Maloney v. Boston Development Corp.
Decision Date | 03 March 1953 |
Parties | MALONEY v. BOSTON DEVELOPMENT CORP. et al. |
Court | New Hampshire Supreme Court |
Maurice A. Broderick and James B. Sullivan, Manchester, for plaintiff.
Devine & Millimet, Manchester, for defendant.
Because of its nature this case requires, for its proper understanding and disposition, a detailed analysis of the facts in their aspect most favorable to the plaintiff. Riley v. Springfield Savings Bank, 86 N.H. 329, 330, 168 A. 721; Leonard v. City of Manchester, 96 N.H. 115, 117, 70 A.2d 915.
Plaintiff submitted to defendant a bid of $14,250 each to build, as a sub-contractor, 23 of the 82 houses in the project. The following conversation then took place between the plaintiff and one MacNeil acting for the defendant. D. P. 'Well it depends upon the terms and so forth.' D. P. They settled on $125 per week.
The plaintiff testified that his bid of $14,250 embodied 'all the estimates and costs of material and labor * * *, plus the contractor's overhead and profit and other expenses, such as night watchman, and different things that one would have to do in preparing for the work, shanties etc.' His bid was prepared on the basis of blueprints and specifications the same or similar to those involved in this action.
As to the setting of a par of $13,000 per house, plaintiff testified that MacNeil brought out the fact that if defendant was to build them they would have certain expenses, such as bookkeeping and overhead and the ordinary expenses of a contractor and that plaintiff's bid contained an item for profit. Hence the setting of a par of $13,000. There was nothing said about superintending or constructing the work necessary beyond the street line.
Maloney asked MacNeil to put the agreement in writing. He agreed and was to bring it up on his next visit to the project. The plaintiff had been working three weeks when the defendant handed him a writing. Its material parts were as follows.
Plaintiff refused to accept the writing. He pointed out to defendant, among other things, that he understood the $125 weekly payment was to be salary and not a drawal against the amount of the difference. Also that there was nothing said in the original conversation about the recommendation of the Federal Housing Administration, the Worcester Federal Savings & Loan Association and the architect. MacNeil was to redraft it and resubmit it to the plaintiff. This was never done.
Subsequently MacNeil told plaintiff 'I have had complaints about your work--the superintendence, and it will be necessary before you continue any further to get a letter of approval from the Federal Housing Administration.' Mr. Baker, State Director of that organization, told Maloney he had no province of approving any employee on any contract and that MacNeil was aware of this. Plaintiff received no further checks and left the job after being on it about six weeks. At that time the entire eighty-two cellars were excavated, forty footings and thirty-one foundations were poured and twenty houses framed.
To substantiate his claim for damages plaintiff testified to the cost of all labor and materials which he stated were necessary to construct the houses on the project. This amounted to $11,166 per house.
On cross-examination he admitted that he had left out certain items which should also be changed in the cost. He then proceeded to prove the cost of most of these items. He failed however to prove the cost of gypsum blocks for firewalls in the cellars, also the cost of certain labor which he admitted should be charged for, the cost of wire lath and the cost of other items. Those proved amounted to $645.18 which brought the total cost of $11,711.18 per house.
There are certain items called for by the plans and specifications such as, supervision, electricity, telephone, temporary heat, trucking, cleaning of windows, snow removal, broom cleaning of premises, repairing damage during construction, insurance, the cost of which is substantial and which plaintiff omitted because he says they are part of the overhead defendant talked about. However plaintiff admitted that aside from mentioning overhead expense MacNeil never itemized the expenses which were to be part of defendant's costs and plaintiff never mentioned them either. He further admitted that he never said anything to MacNeil about omitting anything from or adding anything to the specifications and that MacNeil never told him he could omit anything.
Plaintiff introduced evidence that MacNeil in his application to the City of Manchester, for building permit, filed on behalf of Garden Homes Inc., placed the cost of each house at $7,000. This is exclusive of plumbing, electrical work, driveways, walks, shrubbery, painting and decorating. He introduced further evidence that the Federal Housing Administration had estimated the cost of each house at $12,509.00. However this witness admitted on cross-examination that if the cost of some of the items called for by the specifications and omitted by plaintiff were taken into account the cost of each house could be at least $13,268.
The plaintiff had the burden of producing evidence from which the intention of the parties may be discovered, the nature...
To continue reading
Request your trial-
In re Plourde, No. 05-15221-JMD.
...the defendant had the burden of proving the terms of the contract which supported his set-off and counterclaim); Maloney v. Boston Dev. Corp., 98 N.H. 78, 81, 95 A.2d 129 (1953) (plaintiff had the burden of producing evidence establishing the intention of the parties and the nature and exte......
-
McLaughlin v. Union-Leader Corp.
...party below is entitled to have the evidence considered by the appellate court in its most favorable aspect. Maloney v. Boston Development Corp., 98 N.H. 78, 95 A.2d 129; Isabelle v. Carnes, 99 N.H. 184, 185, 107 A.2d 227. On one view of the evidence the plaintiff was uncooperative, disobed......
- Richardson v. Beattie
-
Trimount Bituminous Products Co. v. Chittenden Trust Co.
...contract has not borne its burden of proving it, the master correctly refused to find such a contract. Maloney v. Boston Development Corp., 98 N.H. 78, 81, 95 A.2d 129, 131 (1953); Mississippi & Dominion Steamship Co. v. Swift, 86 Me. 248, 254-55, 29 A. 1063, 1065 (1894); see Hess v. Shurtl......