Martin v. AAA Brick Co., Inc.

Decision Date21 May 1980
Docket NumberNo. 7629,7629
Citation386 So.2d 987
PartiesMalcolm MARTIN and Ruby Bridges Martin, Plaintiffs-Appellees, v. AAA BRICK COMPANY INC., Defendant-Appellant.
CourtCourt of Appeal of Louisiana — District of US

George F. Griffing, Jonesville, for defendant-appellant.

Broadhurst, Brook, Miller & Reed, Lafayette, for plaintiffs-appellees.

Before DOMENGEAUX, GUIDRY and LABORDE, JJ.

GUIDRY, Judge.

Plaintiffs, Malcolm Martin and Ruby Bridges Martin, filed suit for damages for the unworkmanlike performance of a contract for the construction of a fireplace. The defendant-contractor, AAA Brick Company, Inc., reconvened seeking the contract price and recognition of a lien filed against plaintiffs' property. From a judgment in favor of plaintiffs, in the sum of $6251.25, which also rejected defendant's reconventional demand, defendant has appealed. Plaintiffs neither appealed nor answered the appeal.

On January 17, 1978, defendant entered into a written contract with Mrs. Martin agreeing to furnish and install a brick-encased 40 inch metal fireplace at plaintiffs' residence for the consideration of $1600.00. As part of the agreement defendant was to supply approximately one-half of the bricks required for the job. The bricks to be furnished by defendant were to match as closely as possible bricks supplied by plaintiffs which were left over from the original construction of plaintiffs' home. The inside work was completed on January 18, 1978. The extension of the flue through the roof was accomplished about 10 days later. After the completion of the fireplace plaintiffs experienced a variety of problems. A white powdery residue formed on the surface of the fireplace bricks. The residue, or efflorescence, is the result of salts which are internal in the brick and/or mortar which are brought out to the surface because of water being present. In response to complaints by plaintiffs, defendant sent a man on two occasions to try to clean the bricks. However, after each attempt, the efflorescence returned. When plaintiffs attempted to light a fire in the fireplace, it allegedly smoked excessively. Because of alleged water leaks around the flue where it extended through the roof, plaintiffs had the flue and chimney cap removed and their roof patched. The general dissatisfaction of plaintiffs with the fireplace culminated with the filing of this suit. Plaintiffs alleged that the fireplace is totally useless because of certain defects in its construction.1 On the basis of the alleged defects plaintiffs sought a recision of the contract and damages in redhibition. In the alternative, plaintiffs sought damages for breach of contract.

After trial on the merits the trial court decided in favor of plaintiffs and against defendant. In doing so, the trial court made the following findings:

"It is the opinion of the Court that the fireplace in question was improperly installed as the Court finds the following defects in its construction: (1) The leaks around the chimney which have the effect of saturating the insulation in the attic and leaking through on the ceiling tile in the room in which the fireplace was constructed, which necessitated the removal of the flue and a patching of the roof in order to stop the roof leakage.

Additionally, the Court finds that from the testimony introduced that the fireplace did in fact smoke at the times which it had been used which indicates that the flue had not been extended sufficiently above the roofline to allow proper draft. A viewing of the photographs introduced in evidence indicates to this Court that the chimney as constructed was unsightly as it was not square and that the brick did not match as had been requested by the plaintiffs and that additionally, the courses of the brick were not in line with the preexisting brickwork. Additionally, apparently the efflouresence (sic) which began showing up shortly after the construction of the fireplace continued at least until the date of the trial some year and a half (11/2) later.

All of the above are such as to convince this Court that the plaintiffs should be relieved of the necessity for paying the purchase price for the fireplace and accordingly, the Court will order a recision of the sale and award damages to the plaintiffs as follows: The amount of $150.00 which represents the costs of repairs of the roof to eliminate the roof leaking around the flue. Additionally, the Court will award to the plaintiffs for their mental anguish the sum of $2000.00 each. Additionally, the Court will award to plaintiffs the sum of $101.25 for the bill of Fabian Patin, the architect who inspected the workmanship in the fireplace.

The Court will award as attorney fees for bringing this action the sum of $2000.00. The Court will set the fee of Mr. Fabian Patin, who testified as an expert, in the amount of $250.00 and tax the same as costs. All costs of these proceedings to be assessed against the defendant, AAA Brick Company, Inc.

The reconventional demand of AAA Brick Company against the plaintiffs, Malcolm Martin and Ruby Bridges Martin will be dismissed at said reconvenors cost . . ."

Defendant contends the above findings and awards are erroneous and urges their reversal on appeal. Defendant's arguments in brief, regarding alleged trial court error, address issues solely within the context of an action in redhibition, which the trial court ostensibly found to be properly asserted. The trial court apparently found the contract in question to be a sale pure and simple and, accordingly, applied the legal principles as set forth in LSA-C.C. Article 2520 et seq. in fashioning its judgment. We disagree with the trial court that the present action involves a sale whereby an action in redhibition could be properly maintained. The contract in question did not involve merely the sale and delivery of a fireplace or the materials for its construction. The contract contemplated the installation and erection of a fireplace at plaintiffs' residence by defendant, with the latter furnishing the materials and necessary labor and skill in the performance of the job. Our conclusion is that the contract entered into between defendant and Mrs. Martin was not one of mere sale, but a construction contract.

LSA-C.C. Article 2756 defines a construction contract as follows:

"To build by a plot, or to work by the job, is to undertake a building or a work for a certain stipulated price."

Our jurisprudence has consistently held that a contract involving work to be done on the owner's land or building is a building contract within the definition of Article 2756 even though the undertaker is required to furnish some of the materials.2

For the foregoing reasons, we conclude it was error to apply the sales articles pertaining to redhibitory defects to the case at hand and we reverse the trial court's judgment in as much as it held the present action is one in redhibition and to the extent said judgment differs from our holding today. Further we conclude that the rights and obligations of the parties under the contract in question are governed by the legal principles set forth in Book III, Title IX of the Civil Code under Section 3 which is entitled "Of Constructing Buildings According to Plots, and Other Works by the Job, and of Furnishing Materials".

The legal principles derived from the above cited code section concerning construction contracts and applicable in the present suit were set forth in Neel v. O'Quinn, 313 So.2d 286 (La.App. 3rd Cir. 1975), in which we stated:

"It is implied in every building contract that the work of the builder be performed in a good workmanlike manner, free from defect either in material or workmanship. Nichols Ford Co., Inc. v. Hughes, 292 So.2d 345 (La.App. 2nd Cir. 1974).

The basic law in regard to a contractor's liability for failure to properly perform a building contract is found in LSA-C.C. Art. 2769, as follows:

'Art. 2769. Contractor's liability non-compliance with contract.

If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he should be liable in damages for the losses that may ensue from his non-compliance with his contract.'

This codal provision has been construed by the courts to mean that when a contractor has 'substantially performed' a building contract, even though certain defects are present, he is entitled to recover the contract price, and the owner is relegated to having the price reduced by the amount necessary to perfect or complete the work, i. e., damages attributable to the breach. Airco Refrigeration Service Inc. v. Fink, 242 La. 73, 134 So.2d 880 (1961).

In turn, if the building contract has not been substantially performed, the contractor's recovery is limited in quantum meruit. In the same regard, if the defects are such that cannot be corrected except by removing and replacing the construction, under the jurisprudence the owner may require the contractor to remove the object from his land and restore the premises to their prior condition. In addition, the owner is entitled to damages. National Water-Purifying Co. v. New Orleans W. W. Co., 48 La. (Ann.) 773, 19 So. 865 (1896); Toepfer v. Thionville, 299 So.2d 415 (La.App. 4th Cir. 1974); Scott Fence & Insulation Co., Inc. v. Boudro, 252 So.2d 458 (La.App. 4th Cir. 1971); Montague v. Milan, 67 So.2d 351 (La.App. Orl. Cir. 1953); Home Services v. Marvin, 37 So.2d 413 (La.App. Orl. Cir. 1948)."

In the instant suit the trial court made no determination whether or not the defendant has "substantially performed" the contract in question. Nor did the trial court fix liability under Article 2769. The determination of liability under the aforestated principles must now be fixed by this court. In doing so, we accept the factual finding as set forth in the trial judge's written reasons that the fireplace was improperly installed for the reasons given, supra. From our review of the...

To continue reading

Request your trial
32 cases
  • Fontenot v. F. Hollier & Sons
    • United States
    • Court of Appeal of Louisiana — District of US
    • November 27, 1985
    ...distinction made between contract and tort cases when it comes to the assessment of nonpecuniary damages. See Martin v. AAA Brick Co., Inc., 386 So.2d 987 (La.App. 3rd Cir.1980), concurring opinion; Elliott v. Louisiana Intrastate Gas Corp., 390 So.2d 571 (La.App. 3rd Cir.1980), footnotes 2......
  • Cell-O-Mar, Inc. v. Gros
    • United States
    • Court of Appeal of Louisiana — District of US
    • November 19, 1985
    ...2756 and 2757. Such agreements are commonly called building or construction contracts. See, for example, Martin v. AAA Brick Company, Inc., 386 So.2d 987 (La.App. 3rd Cir.1980). The contractor (builder) in such an agreement has an implied duty to perform in a workmanlike manner free from de......
  • Guillory v. Jim Tatman's Mobile Homes, Inc.
    • United States
    • Court of Appeal of Louisiana — District of US
    • June 25, 1986
    ...distinction made between contract and tort cases when it comes to the assessment of non-pecuniary damages. See Martin v. AAA Brick, Co. Inc., 386 So.2d 987 (La.App. 3rd Cir.1980), concurring opinion; Elliott v. Louisiana Intrastate Gas Corp., 390 So.2d 571 (La.App. 3rd Cir.1980), footnotes ......
  • Hebert v. McDaniel
    • United States
    • Court of Appeal of Louisiana — District of US
    • December 11, 1985
    ...to its prior condition. Additionally, the owner is entitled to damages. Caubarreaux v. Hines, supra, at 900; Martin v. AAA Brick Company, Inc., 386 So.2d 987 (La.App. 3 Cir.1980), citing Neel v. O'Quinn, supra, at 290, and cases cited The trial court found that McDaniel had breached the imp......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT