Marine v. Entities
Decision Date | 19 November 2010 |
Docket Number | 1090421. |
Citation | 63 So.3d 615 |
Parties | NATURES WAY MARINE, LLCv.DUNHILL ENTITIES, LP, et al. |
Court | Alabama Supreme Court |
OPINION TEXT STARTS HERE
Allen E. Graham, William E. Shreve, Jr., and A. Grady Williams IV of Lyons, Pipes & Cook, P.C., Mobile, for appellant.Edward A. Dean and Benjamin Y. Ford of Armbrecht Jackson, LLP, Mobile, for appellees.SHAW, Justice.
Natures Way Marine, LLC (“Natures Way”), an Alabama limited-liability company and the plaintiff below, appeals from a partial summary judgment entered in favor of Dunhill Entities, LP (“Dunhill”), a Texas limited partnership and a defendant below, as to Natures Way's claim seeking to enforce a mechanic's and materialman's lien pursuant to § 35–11–210, Ala.Code 1975. 1 For the reasons discussed below, we dismiss the appeal.
Dunhill owns property abutting the Mobile River in Mobile. In order to accept barge deliveries, Dunhill, on or around March 11, 2008, contracted with Natures Way, which “is in the business of bareboat charters and related services for barges it owns,” to perform dredging work necessary to deepen the approaches to the barge berth located on the Dunhill property. Work began on or around May 12, 2008. Following completion of the dredging project, Natures Way alleged, Dunhill paid a portion of the outstanding invoices but still owes Natures Way $332,746.33.
On May 19, 2009, Natures Way sued numerous corporate entities apparently operated by Dunhill (hereinafter referred to collectively as “the Dunhill entities”) and three fictitiously named defendants,2 seeking to recover the purported outstanding amount on the following claims: breach of contract, work and labor done, action on account, account stated, and unjust enrichment. The Dunhill entities answered, generally denying the allegations of Natures Way's complaint. In their answer, the Dunhill entities also asserted a counterclaim alleging breach of contract, failure to perform the dredging work in a good and workmanlike manner, fraud, and unjust enrichment. The Dunhill entities further asserted that the invoices submitted by Natures Way were duplicative and that they included charges for work Natures Way allegedly did not perform.
Following the filing of a verified statement of lien in the Mobile Probate Court on July 8, 2009,3 Natures Way amended its original complaint to add an enforcement-of-lien count seeking to enforce a lien against Dunhill's Mobile property pursuant to § 35–11–210.4 Dunhill moved for a partial summary judgment as to the lien-enforcement claim. In its motion seeking a partial summary judgment, Dunhill argued that any dredging work performed by Natures Way occurred on or in public waters and thus that there was no dredging on its land and that all dredging work performed by Natures Way ceased as of December 10, 2008, which, pursuant to § 35–11–215, Ala.Code 1975, would have rendered Natures Way's statement of lien, filed on July 8, 2009, untimely.5
Natures Way opposed Dunhill's motion for a partial summary judgment, relying on invoices that, it said, demonstrated the use of its barge by Dunhill from January 19, 2009, until January 25, 2009, and, thus, its timely filing of its verified statement of lien. In addition, Natures Way argued that Dunhill possessed riparian rights that extended over the submerged land on which Natures Way had performed dredging work; therefore, Natures Way contended, the work benefited Dunhill's property.
On September 14, 2009, the trial court granted Dunhill's motion for a partial summary judgment. Although the trial court's order failed to include the factual findings on which it based that decision, it specifically “ordered” that “Nature's [sic] Way Marine, LLC does not have a valid lien on the property of Dunhill Entities, L.P. ...”
Natures Way timely filed a motion asking the trial court to “reconsider” its ruling, which the trial court denied. In its order denying the motion filed by Natures Way, the trial court reaffirmed its previous partial summary judgment, stating:
(Emphasis original.) On November 6, 2009, pursuant to a request by Natures Way,6 the trial court purported to certify the partial summary judgment as final pursuant to Rule 54(b), Ala. R. Civ. P. Natures Way timely appealed.
As noted, Natures Way purports to appeal the trial court's partial summary judgment resolving its lien-enforcement claim against Dunhill. Although neither party to this appeal has raised the issue of the appropriateness of the trial court's Rule 54(b) certification, it is well settled that this Court may consider, ex mero motu, whether a judgment or order is sufficiently final to support an appeal.
“ ‘ “As this court has said many times previously, a final judgment is necessary to give jurisdiction to this court on an appeal, and it cannot be waived by the parties....”
“ ‘....
“ ‘When it is determined that an order appealed from is not a final judgment, it is the duty of the Court to dismiss the appeal ex mero motu.’
“ Powell v. Republic Nat'l Life Ins. Co., 293 Ala. 101, 102, 300 So.2d 359, 360 (1974) (quoting McGowin Investment Co. v. Johnstone, 291 Ala. 714, 715, 287 So.2d 835, 836 (1973)).
“
“ Grantham v. Vanderzyl, 802 So.2d 1077, 1079–80 (Ala.2001).”
North Alabama Elec. Coop. v. New Hope Tel. Coop., 7 So.3d 342, 344 (Ala.2008).
Here, as noted above, the trial court certified as final pursuant to Rule 54(b) its partial summary judgment as to the lien-enforcement claim. However, “ ‘[n]ot every order has the requisite element of finality that can trigger the operation of Rule 54(b).’ ” Dzwonkowski v. Sonitrol of Mobile, Inc., 892 So.2d 354, 361 (Ala.2004) (quoting Goldome Credit Corp. v. Player, 869 So.2d 1146, 1147 (Ala.Civ.App.2003) (emphasis omitted)).
“ ‘Rule 54(b) certifications “should be made only in exceptional cases.” ’ [ Wallace v. Tee Jays Mfg. Co., 689 So.2d 210] at 212 [ (Ala.Civ.App.1997) ]. ‘[I]n an action involving claims and counterclaims, Rule 54(b) certification has been determined to be improvident where the issues in the claims were deemed to be “so closely intertwined that separate adjudication would pose an unreasonable risk of inconsistent results.” ’ Fullilove v. Home Fin. Co., 678 So.2d 151, 154 (Ala.Civ.App.1996) (quoting Branch v. SouthTrust Bank of Dothan, N.A., 514 So.2d 1373, 1374 (Ala.1987)). In Branch v. SouthTrust Bank of Dothan, N.A., [this] court stated:
“
...
To continue reading
Request your trial-
Wright v. Harris
...may consider, ex mero motu, whether a judgment or order is sufficiently final to support an appeal.’ Natures Way Marine, LLC v. Dunhill Entities, LP, 63 So.3d 615, 618 (Ala. 2010)." ‘ "Ordinarily, an appeal can be brought only from a final judgment. Ala. Code 1975, § 12–22–2. If a case invo......
-
Blackmon v. Renasant Bank
...may consider, ex mero motu, whether a judgment or order is sufficiently final to support an appeal." Natures Way Marine, LLC v. Dunhill Entities, LP, 63 So.3d 615, 618 (Ala. 2010). In the present case, as noted above, the circuit court certified as final pursuant to Rule 54(b) its December ......
-
84 Lumber Co. v. City of Northport, 2150876
...may consider, ex mero motu, whether a judgment or order is sufficiently final to support an appeal.’ Natures Way Marine, LLC v. Dunhill Entities, LP, 63 So.3d 615, 618 (Ala. 2010)." ‘ "Ordinarily, an appeal can be brought only from a final judgment. Ala. Code 1975, § 12–22–2. If a case invo......
-
Cathedral of Faith Baptist Church, Inc. v. Moulton
...may consider, ex mero motu, whether a judgment or order is sufficiently final to support an appeal." Natures Way Marine, LLC v. Dunhill Entities, LP, 63 So. 3d 615, 618 (Ala. 2010)." ‘Ordinarily, an appeal can be brought only from a final judgment. Ala. Code 1975, § 12-22-2. If a case invol......