Marshall County Redi-Mix, Inc. v. Matthew, REDI-MI

Decision Date16 January 1984
Docket NumberINC,No. 184S19,REDI-MI,184S19
Citation458 N.E.2d 219
PartiesMARSHALL COUNTY, and Wright-Denaut Construction Co., of Plymouth, Indiana, Appellants, v. LaVerne MATTHEW and Martha P. Matthew, Appellees.
CourtIndiana Supreme Court

B. Patrick Maloy, Mulligan & Maloy, North Judson, for appellants.

Orville W. Nichols, Nichols, Wallsmith & Weaver, Knox, for appellees.

PIVARNIK, Justice.

This cause comes to us on a petition to transfer from the Indiana Court of Appeals. The Starke Circuit Court heard the suit between the respondents, Marshall County Redi-Mix, Inc. (Redi-Mix) and Wright-Denaut Construction Co., and the petitioners, LaVerne Matthew and Martha Matthew. Redi-Mix sued to foreclose on a mechanic's lien lodged against the Matthews' property. The Matthews brought a counterclaim and sought damages. The trial court ruled in the Matthews' favor on both issues and awarded them $1,700.00 damages. The Court of Appeals, Third District, affirmed the trial court's decision in discharging the mechanic's lien but reversed the award of damages to the Matthews on their counterclaim. Marshall County Redi-Mix, Inc. v. Matthew, (1983) Ind.App., 447 N.E.2d 1165.

The question presented for our review is whether the stipulation by the parties that the materials and workmanship were both satisfactory bars a recovery of damages on behalf of the petitioners. We find that the Court of Appeals erred in reversing on the issue of damages. Transfer is granted and the opinion of the Court of Appeals is vacated.

The petitioners, LaVerne and Martha Matthew, were constructing a building for the storage of antique vehicles. They hired a construction firm to erect the building and the respondents, Redi-Mix and Wright-Denaut, were contracted to pour and finish the concrete floor. The concrete floor was to be poured prior to the installation of the walls in order to permit easier accessibility during the pouring of the floor. The floor was poured on January 3, 1980, and the trowelling and leveling was completed on January 4. Due to the cold weather, Redi-Mix supplied the Matthews with straw to spread on the concrete for insulation and protection against freezing temperatures. Despite this precaution, the concrete froze, leaving the top 1/16" of the 4" base in a crumbling and powdery condition. Later in January, LaVerne Matthew met with representatives of the contractors and General Portland Cement but reached no agreement about correcting the problem. The Matthews finished the building and began to use it although the floor was unsightly and the friable condition created dust. The Matthews refused to pay for the floor and Redi-Mix and Wright-Denaut sued to foreclose their mechanic's lien on the property. The cases were consolidated and the Matthews filed a counterclaim alleging that the contractors were responsible for the concrete freezing and seeking damages in the amount necessary to correct the problem. The parties stipulated that the contractors were joint venturers or partners in the enterprise. They also stipulated that the materials and workmanship were satisfactory; the sole problem was the freezing of the concrete. Both parties called expert witnesses to testify about the concrete freezing and how to correct the problem. The trial court refused to enforce the mechanic's lien and awarded the Matthews $1,700.00 in damages.

The Court of Appeals held that the trial court was correct in determining that the contractors could not enforce the mechanic's lien, 447 N.E.2d 1167, but reversed the award of damages. The Court of Appeals stated that the Matthews were barred from recovering damages because they had stipulated that the workmanship was satisfactory. 447 N.E.2d at 1168.

Although we are vacating the Court of Appeals' opinion because of its treatment on the issue of damages, we agree with its holding concerning the mechanic's lien. We adopt the applicable portions of that opinion and make it part of this opinion as follows:

"In establishing their right to foreclose, the burden was on the contractors to prove that the lien met the statutory requirements. Blade Corp. v. American Drywall, Inc., (1980) Ind.App., 400 N.E.2d 1183. See IC 1976, 32-8-3-1 et seq. (Burns Code Ed., Repl.1980). The Matthews have not alleged any failure to comply with the applicable statutes. The owner of the property subject to a mechanic's lien may file a set-off, see Goodwin v. Schwartz, (1945) 115 Ind.App. 422, 59 N.E.2d 363, or a counterclaim to the lienholder's complaint. Jose-Balz Co. v. DeWitt, (1931) 93 Ind.App. 672, 176 N.E. 864. The Matthews filed a counterclaim, asserting that the concrete froze, rendering the floor unsuitable and that the contractors were responsible. At the time the concrete froze, the floor had been poured but not yet sealed.

* * *

* * *

Where the subject matter of a construction contract has been destroyed during construction through no fault of the property owner, the contractor cannot enforce a mechanic's lien. Hipskind Heating & Plumbing Co. v. General Industries, Inc., (1963) 136 Ind.App. 647, 194 N.E.2d 733, trans. denied, 246 Ind. 215, 204 N.E.2d 339. In determining whether the loss was total, we consider only the evidence most favorable to the judgment of the trial court and the reasonable inferences which may be drawn from that evidence. Smith v. Bruning Enterprises, Inc., (1981) Ind.App., 424 N.E.2d 1035, 1037. We will affirm the trial court's judgment if there is evidence of probative value to sustain it. The record contains expert testimony that one method of repairing the floor would be to remove the old floor and lay a new one. This is sufficient to support the judgment of the trial court discharging the liens. The partial use of the building by the Matthews does not prevent them from claiming the loss. Cf. Jose-Balz Co., supra (Occupation of the premises does not prevent the filing of a counterclaim if the owner complained to the contractor upon discovery of the defect).

Because the record contains evidence that the floor froze through no fault of the Matthews and that one method of repair would require removal of the entire floor we affirm the trial court's discharge of the mechanic's lien."

While we agree with the treatment of the mechanic's lien, we feel the Court of Appeals erred in reversing the award of damages. The Court of Appeals felt that when the Matthews stipulated that the workmanship was satisfactory, the contractors were absolved of any fault and therefore the Matthews could not recover damages in addition to the discharge of the mechanic's lien. We find that the Court of Appeals gave an interpretation to the stipulation that was not intended by any of the parties. The Matthews did stipulate that the workmanship was satisfactory but it was also part of that stipulation that the issue to be tried to the bench was the placement of responsibility for the freezing of the concrete floor. Both parties agreed that this was the issue remaining for the trial court to determine. We agree with the dissent, in which Judge Garrard wrote that "[i]t appears to me that the parties and the trial court treated the stipulation as obviating inquiry into the quality of the materials or the workmanship that went into pouring the floor. I believe we should do likewise."

This Court will affirm the trial court's decision if it is sustainable upon any...

To continue reading

Request your trial
15 cases
  • Associates Inv. Co. v. Claeys
    • United States
    • Indiana Appellate Court
    • February 8, 1989
    ... ... 3; Thompson v. Daviess-Martin County REMC (1985), Ind.App., 486 N.E.2d 1102, 1104 ... Life Insurance Co. of North America, Inc. (1985), 174 Ga.App. 753, 331 S.E.2d 609, 610 ... E.g., Marshall County Redi-Mix, Inc. v. Matthew (1984), Ind., ... ...
  • Trw Vehicle Safety Sys. Inc. v. Moore
    • United States
    • Indiana Supreme Court
    • October 13, 2010
    ... ... Marshall County Redi-Mix, Inc. v. Matthew, 458 N.E.2d 219, 222 ... ...
  • Lawyers Title Ins. Corp. v. Pokraka
    • United States
    • Indiana Supreme Court
    • July 6, 1992
    ... ... v. Indpls. Newpapers Inc. (1991), Ind., 577 N.E.2d 208, 211-12 (citations ... Pepinsky v. Monroe County Council (1984), Ind., 461 N.E.2d 128, 135. We ... Marshall County Redi-Mix, Inc. v. Matthew (1984), Ind., ... ...
  • Plymouth Fertilizer Co., Inc. v. Balmer, 3-185-A-17
    • United States
    • Indiana Appellate Court
    • February 11, 1986
    ... ... the owner in fee simple of real estate situate in Marshall County, Indiana, and being the Southwest Quarter of Section ... Marshall County Readi-Mix, Inc. v. Matthew (1984), Ind., 458 N.E.2d 219; Litzelswope v. Mitchell ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT