Marion Mfg. Co. v. Long

Decision Date12 December 1978
Docket NumberNo. 76-2347,76-2347
PartiesMARION MANUFACTURING COMPANY, Petitioner-Appellee, v. W. B. LONG, d/b/a W. B. Long Company, and Robert Manning, Jr., d/b/a Webb Cotton Company, Respondents-Appellants.
CourtU.S. Court of Appeals — Sixth Circuit

Theodore A. Snyder, Jr., Walhalla, S.C., J. Kimbrough Johnson, Memphis, Tenn., for respondents-appellants.

O. G. Calhoun, H. R. Stephenson, Jr., Greenville, S.C., John W. McQuiston, II, Goodman, Glazer, Strauch & Schneider, Memphis, Tenn., for petitioner-appellee.

Before PHILLIPS, Chief Judge, and CELEBREZZE and KEITH, Circuit Judges.

KEITH, Circuit Judge.

Respondents below appeal from a judgment of the district court confirming and enforcing an arbitration award pursuant to 9 U.S.C. § 9 (1970). We affirm the judgment of Chief Judge Bailey Brown.

The underlying dispute concerns three contracts, numbered 100, 102 and 105, entered into between sellers-appellants W. B. Long, d/b/a W. B. Long Company, and Robert Manning, d/b/a Webb Cotton Company (hereinafter Long and Manning), and buyer-appellee Marion Manufacturing Company (hereinafter Marion), for the purchase and sale of cotton. 1 In an earlier proceeding between these parties, the United States District Court for the District of South Carolina held that the contracts were subject to the arbitration provisions of Rule 44 of the Southern Mill Rules for Buying and Selling Cotton, (1971 ed.). The Court ordered the parties to arbitrate their dispute pursuant to 9 U.S.C. §§ 1-3. Long v. Marion Manufacturing Co., 402 F.Supp. 69 (D.S.C.1974), Aff'd, 511 F.2d 1398 (4th Cir. 1975). Arbitration proceedings were held before the Board of Appeals of the Cotton States Arbitration Board in Memphis, Tennessee. The Board's decision is set out at the margin. 2

After the Board's decision was announced on August 4, 1975, Marion petitioned the Board for a clarification of its decision to determine the amount of money damages. Long and Manning objected to a clarification of the award, contending that the award was clear that "Contracts 100, 102 and 105 are open contracts and that Sellers are required to ship enough cotton to complete each of them." Appendix at 78. On September 10, 1975, the Board of Appeals denied the request to clarify its award. Long and Manning then indicated to Marion their willingness to ship the cotton under the contract; Marion responded that delivery in accordance with the Southern Mill Rules was now impossible as the contracts had called for performance in 1974. Marion requested the sellers to forward to it the sum of $13,017.50, plus one-fourth cent per pound for 127 bales of cotton, in damages.

Long and Manning subsequently moved in the United States District Court for the District of South Carolina to confirm the arbitration award. The district court denied the motion, holding that absent an agreement between the parties, a judgment on an arbitration award may not be entered in a court other than the district court for the district in which the award was made. W. B. Long v. Marion Manufacturing Co., No. 74-659 (D.S.C., March 10, 1976); 9 U.S.C. § 9. Marion then brought this action in the United States District Court for the western District of Tennessee for an order confirming, modifying, correcting or vacating the award. Long and Manning filed a cross-petition to confirm the award.

On August 11, 1976, Chief District Judge Bailey Brown entered an order confirming the arbitration award. The court ordered that all three contracts be completed with performance to be made within thirty days of the entry of judgment. Delivery and payment were to be made in accordance with the contract. The court also ordered Marion to pay Long and Manning the balance of $39,622.42 owing on an April, 1974, shipment of cotton. Enforcement of the judgment was stayed pending this appeal.

In reaching its decision, the district court stated in pertinent part:

In conformity with well-established legal precedent (See James Richardson & Sons v. Hedger Transportation Corp., 98 F.2d 55 (2nd Cir. 1938), cert. denied, 305 U.S. 657, 59 S.Ct. 357, 83 L.Ed. 426 (1939), this court has no intention of reviewing the merits of the arbitration award. However, the language of the above quoted award leaves the court somewhat puzzled. The word "fulfill" as defined by The American College Dictionary (1970 Edition) entails "carrying out" or "performing;" in short, specific performance, as stated in legal terminology. Whereas, the ordering of specific performance is somewhat unusual in a contract of sale for a product like cotton, it is not for this court to question the decision of the arbitrators. Raytheon Co. v. Rheem Manufacturing Co., 322 F.2d 173 (9th Cir. 1963).

Upon accepting the interpretation of the award as providing for specific performance, the refusal of the arbitrators to provide further clarification of the award becomes significant. The date on which the cotton is purchased for performance is immaterial; the essential criterion to be met is fulfillment of the contract. However, before such performance may be rendered one further issue must be resolved; that is, we must determine which contract should be credited with the disputed April 1974 delivery.

Marion Manufacturing Co. v. W. B. Long, No. C-76-127 (W.D.Tenn., August 11, 1976), slip opinion at 4. We agree with the court that specific performance of a contract for the purchase and sale of fungible goods is somewhat unusual, but we do not sit to review the merits of the arbitration award. 3

The question presented on appeal is whether the rights and duties of the parties were fixed as of the date the contracts were breached, or the date of the arbitration award, August 4, 1975, or the date of the district court judgment, August 11, 1976. We hold that that part of the district court's judgment which orders the buyer to pay the seller the balance of $36,622.42 owed on the April, 1974, cotton shipment fixes the rights of the parties as of the date of the judgment. Although this issue was submitted to the arbitration panel in Long and Manning's statement of Issues on Arbitration, it was not ruled upon by the Board. The Judgment of the district court was the first adjudication of this claim between these parties. As such, it determined their rights as of the date it was entered.

The remaining portion of the district court's judgment confirmed and implemented the arbitration award. We hold that this part of the judgment fixed the rights of the parties as of the date of the award. An arbitration award conclusively determines the rights of the parties unless it is invalidated by a reviewing court. Nix v. Spector Freight Systems, Inc., 264 F.2d 875 (3rd Cir. 1959). Thus, if the award is upheld in a reviewing court, the rights of the parties are determined from the date of the award and not the date of the court's judgment confirming the award. See Lundgren v. Freeman, 307 F.2d 104, 112 (9th Cir. 1962). Any other result would defeat the purpose of arbitration which is to finally decide the issues between the arbitrating parties without judicial intervention. Amicizia Societa Navegazione v. Chilean Nitrate & Iodine Sales Corp., 274 F.2d 805 (2nd Cir.), Cert. denied, 363 U.S. 843, 80 S.Ct. 1612, 4 L.Ed.2d 1727 (1960). It should be the rule, rather than the exception, that when arbitrators hand down an award the parties will comply with it, without the necessity of court proceedings, just as it is (or should be) the normal or usual result that parties comply with a judgment, without the necessity of resort to process or appeal.

Lundgren v. Freeman, 307 F.2d at 112.

An arbitration award which comes within the purview of 9 U.S.C. §§ 1 Et seq. (1970), will only be vacated or set aside if fraud, misconduct or partiality is shown, or if the arbitrator has exceeded his authority, or if the award is not mutual, final and definite. 9 U.S.C. § 10; Aerojet-General Corp. v. American Arbitration Ass'n., 478 F.2d 248 (9th Cir. 1973). These circumstances are not present in the instant case.

The judgment of the district court is affirmed. On Motion

for Clarification and in the Alternative, Petition

for Rehearing

The basic difficulty in this unduly protracted litigation is the arbitration panel's award of "specific performance" of a contract involving the sale of fungible goods. Both parties have realized that "specific performance" of the sale of a fungible good or product is nothing more than an unusual way of fixing money damages. In a case such as this, involving cotton, "specific performance" on a given day merely means that the seller will ship the cotton and receive the contract...

To continue reading

Request your trial
16 cases
  • Ronnisch Constr. Grp., Inc. v. Lofts On the Nine, LLC.
    • United States
    • Michigan Supreme Court
    • July 26, 2016
    ...(Scalia, J., concurring).61 See Corallo v. Merrick Central Carburetor, Inc., 733 F.2d 248, 252 (C.A.2, 1984) ; Marion Mfg. Co. v. Long, 588 F.2d 538, 541 (C.A.6, 1978) ; Nix v. Spector Freight Sys., Inc., 264 F.2d 875, 877 (C.A.3, 1959).62 As previously noted, one of the fundamental purpose......
  • Krystal Co. v. Caldwell, 1:11-CV-81
    • United States
    • U.S. District Court — Eastern District of Tennessee
    • March 13, 2012
    ...award of prejudgment interest begins. Generally, interest should be awarded from the date of the arbitration award. Marion Mfg. Co. v. Long, 588 F.2d 538 (6th Cir. 1978) (noting that "if the award is upheld in a reviewing court, the rights of the parties are determined from the date of the ......
  • Jeppsen v. Piper, Jaffray & Hopwood, Inc.
    • United States
    • U.S. District Court — District of Utah
    • March 6, 1995
    ...as to the correct compilation of damages." ARW Exploration Corp. v. Aguirre, 45 F.3d 1455 (10th Cir.1995) (citing Marion Mfg. Co. v. Long, 588 F.2d 538, 541 n. 3 (6th Cir.1978)). As noted previously, the court does not review for errors of fact or law. Lastly, based on the authorities cited......
  • David Co. v. Jim W. Miller Const., Inc.
    • United States
    • Minnesota Supreme Court
    • September 8, 1989
    ...379, 474 N.E.2d 1151 (1985), cert. denied, 394 Mass. 1103, 477 N.E.2d 595 (1985) (award requiring indemnification); Marion Mfg. Co. v. Long, 588 F.2d 538 (6th Cir.1978) (specific performance of a contract for sale and purchase of fungible goods); United States v. Woodcrest Nursing Home, 706......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT