McCarthy Bros. Const. Co. v. Pierce, 84-1830C (A).

Decision Date14 January 1986
Docket NumberNo. 84-1830C (A).,84-1830C (A).
Citation626 F. Supp. 981
PartiesMcCARTHY BROTHERS CONSTRUCTION COMPANY, a Missouri corporation, Plaintiff, v. Samuel R. PIERCE, Jr., in his official capacity as Secretary of the United States Department of Housing & Urban Development, and National Church Residences of St. Charles, Missouri, an Ohio non-profit corporation, Defendants.
CourtU.S. District Court — Eastern District of Missouri

James L. Hawkins, Jeffrey L. Demerath, St. Louis, Mo., for plaintiff.

Joseph B. Moore, Asst. U.S. Atty., St. Louis, Mo., Keith W. Hazelwood, St. Charles, Mo., for defendants.

MEMORANDUM OPINION

HARPER, District Judge.

This matter is before the Court on plaintiff's declaratory judgment action. Plaintiff seeks a declaration that it is entitled to $131,850.00 incentive fee under a construction contract between it and defendant, National Church Residences of St. Charles, Missouri (hereinafter referred to as National Church). Plaintiff bases federal jurisdiction over this matter upon diversity of citizenship pursuant to 28 U.S.C. § 1332.

This case was submitted to the Court upon joint stipulations of fact which the Court adopts as its statement of facts. The parties have also submitted a list of exhibits and a stipulation relating to them. From these facts and exhibits, the Court has reached the following conclusions.

Plaintiff, McCarthy Brothers Construction Company, and defendant, National Church, on September 29, 1981, contracted to build the Jaycee Fairgrounds Village (hereinafter referred to as the project). The project was to provide low-cost housing for the elderly. Financing for the project was supplied by the Department of Housing & Urban Development (hereinafter referred to as HUD) through a direct loan.

In addition to an original fee of $247,272.00, the contract provided for the payment of an incentive fee to plaintiff if certain conditions were met. These conditions consisted of, (1) a cost savings, and (2) an early completion. Plaintiff built the project at a cost of nearly $480,000.00 below that which was estimated. To satisfy the second requirement, plaintiff needed to have substantially completed the project before March 14, 1983 — the contract's completion date.

The parties to this lawsuit disagree as to whether plaintiff fulfilled the second condition required to qualify for the incentive fee. Their disagreement arises from a dispute over the definition of the term "substantial completion."

Under the definition desired by plaintiff, substantial completion would have occurred nearly two weeks (March 1, 1983) prior to the contract's completion date. On the other hand, HUD's definition of the term would have resulted in substantial completion occurring approximately eleven days late, on March 25, 1983.

Plaintiff claims that Article 8.1.3 of the AIA Document A2011 properly defines the term "substantial completion." This provision reads as follows:

"8.1.3 The Date of Substantial Completion of the Work or Designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended."

The parties do not disagree that under this definition substantial completion occurred prior to March 14, 1983.

HUD advocates that Article 2D of the construction contract properly defines the disputed term. This provision reads as follows:

"D. The date of substantial completion shall be the date the HUD representative signs the HUD Representative Trip Report (Form HUD 5379) which indicates construction is complete and which report is substantially endorsed by the Chief Architect as being the Final Inspection Report."

Once again, the parties do not disagree that under this definition substantial completion occurred after March 14, 1983.

This matter simply requires the Court to decide which definition of "substantial completion" applies to the issue of incentive fees. Clearly, Article 2D denotes a meaning of "substantial completion." Furthermore, Article 1A of the construction contract expressly states, inter alia, that "the provisions of this instrument and the said FHA Supplementary Conditions take precedence over all inconsistent provisions in the said AIA General Conditions." (Emphasis added.)

Article 8.1.3 of the AIA General Conditions and Article 2D of the construction contract are inconsistent. The inconsistency arises over the person designated to determine "substantial completion." Article 8.1.3 requires the administering architect to make the determination while Article 2D delegates that responsibility to...

To continue reading

Request your trial
3 cases
  • Nelson v. Globe Intern., Inc.
    • United States
    • U.S. District Court — Southern District of New York
    • 14 Enero 1986
  • McCarthy Bros. Const. Co. v. Pierce
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • 22 Octubre 1987
    ...contract and granted the counterclaim of National Church Residences of St. Charles, Missouri, for overpayment on that contract, 626 F.Supp. 981. We On September 29, 1981, National Church Residences of St. Charles, Missouri (National Church), entered into a contract with McCarthy Brothers Co......
  • McCarthy Bros. v. Pierce
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • 25 Junio 1986
    ...681 794 F.2d 681 McCarthy Bros. v. Pierce 86-1127 United States Court of Appeals, Eighth Circuit. 6/25/86 E.D.Mo., 626 F.Supp. 981 ...

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT