Merion Spring Co. v. Muelles Hnos. Garcia Torres, S.A.

Decision Date04 August 1983
Citation315 Pa.Super. 469,462 A.2d 686
PartiesMERION SPRING COMPANY T/A Green Spring Company, v. MUELLES HNOS. GARCIA TORRES, S.A., Appellant. MERION SPRING COMPANY T/A Green Spring Co., Appellant v. MUELLES HNOS. GARCIA TORRES, S.A.
CourtPennsylvania Superior Court

Gilbert E. Toll, Philadelphia, for appellant (at No. 1418) and for appellee (at No. 1343).

Before SPAETH, ROWLEY and CIRILLO, JJ.

ROWLEY, Judge:

These are cross-appeals from a judgment entered pursuant to an order of the court en banc. The court rendered a partial "Judgment N.O.V." in favor of the appellant in No. 1418, but otherwise affirmed the general decision entered by the trial judge who sat without a jury.

Merion Spring Company (hereafter "Merion" or "plaintiff"), appellant in No. 1418, commenced this action on February 14, 1974, by filing a complaint in assumpsit. Merion sought damages in the amount of $32,515.75 for breach of a contract for the sale of twenty-five automobile spring manufacturing machines. In April 1976, the defendant, appellant in No. 1343, Muelles Hnos. Garcia Torres, S.A. (hereafter "Muelles" or "defendant"), 1 a corporation formed and located in the Republic of Mexico, filed an answer averring that it had not breached the contract. Furthermore, by way of counterclaim, Muelles averred that Merion had breached the contract and prayed that judgment be entered in its favor in an amount in excess of $500,000.00, in large part representing a claim for lost profits. In December, 1978, the case was tried before the Honorable Calvin T. Wilson, sitting without a jury. Following two days of testimony, the trial judge returned a general decision in favor of Muelles on both the complaint and the counterclaim, assessing against plaintiff Merion the following damages:

Muelles filed no exceptions to the trial judge's decision. However, Merion filed timely exceptions and was granted leave to file further exceptions within ten days of the completion and filing of the transcript of testimony. After the additional exceptions were filed, all were briefed and argued before a three-judge court en banc which included the trial judge. The court en banc entered what it styled as a "Judgment N.O.V." in favor of Merion with respect to the damages awarded for lost profits on the ground that such losses had not been proven with sufficient certainty to permit their inclusion in the decision returned against Merion. The court said The lost profits which are alleged by defendants [Muelles] are remote, are speculative and were not proved at trial to a degree of certainty that would warrant the grant of those damages. The court finds that defendant's business was unestablished and inoperable for spring manufacturing purposes prior to the time of the making of the contract. (Op.Ct. En Banc, p. 7)

Merion's remaining exceptions were dismissed and the court ordered that judgment be entered in favor of Muelles in the reduced amount of $34,000.00.

Muelles filed an appeal challenging 1) the propriety of the "Judgment N.O.V.," 2) the court's failure to award a specific amount for the interest element of the damages assessed and 3) mistakes or errors in the transcript of testimony. Merion also filed an appeal claiming that the trial court's conclusion that it had breached the contract was against the weight of the evidence and that the damages assessed for losses due to "nonproductive plant" and for "operating loss" were not supported by any competent evidence of record.

FACTS

The agreement upon which these appeals are based is evidenced by two handwritten memoranda, signed by the parties, which were executed on May 21, 1972, in the Greyhound Bus Terminal in Philadelphia. 2 The memoranda set forth the agreement of the plaintiff to sell, and the defendant to buy, twenty-five automotive spring manufacturing machines for the sum of $42,250.00. One memorandum stated that the machines were to be "working and running" while the other stated only that they were to be "working." The machines had been purchased earlier by Merion at a public sale in Detroit. Merion first offered the machines for sale at the end of April, 1972, while they were still in Detroit. Muelles learned through a broker that the machinery was offered for sale and Muelles' president, Luis Garcia Torres, and its general manager, Emilio Cano Bazaldua, traveled to Detroit. There the two men made a superficial inspection of the equipment. At that time, the machines were partially disassembled and being prepared for shipment to Merion's plant in Philadelphia. Torres and Cano accepted Merion's invitation to inspect the machinery more thoroughly in Philadelphia and they visited Merion's plant accompanied by a Mr. Mota, an engineer hired in Detroit for the purpose of assisting in the inspection. At the end of this visit, the memoranda were signed.

Subsequent to the formation of the agreement and upon Merion's request, Muelles forwarded a check to Merion in the amount of $2,000.00 as a deposit on the full purchase price of the machinery. In an accompanying letter, Muelles stated that it expected the machines to be delivered "working and running to our satisfaction." On June 5, 1972, Merion responded, denying having committed itself to turn over the machinery in such condition as to satisfy Muelles, but stating that it would comply with the terms set out in the memoranda. Merion again wrote to Muelles on July 25, 1972, and demanded that Muelles pay the balance due on the purchase price or storage charges of $8,000.00 or forget about the transaction and forfeit the sum already paid. In response, Muelles offered information legitimizing the delays. It informed Merion that the Mexican government had altered the regulations governing the importation of machinery and that it was Having failed to obtain the requested payment, on July 30, 1972, Merion again wrote to Muelles demanding this time only that the Mexican firm pay the additional deposit of $8,000.00 demanded on July 25. On August 30, 1972, Muelles sent a check to Merion in the amount of $6,000.00 and promised to send $2,000.00 more the following week. Muelles also informed Merion that it required six pictures and detailed specifications for each machine from Merion in order to procure the necessary import license. Muelles was tardy in sending the additional $2,000.00. On October 6, 1972, Merion demanded that Muelles pay the $2,000.00 plus one-half of the handling and loading charges, a total sum of $3,450.00. Merion stated that, should payment not be made within seven days, "we will assume that you are no longer interested in the equipment and you may consider your advance money as compensation for liquidated damages." These demands were renewed on October 18. On October 21, 1972, Muelles sent a check for $2,000.00. In an accompanying letter, Muelles agreed to pay the extra charges, but asked for an adjustment in the date from which these storage and handling charges began to accrue. Muelles also again sought the information it required to obtain an import license. Both by letter and cable, on October 30, Merion again demanded payment of $3,400.00.

seeking legal advice as to how to proceed with respect to obtaining an import license.

On November 1, 1972, however, matters took a turn for the better. By letter, Merion assured Muelles that "we are trying to cooperate with you" and acknowledged receipt of the October 21st letter. After setting forth a calculation showing $36,150.00 due on account, Merion asked that Muelles pay $16,150.00. On November 16, 1972, Merion again wrote to Muelles stating that it was sending two pictures of each machine and "whatever information we had available to us." Merion stated that it performed these tasks as "a favor to you at no charge" but suggested that, if Muelles needed anything further along these lines, it contact someone else to do the work. Merion closed by saying, "we have done more than we should and insist upon payment of an additional $16,150.00 ...." This demand was renewed on December 1, 1972, and again Merion threatened to sell the equipment if payment was not tendered within seven days.

In January, 1973, a Merion representative then in Mexico received an additional $10,000.00 on account. Relations between the two parties were stable for two months, but in March, Merion twice demanded that Muelles make an additional payment of $8,000.00. During the Spring of 1973, Muelles completed construction of the plant intended to house the twenty-five machines. In June, 1973, Cano again visited Philadelphia in order to make a final inspection of the equipment and tender final payment of the balance then due. However, this inspection disclosed that some of the machines had been cannibalized and some parts were missing. Moreover, some of the machines were missing altogether and few, if any, were in operable condition. Cano returned to Mexico without making any payment and without the machinery. By letter, On June 29, 1973, Muelles informed Merion as to some of the defects revealed by the inspection. On July 12, 1973, Merion informed Muelles by letter and confirming cable that it considered Muelles to be in default and that a public sale of the machinery would be held on July 20, 1973. At the sale, Merion purchased the machinery for a nominal sum. Thirteen months later, Merion filed suit for the balance of the purchase price and the expenses of storage and handling.

SCOPE OF REVIEW

Our initial task in this case, as in every case which we undertake to review, is to determine our proper scope of review. In the case before us, the trial judge heard the testimony without a jury pursuant to Pa.R.C.P. No. 1038. As permitted by that rule, the trial judge made only general findings of liability as to all parties and he disposed of...

To continue reading

Request your trial
22 cases
  • Delahanty v. First Pennsylvania Bank, N.A.
    • United States
    • Pennsylvania Superior Court
    • September 26, 1983
    ...state of the record, he could only have been speculating. It is important to note that the evidence presented in Merion Springs v. Torres, --- Pa.Super. ---, 462 A.2d 686 (1982) was quite detailed and, accordingly, this Court awarded future lost profits in that case.8 Section 909 of the Res......
  • Guidance Endodontics LLC v. Dentsply Int'l Inc. A Del. Bus. Corp.
    • United States
    • U.S. District Court — District of New Mexico
    • March 23, 2010
    ...sought to estimate prospective damages when selecting the liquidated damages amount); Merion Spring Co. v. Muelles Hnos. Garcia Torres, S.A., 315 Pa.Super. 469, 492, 462 A.2d 686, 699 (1983) (holding that the evidence proffered by the plaintiff was sufficient to warrant awarding lost profit......
  • Birth Center v. St. Paul Companies, Inc.
    • United States
    • Pennsylvania Superior Court
    • March 9, 1999
    ...suffered; it is proving income and outgo that the amount of any kind of profit is established. Merion Spring Co. v. Muelles Hnos. Garcia Torres, S.A., 315 Pa.Super. 469, 462 A.2d 686, 695 (1983) (quoting Restatement (Second) of Contracts § 331 cmt. c). Thus, lost profits may not be awarded ......
  • In re Jackson
    • United States
    • U.S. Bankruptcy Court — Eastern District of Pennsylvania
    • December 9, 1988
    ...See Blackwood Coal Co. v. Diester Concentrator Co., 626 F.Supp. 727, 731-32 (E.D.Pa.1985); and Merion Spring Co. v. Muelles Hnos. Garcia Torres, 315 Pa.Super. 469, 487, 462 A.2d 686, 698 (1983). The Blackwood court further stated, citing Merion, that "it is often very difficult for a new bu......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT