; Luick v. Graybar ELectric Co., Inc. (8th Cir. 1973), 473 F.2d 1360; Kohlenberger, Inc. v. Tyson's Foods, Inc. (1974), 256 Ark. 584, 510 S.W.2d 555; Haugen v. Ford Motor Co. (N.D.19......
  • Miller v. Stifel, Nicolaus & Co., Civ. No. 10–1258 (JJK).
    • United States
    • U.S. District Court — District of Minnesota
    • September 20, 2011
    ...Law Firm, No. 07–45, 2007 WL 2750670, at *3 (E.D.Ark. Sept. 18, 2007) (quoting Fed.R.Civ.P. 36(a)-(b)); see also Luick v. Graybar Elec. Co., 473 F.2d 1360, 1362 (8th Cir.1973) (stating that “[u]nanswered requests for admissions render the matter conclusively established” and that “summary j......
  • Carlson Companies, Inc. v. Sperry & Hutchinson Co.
    • United States
    • U.S. District Court — District of Minnesota
    • February 7, 1974
    ...circumstances. Rotermund v. United States Steel Corporation, 474 F.2d 1139, 1143-1144 (CA8 1973); Luick v. Graybar Electric Company, Inc., 473 F.2d 1360, 1362-1363 (CA8 1973); Cervantes v. Time, 464 F.2d 986, 993 (CA8 1972) and Traylor v. Black, Sivalls & Bryson, Inc., 189 F.2d 213 (CA8 Oza......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT