Melton v. United States

Decision Date12 March 1980
Docket NumberCiv. A. No. 76-1891.
Citation488 F. Supp. 1066
PartiesBeatrice MELTON, Plaintiff, v. UNITED STATES of America, Defendant.
CourtU.S. District Court — District of Columbia

COPYRIGHT MATERIAL OMITTED

Florence R. King, Washington, D. C., for plaintiff.

John H. E. Bayly, Jr., Asst. U. S. Atty., Washington, D. C., for defendant.

OPINION

HAROLD H. GREENE, District Judge.

This is an action under the Federal Tort Claims Act, 28 U.S.C. § 2671 et seq., alleging that the government negligently selected contractors to rehabilitate real property plaintiff owns in the District of Columbia and negligently supervised the rehabilitation project after it was started. The case was tried by the Court, and this Opinion incorporates the Court's findings of fact and conclusions of law.

I

Plaintiff, a resident of Jamaica, New York, is the owner of a small house located at 1812 — 9th Street, N.W., in the District of Columbia, given to her by her father. In June 1972, she was warned by the D.C. Department of Building, Housing, and Zoning that an inspection of the property — which then contained three rental apartments — had revealed 98 violations of the housing code and that she was required to abate these violations. Shortly thereafter, plaintiff was contacted by the Redevelopment Land Agency (RLA)1 which advised her that, because her property was located in the Shaw Urban Renewal Area, she was entitled to a so-called section 312 housing and urban development loan, 42 U.S.C. § 1452b, designed to enable her to comply with the government's requirements in regard to the housing violations, and to permit her to remodel the property so as to provide four apartments instead of three. Through the efforts and with the assistance of the RLA, plaintiff was awarded a $40,600 loan to be used for the rehabilitation and renovation work.2

In February 1973, RLA personnel completed, and plaintiff approved, a detailed work-up, describing the plans and specifications for the project. Two months later, the Agency, on the basis of sealed bids3 submitted by contractors on an Agency-maintained list,4 selected Apex Modernizing Co. (Apex) to perform the work called for by the plans.

Plaintiff herself had no voice in selecting the contractor,5 except that she did sign a form on which Apex had tentatively been preselected by RLA. In fact, Ms. Melton did not meet representatives of Apex until August 1973, when together they attended a settlement conference with RLA. At that conference, plaintiff signed another RLA form representing the agreement with Apex for the performance of the rehabilitation work, a promissory note for the amount of the loan, and a deed of trust securing that note. Under the agreement, Apex was to be paid in installments in accordance with a specific formula as the work progressed.

Thereafter, plaintiff at various times6 received forms forwarded or submitted to her, signed both by James Greenleaf, rehabilitation specialist in charge of plaintiff's project for RLA,7 and his supervisors,8 evidencing progress in accordance with the terms of the agreement. Upon receipt of these forms, and in accordance with RLA advice, plaintiff signed the forms — which authorized the disbursement of funds — and the corresponding checks on her loan account.9

In the meantime, various problems arose. In December 1973, plaintiff was notified by the D.C. Department of Building, Housing, and Zoning that work on the project would have to be halted for lack of a building permit, and in February 1974, she was advised that a zoning variance was necessary if the project was to proceed further. However, RLA's employees continued to assure her that these were essentially technicalities peculiar to the way of doing business in the District of Columbia, that there was no cause for concern, and that these matters were being taken care of.10 Plaintiff had no reason to doubt these assurances, for the agreement explicitly provided that the responsibility for obtaining all permits and licenses rested with the contractor.11

Plaintiff was also advised that the RLA was monitoring and supervising the work on a continuing basis,12 and accordingly she did not, except on two or three occasions, travel to Washington to review the progress of construction. She did, however, fill in the appropriate blank on RLA's progress report forms whenever called upon to do so, evidencing that the work done was of an acceptable quality.13

In July 1974, by a letter signed by Claude N. Juggins, its president, Apex withdrew from the project, and RLA awarded the contract to J. Coleman Masonry & Concrete Work. Coleman likewise failed to perform, and in March 1975, plaintiff was informed that the funds were exhausted,14 and that, although the project had not been completed, all work had ceased.

In the meantime, Greenleaf had been replaced as the rehabilitation specialist in charge of the Melton project by Gerard E. Rogers. Rogers estimated that it would cost $17,000 to finish the job, but by then the balance remaining in plaintiff's account was far below that amount. RLA sought a grant15 from the U.S. Department of Housing and Urban Development to complete the job but this was not approved. HUD also turned down a plan to use the remaining funds in plaintiff's escrow account to board up the property to protect it from vandalism.

No additional progress has been made on the project since the funds ran out in January 1975. Instead, through vandalism and neglect, the property has been essentially gutted. In February 1977, the D.C. Department of Finance and Revenue issued a special assessment to plaintiff, charging her $1,145 for the cost of barricading the premises and for removing trash and debris. In March 1975, Greenleaf, the rehabilitation specialist assigned by RLA to plaintiff's project, pleaded guilty to receipt of a $2,000 bribe from Apex' president Juggins in connection with that project (and possibly others), and he was sentenced by Judge George L. Hart, Jr. to imprisonment for a term of six to eighteen months.16

Plaintiff's account of the history of the rehabilitation project and her understanding of her responsibilities and those of RLA's agents was corroborated both by the documentary evidence and by a former RLA official. James Littlejohn, the rehabilitation officer in charge of the Shaw Urban Renewal Area between 1974 and 1979, testified that his office was giving technical advice and assistance to owners in the Shaw area, providing them with data, helping them to process applications, and the like. His officers and specialists also prepared surveys and work write-ups, and selected the contractors to perform the work. If the cost of any particular project exceeded $10,000, the contract was awarded by competitive bidding, but the bidding was limited to contractors on RLA's list of eligible companies. That list was prepared and maintained by RLA officials at an administrative or supervisory level. Neither Apex nor Coleman should have been on the list at all, for they lacked both the requisite experience and the necessary home improvement licenses. Littlejohn further explained that jobs were awarded by RLA to the lowest bidder from those on the list, the homeowner himself having no effective influence on the selection process. After a contract was signed, an RLA rehabilitation specialist had the duty to monitor the job. Payments were made in installments as the job progressed, the progress to be measured by the rehabilitation specialist and his supervisors.

In Littlejohn's view, the rehabilitation project on plaintiff's property was a failure because (1) it was not properly planned, in that zoning requirements, the need for structural changes, and the like were not adequately taken into account, (2) neither Apex nor Coleman had previous experience with this kind of project, (3) Coleman lacked the requisite financial ability, and Apex, through its president Juggins, was dishonest, and (4) the job was not properly monitored. The witness stated that, in his opinion, there was nothing plaintiff could have done to avert the failure of the project, and that she acted as any other prudent homeowner would have acted.

In August 1974, plaintiff filed an administrative claim against the United States in the amount of $90,370.37. That claim was denied, and on October 12, 1976, she filed the instant action in this Court.17

The government raises three defenses: (1) contributory negligence, (2) plaintiff's action is based on a claim of misrepresentation and involves a discretionary government function and is for those reasons not covered by the Federal Tort Claims Act, and (3) the acts of James Greenleaf were beyond the scope of his employment and are therefore not binding on the government.

II

Defendant's claim of contributory negligence may be quickly dismissed. The evidence shows that the government's agents assumed complete control both for the award of the contracts and for monitoring the work after the contracts had been signed. While on paper plaintiff may have had the option to reject the government-selected contractors, as a practical matter she was so tied by government regulations and procedures to RLA's choices that her rejection of those choices would have meant no rehabilitation contract at all. Similarly, it was RLA — through its rehabilitation specialist and that individual's supervisor — which monitored and supervised the work and which had to be satisfied with its progress, not plaintiff. RLA's officials retained all real authority with respect to the contractors' performance, they were on the scene, and they vouched for the progress of the work in writing before any new expenditures could be made.

It would be exalting form over substance to hold that plaintiff was contributorily negligent because she did not conduct her own investigation to make certain that RLA's conclusions were actually supported by the facts. As the plaintiff, whom the Court finds to be a...

To continue reading

Request your trial
14 cases
  • Local 1814, Intern. Longshoremen's Ass'n, AFL-CIO v. N.L.R.B.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • July 20, 1984
    ...interest when they commit such crimes. Further illustration is provided by another case upon which petitioners rely, Melton v. United States, 488 F.Supp. 1066 (D.D.C.1980), in which a government rehabilitation specialist had been bribed by a developer to falsify reports. The government was ......
  • Claude v. United States, No. C00-3010-MWB (N.D. Iowa 4/12/2001)
    • United States
    • U.S. District Court — Northern District of Iowa
    • April 12, 2001
    ...are acts of negligence pure and simple and do not fall within the FTCA's discretionary function exception); Melton v. United States, 488 F. Supp. 1066, 1072-73 (D.D.C. 1980) (finding that the government acts of selecting incompetent contractors and supervising them in a careless manner are ......
  • Focke v. United States
    • United States
    • U.S. District Court — District of Kansas
    • March 22, 1982
    ...in International Distributing Corp. v. American Dist. Telegraph Co., 569 F.2d 136, 139 (D.C.Cir.1977). Also see Melton v. United States, 488 F.Supp. 1066, 1074 (D.D.C.1980). Once again, as with any claim of negligence, it is incumbent upon the plaintiffs to demonstrate that the V.A. Hospita......
  • Roman Catholic Church of Archdiocese of New Orleans v. Louisiana Gas Service Co.
    • United States
    • Louisiana Supreme Court
    • May 24, 1993
    ...476 A.2d 974, 975-76 (1984) ($9,674.00 for replanting shrubs removed by construction in widening a road); Melton v. United States, 488 F.Supp. 1066, 1069, 1075 (D.D.C.1980) ($90,000.00 to complete a $40,000.00 restoration job); Trinity Church v. John Hancock Mut. Life Ins. Co., 399 Mass. 43......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT