Mar-Len of Louisiana, Inc. v. Parsons-Gilbane

Citation773 F.2d 633
Decision Date11 October 1985
Docket NumberMAR-LEN,No. 85-4125,PARSONS-GILBANE,85-4125
PartiesOF LOUISIANA, INC., Plaintiff-Appellee, v., a Joint Venture, Defendant-Appellant. Summary Calendar.
CourtUnited States Courts of Appeals. United States Court of Appeals (5th Circuit)

McGlinchey, Stafford, Mintz & Cellini, Henri Wolbrette, III, Kathleen A. Manning, New Orleans, La., for defendant-appellant.

Allen R. Boudreaux, Thibodaux, La., for plaintiff-appellee.

Appeal from the United States District Court For the Western District of Louisiana.

Before RUBIN, JOHNSON, and JONES, Circuit Judges.

JOHNSON, Circuit Judge:

Parsons-Gilbane appeals from an order of the district court staying pending arbitration proceedings. On appeal, Parsons-Gilbane asserts that the district court erroneously concluded that a dispute with Mar-Len of Louisiana, Inc. (Mar-Len) regarding the validity of certain contract modifications is beyond the scope of an arbitration agreement between the parties. This Court finds that the dispute is subject to the party's arbitration agreement. The order of the district court is vacated and remanded.

I. BACKGROUND

Acting as construction manager of the Department of Energy's Strategic Petroleum Reserve Project, Parsons-Gilbane contracted with Mar-Len of Louisiana, Inc. on April 28, 1981, to construct and install a fire and flushwater system at West Hackberry, Louisiana. The original contract between Parsons-Gilbane and Mar-Len provided that Mar-Len would complete construction and testing of the system by December 18, 1981, and would be paid $4,387,500.

Eventually, the parties added thirty-nine modifications to the basic contract. These modifications increased the contract price to $5,607,205.30 and extended the completion date for the contract work to January 29, 1982. Two of these modifications are central to the current dispute. In Modification 22, Parsons-Gilbane granted Mar-Len a waiver of a backfill specification that Mar-Len considered expensive and time consuming. The contract originally required that pipeline hydrostatic testing be done before backfilling was accomplished. Modification 22 granted Mar-Len a performance time extension and a change to allow post-backfill testing. In return, Mar-Len agreed to waive certain delay claims.

On September 3, 1982, after Mar-Len's activities at the worksite had ceased, Mar-Len delivered to Parsons-Gilbane a seven-volume claim package alleging various deficiencies and inefficiencies and requiring that Mar-Len receive an additional $6,153,629.25 for performance of the contract work. Attempts to resolve this dispute concerning the amount of compensation due Mar-Len for its performance began shortly after the claim package was reviewed by Parsons-Gilbane and government auditors, but only a partial compromise was reached. This compromise became Modification 39. Modification 39 granted Mar-Len an additional $300,000 in compensation for work done at the site which Mar-Len claimed was beyond the scope of its contractual responsibilities. Mar-Len later repudiated Modifications 22 and 39 alleging that they were obtained without its consent due to the exertion of economic duress by Parsons-Gilbane.

The Parsons-Gilbane/Mar-Len contract contains the following language governing the resolution of disputes between the parties:

"ARTICLE XIV--Disputes (July 1979)

1.0 Any dispute arising under this subcontract that is not settled by agreement of the parties, or pursuant to the administrative relief provided for in the following paragraphs of this Article, shall be settled by arbitration as provided in Clause 5.0 of this Article.

* * *

5.0 In the event of any dispute not settled by agreement of the parties, or pursuant to the administrative relief provided for in the preceding Paragraphs 1.0, 2.0, or 3.0 of this Article, between Contractor and Subcontractor with respect to the interpretation or performance of this Subcontract, the same shall be settled by arbitration by the American Arbitration Association ("Association") before a single arbitrator in accordance with the Association's Construction Industry Arbitration Rules, at New Orleans, Louisiana." (emphasis added).

Because Mar-Len had repudiated the two modifications, Parsons-Gilbane initiated arbitration on January 17, 1983, before the American Arbitration Association. In the arbitration proceeding, Parsons-Gilbane sought a declaration that Modification 22 waived certain delay claims contained in the seven-volume claim package and that Modification 39 settled amounts Mar-Len claimed for extra work. Arbitration proceedings were stayed to allow the parties time to explore settlement negotiations. The stay ended on July 18, 1983, after attempts at amicable resolution had failed.

Mar-Len then filed suit on August 5, 1983, in the Fourteenth Judicial District Court, Calcasieu Parish, Louisiana, seeking reformation or voidance of Modifications 22 and 39 of its contract with Parsons-Gilbane based on lack of consent (economic duress) in contracting for these two provisions. On August 16, 1983, Parsons-Gilbane removed the action to the United States District Court, Western District of Louisiana. Parsons-Gilbane then filed a motion to compel arbitration and to stay the proceedings. On November 30, 1983, the federal district court denied the motion to stay and to compel arbitration and ordered the trial of Mar-Len's action. The district court concluded that the Parsons-Gilbane/Mar-Len arbitration agreement was "not susceptible of an interpretation that covers the asserted dispute." The district court held that the arbitration agreement covered only disputes involving the interpretation and performance of the contract but not challenges to the validity of subsequent contract modifications.

Parsons-Gilbane appealed the district court's determination to this Court. In Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 732 F.2d 444 (5th Cir.1984), a divided panel of this Court dismissed the appeal. This Court concluded that the district court's denial of Parsons-Gilbane's motion to stay and to compel arbitration was not an appealable interlocutory order under 28 U.S.C. Sec. 1292(a)(1).

Subsequent to this Court's order dismissing Parsons-Gilbane's appeal, Mar-Len filed a motion requesting the district court to issue an injunction prohibiting any further proceedings in the pending arbitration. On December 12, 1984, the district court issued the requested injunction based on that court's earlier conclusion that the dispute between Mar-Len and Parsons-Gilbane is not within the scope of their arbitration agreement. On January 2, 1985, Parsons-Gilbane properly perfected this appeal from the district court's order granting the injunction. 1 On appeal, Parsons-Gilbane argues that the district court improperly stayed the arbitration because of the district court's erroneous conclusion that the Mar-Len/Parsons-Gilbane dispute was not arbitrable.

II. ARBITRABILITY

The question of arbitrability is determined on the basis of the existence of an arbitration clause that on its face appears broad enough to encompass the parties' claims. Commerce Park at DFW Freeport v. Mardian Construction Co., 729 F.2d 334, 338 (5th Cir.1984). A presumption of arbitrability exists requiring that whenever the scope of an arbitration clause is fairly debatable or reasonably in doubt, the court should decide the question of construction in favor of arbitration. United Steelworkers of America v. Warrior & Gulf Navigational Co., 363 U.S. 574, 583 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960). The weight of this presumption is heavy: arbitration should not be denied "unless it can be said with positive assurance that an arbitration clause is not susceptible of an interpretation that could cover the dispute at issue." Wick v. Atlantic Marine, Inc., 605 F.2d 166, 168 (5th Cir.1979).

The presumption favoring arbitrability is based in large part on policy considerations. A primary consideration recognized by ...

To continue reading

Request your trial
67 cases
  • Alamria v. Telcor Intern., Inc., Civil Action No. CCB-95-1551.
    • United States
    • U.S. District Court — District of Maryland
    • April 3, 1996
    ...policy favoring arbitration, particularly in international business disputes." Id. at 194; see also Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633, 637 (5th Cir.1985) (noting that "the Second Circuit itself observed that Kinoshita is inconsistent with federal policy favoring ar......
  • Torrence v. Murphy
    • United States
    • U.S. District Court — Southern District of Mississippi
    • February 23, 1993
    ...cover the dispute at issue. See Neal v. Hardee's Food Systems, Inc., 918 F.2d 34, 37 (5th Cir.1990); Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633, 635-36 (5th Cir.1985), and the authority therein cited. This is so because the law favors arbitration agreements and interprets t......
  • Efund Capital Partners v. Pless
    • United States
    • California Court of Appeals Court of Appeals
    • May 21, 2007
    ...accord with present day notions of arbitration as a viable alternative dispute resolution procedure"]; Mar-Len of Louisiana, Inc. v. Parsons-Gilbane (5th Cir. 1985) 773 F.2d 633, 637 ["Kinoshita is inconsistent with federal policy favoring arbitration"].) Consistent with the presumption fav......
  • Dialysis Access Ctr. Llc v. Rms Lifeline Inc.
    • United States
    • U.S. Court of Appeals — First Circuit
    • March 30, 2011
    ...in the contract, whether or not they implicate interpretation or performance of the contract per se”); Mar–Len of Louisiana, Inc. v. Parsons–Gilbane, 773 F.2d 633, 637 (5th Cir.1985) (recognizing that Kinoshita is inconsistent with federal policy favoring arbitration). The case law that we ......
  • Request a trial to view additional results
3 books & journal articles
  • Defendant's Standard Brief in Support of Motion to Stay Pending Arbitration (Federal Court)
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2016 Appendices Substantive Forms
    • July 30, 2023
    ...Securities, Inc., 654 F. Supp. 101 (E.D. Mich. 1987)........................ Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633 (5th Cir. Matterhorn, Inc. v. NCR Corp., 763 F.2d 866 (7th Cir. 1985)............................ Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Haydu......
  • Defendant's Standard Brief in Support of Motion to Stay Pending Arbitration (Federal Court)
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2017 Appendices Substantive
    • August 19, 2023
    ...Securities, Inc., 654 F. Supp. 101 (E.D. Mich. 1987)........................ Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633 (5th Cir. Matterhorn, Inc. v. NCR Corp., 763 F.2d 866 (7th Cir. 1985)............................ Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Haydu......
  • Defendant's standard brief in support of motion to stay pending arbitration (Federal Court)
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2014 Appendices Substantive
    • August 16, 2023
    ...Securities, Inc., 654 F. Supp. 101 (E.D. Mich. 1987)........................ Mar-Len of Louisiana, Inc. v. Parsons-Gilbane, 773 F.2d 633 (5th Cir. Matterhorn, Inc. v. NCR Corp., 763 F.2d 866 (7th Cir. 1985)............................ Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Haydu......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT