Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co.
Decision Date | 27 July 1923 |
Citation | 122 A. 102,99 Conn. 396 |
Parties | MARTIN TIRE & RUBBER CO. v. KELLY TIRE & RUBBER CO. APPLICATION OF CHARLES R. HEDDEN CO. |
Court | Connecticut Supreme Court |
Appeal from Superior Court, New Haven County; John W. Banks, Judge.
Receivership proceedings by the Martin Tire & Rubber Company against the Kelly Tire & Rubber Company. On application of the Charles R Hedden Company for allowance of a preferred claim. From judgment for applicant, the receivers appeal. Affirmed.
The finding recites the following facts: On May 23, 1921, the Charles R. Hedden Company, petitioner herein, filed its mechanics' lien on land and a building of the defendant. The Kelly Tire & Rubber Company, which recites that the petitioner ceased furnishing material and rendering services on the building on April 6, 1921. On May 24, 1921, a temporary receiver was appointed by the superior court, and on June 27th two permanent receivers were appointed of the defendant. The petitioner furnished materials and rendered services in the erection and construction of a factory building for the defendant under a written contract between it and the petitioner. The receivers and the petitioner agreed in settlement upon the sum of $41,000 as the amount still due the petitioner under its contract, and which sum was a part of the claim which was secured by its mechanics' lien. The petitioner subsequently released the lien, reserving its priority thereunder to the fund which should be realized from the sale of the premises of the Kelly Company and thereafter presented its claim as a preferred claim. The petitioner between March 7, 1921, and April 6, 1921, expended for services in the completion and construction of this contract $1,156.79; of this $151.75 was for a pay roll, on March 9, 1921, for engineer, carpenter foreman, tool boy, bricklayer, and two laborers. After March 9, 1921, no material was furnished, and the only labor furnished after that date was the services of a carpenter on March 25, 1921, and of a civil engineer, the petitioner's superintendent of construction, who was employed up to and including April 6, 1921, in cleaning up and making alterations and getting petitioner's equipment in condition for removal and removing it from the job as required by the contract. The services of the superintendent were rendered in completion of the contract for construction of the building and were charged to the construction contract by the petitioner. No payments on account of the contract have been made since March 7, 1921.
Albert H. Barclay, of New Haven, for appellants.
Henry F. Parmelee and Arthur W. Chambers, both of New Haven, for appellee.
WHEELER, C.J. (after stating the facts as above).
Defendant claims that the facts stated in paragraphs 8 and 11 of the finding should be corrected because they are inconsistent and found without evidence. The petitioner, on the other hand, says that these are findings of fact made upon undisputed evidence. The statement, in paragraph 8, that the petitioner continued to furnish services in the completion of the contract for the construction of the building, we regard as a mixed conclusion of law and fact, that the conclusion of fact must have been found from the other facts in the finding, and hence the conclusion is reviewable. The statement in paragraph 11, that the services of the superintendent were rendered in completion of the contract for the construction of the building, is the same sort of conclusion. Both of these conclusions depend upon the conclusion to be drawn from the subordinate facts, together with a construction of the building contract, and the application of the subordinate facts to the contract so construed.
Thus in Nichols v. Culver, 51 Conn. 177, it is held that trivial work done or material furnished will be sufficient to extend the time for filing the lien if done at the request of the owner, and not for the mere purpose of saving his lien.
In the first of these cases the delay was nine...
To continue reading
Request your trial-
F.B. Mattson Co., Inc. v. Tarte, 15857
...lien commences on the last date on which services were performed or materials were furnished; Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., 99 Conn. 396, 403, 122 A. 102 (1923); when work has been substantially completed and the contractor unreasonably has delayed final completion, t......
-
Cianci v. Originalwerks Llc.
...to discharge the mechanic's lien. 7. The court did recognize, however, that under the circumstances of Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., 99 Conn. 396, 122 A. 102 (1923), pursuant to Connecticut law, “preparation for removal and the removal of the [contractor's] equipment ......
-
Diamond Nat. Corp. v. Dwelle
...mechanic's lien is a creature of statute and gives a right of action which did not exist at common law. Martin Tire & Rubber Co. v. Kelly Tire & Rubber Co., 99 Conn. 396, 403, 122 A. 102; comment, 'Mechanics' Liens in Connecticut,' 37 Conn.B.J. 209, 212. Since § 49-39 sets the time within w......
-
Priddy v. Kernersville Lumber Co., 396
...Co., 202 Md. 43, 95 A.2d 90, 39 A.L.R.2d 387. Gem State Lumber Co. v. Witty, 37 Idaho 489, 217 P. 1027; Martin Tire and Rubber Co. v. Kelly Tire and Rubber Co., 99 Conn. 396, 122 A. 102. The reason for the rule is clearly stated in Cahoon et al. v. Fortune Min. & Mill. Co., 26 Utah 86, 72 P......