Masonry Equipment & Supply v. Willco Associates, Inc.

Decision Date10 June 1988
Docket NumberNo. 880072-CA,880072-CA
Citation755 P.2d 756
PartiesMASONRY EQUIPMENT & SUPPLY, Plaintiff and Respondent, v. WILLCO ASSOCIATES, INC., Defendant and Appellant.
CourtUtah Court of Appeals

John A. Snow, David Black (argued), R. Stephen Marshall, Salt Lake City, for defendant and appellant.

Boyd M. Fullmer, Salt Lake City, for plaintiff and respondent.

Before DAVIDSON, GARFF and JACKSON, JJ.

OPINION

DAVIDSON, Judge:

Defendant and appellant Willco Associates (Willco) appeals from findings of fact and conclusions of law entered by the district court and from the judgment against Willco for the principal sum of $8,626.82 together with interest, costs, and attorney fees.

This is a suit on a rental agreement for damages caused to a LC-30 Gerlinger Crawler that was rented by Willco from plaintiff and respondent Masonry Equipment & Supply Company (MESCO). Willco rented the machine from MESCO from December 11, 1981 to March 30, 1982. 1 The rental agreements provided that the lessee would be responsible for maintenance and repairs to the rental equipment. 2

MESCO gave Willco repair order No. 1426, dated March 2, 1982, charging Willco $2,390.06 for repairs made by MESCO to the machine's track and a catalytic converter. These repairs were performed before the machine was returned to MESCO. The day the machine was returned MESCO informed Willco that the machine was damaged and Willco would be charged for additional repairs.

Willco's president, Frank Willden, testified that he had two telephone conversations with Matthew Lyman, an officer of MESCO, in which Willden disputed the amount charged under repair order No. 1426. Mr. Willden also disputed that Willco was responsible for any other damages MESCO claimed. Mr. Willden testified he agreed to pay $2,390.00, as indicated on the repair order, so long as MESCO agreed to accept that payment as payment in full, including charges thereon and any other charges or damages. Mr. Lyman testified he did not recall any conversation with Mr. Willden that payment of $2,390.00 would be payment in full of the Willco account. Mr. Willden also testified Willco experienced difficulties with the machine, which caused approximately 80 hours of down time, during which its equipment and employees were idle. MESCO made a number of service calls to the Kennecott job site to work on the machine. Willco was not charged for these calls.

Willco tendered its check in the amount of $2,390.00, dated October 4, 1982. The check was tendered as payment in full, and stated on the back, "Endorsement of this check constitutes payment in full of your account # 2224: Willco Assoc." MESCO accepted and cashed the check.

Approximately three weeks after the check was cashed, MESCO disassembled the machine and inspected it. MESCO thereafter prepared repair order No. 1656 which set the total damages at $8,626.82. Willco refused to pay, claiming MESCO had cashed its check which had been tendered as payment in full for the entire account.

On December 3, 1982, MESCO commenced this action. Trial was held on March 5, 1986. A second hearing was held on April 28, 1986, upon Willco's motion to amend findings of fact and conclusions of law, and Willco's motion in objection to the same. The court entered its judgment May 8, 1986, granting MESCO $8,626.82 as the principal sum, interest on the sum at 12% per annum from March 30, 1982, the date of the return of the equipment, attorney fees in the amount of $1,875.00, and costs. The court refused Willco an offset for any down time. Specifically, the court found in its ruling:

The evidence in this case, in my judgment, has established by a preponderance that the equipment was damaged and that the defendant is responsible to pay said sums. There is no separate consideration for an accord and satisfaction.... Neither am I persuaded there was a meeting of the minds.... Neither am I persuaded that there was offsetting down time. The defendant continued to rent the machine even as of the 2nd of March of 1982, at which time he signed another form rental agreement and accepted the equipment.

Willco claims, as a matter of law, that an accord and satisfaction had been reached between MESCO and Willco. A definition of accord and satisfaction is found in Golden Key Realty, Inc. v. Mantas, 699 P.2d 730 (Utah 1985), where the Utah Supreme Court held:

An accord and satisfaction arises when the parties to a contract agree that a different performance, to be made in substitution of the performance originally agreed upon, will discharge the obligation created under the original agreement.

The substituted agreement calling for the different performance discharges the obligation created under the original agreement. The elements essential to contracts generally must be present in a contract of accord and satisfaction, including offer and acceptance, competent parties, and consideration.

Id. at 732 (citations omitted). See also Brimley v. Gasser, 754 P.2d 97 (Utah App.1988). This defines the usual case and is the definition applied by the trial court. However, a different definition of accord and satisfaction applies to this case.

The case of Marton Remodeling v. Jensen, 706 P.2d 607 (Utah 1985), is remarkably...

To continue reading

Request your trial
3 cases
  • Estate Landscape and Snow Removal Specialists, Inc. v. Mountain States Tel. & Tel. Co.
    • United States
    • Utah Supreme Court
    • December 17, 1992
    ...(iii) an acceptance of the payment. See Marton Remodeling v. Jensen, 706 P.2d 607, 609 (Utah 1985); Masonry Equip. & Supply v. Willco Assoc., Inc., 755 P.2d 756, 758 (Utah Ct.App.1988). Although Mountain Bell discusses all three elements of accord and satisfaction in its brief, the trial co......
  • Cornia v. Wilcox
    • United States
    • Utah Supreme Court
    • June 28, 1995
    ... ... Inc., a Utah corporation, and Dennis Weston, ... ...
  • Estate Landscape and Snow Removal Specialists, Inc. v. Mountain States Tel. & Tel. Co.
    • United States
    • Utah Court of Appeals
    • May 24, 1990
    ...decisions in Cove View Excavating and Constr. Co. v. Flynn, 758 P.2d 474 (Utah Ct.App.1988), and Masonry Equipment & Supply v. Willco Assocs., Inc., 755 P.2d 756 (Utah Ct.App.1988), ruled that "this case is controlled by Marton Remodeling v. Jensen, 706 P.2d 607 (Utah 1985)." But the spring......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT