Milford Emp. Ass'n v. City of Milford

Citation427 A.2d 859,179 Conn. 678
CourtConnecticut Supreme Court
Decision Date26 February 1980
Parties, 106 L.R.R.M. (BNA) 2382 MILFORD EMPLOYEES ASSOCIATION et al. v. CITY OF MILFORD.

John R. Williams, New Haven, with whom, on brief, was Sue L. Wise, New Haven, for appellants (plaintiffs).

Andrew J. Broughel, Milford, with whom was George F. Martelon, Jr., Milford, for appellee (defendant).

Before COTTER, C. J., and LOISELLE, BOGDANSKI, PETERS and HEALEY, JJ.

HEALEY, Associate Justice.

The plaintiffs 1 were employed as inspectors in the engineering division of the department of public works of the defendant city of Milford. On June 30, 1972, they were discharged after a decision by the city's board of aldermen that, due to budgetary considerations, their positions were to be eliminated. Thereafter, the plaintiffs filed a grievance with the city's civil service commission. The plaintiffs claimed that they were wrongfully discharged for two reasons: (1) their discharge was based on personal and political animosity; and (2) their discharge was planned so that they could be replaced with temporary employees hired under the Federal Emergency Employment Act. The commission found in favor of the defendant city and the parties then submitted the matter to the state board of mediation and arbitration for arbitration. The submission to the arbitrators read as follows: "Were Louis Krasenics and Ralph Pascarelli terminated from their employment in accordance with the layoff provision of Article VIII, Section 4 of the Civil Service Rules and Regulations? If not, what is the remedy?" The arbitrators issued the following award: "Louis Krasenics, and Ralph Pascarelli were terminated from their employment in accordance with the layoff provision of Article VIII, Section 4, of the civil service rules and regulations." 2 Upon that determination the plaintiffs brought an action in the Superior Court, pursuant to General Statutes §§ 52-420 and 52-418, in which they sought to have the award vacated and to be reinstated in their positions with back pay. The matter was referred to a state trial referee. The complaint before the referee was in three counts. 3 In the first count the plaintiffs claimed that the award of the arbitrators should be vacated on the ground that the "arbitrators have exceeded their powers (and) so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made." See General Statutes § 52-418(d). In the second count they claimed that the award was null and void because it was rendered after the period in which the arbitration board was to act had expired. 4 In the third count they alleged that the city acted unlawfully and in bad faith in discharging the plaintiffs and that, in so doing, it violated 42 U.S.C. § 4881(a)(1)(B) of the Federal Emergency Employment Act. Over the objection of counsel for the city, the plaintiffs presented evidence before the referee that was substantially the same as that received by the arbitration panel. The state trial referee made an extensive finding addressing the merits of the plaintiffs' claim of wrongful discharge and rendered judgment for the defendant. The appeal to this court followed.

Although the plaintiffs raised various issues below as well as on appeal, 5 a preliminary matter must be considered, that is, the extent of judicial review of arbitration awards. "Arbitration is a contractual remedy designed to expedite, in an informal context, the resolution of disputes." Waterbury Board of Education v. Waterbury Teachers Assn., 168 Conn. 54, 62, 357 A.2d 466, 470 (1975). We have always respected the autonomy of the arbitration process and have often said that an arbitration award will be disturbed only where it clearly falls within the proscriptions of General Statutes § 52-418. Ibid.; Board of Education v. Bridgeport Education Assn., 173 Conn. 287, 290, 377 A.2d 323 (1977); Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., 164 Conn. 472, 475, 325 A.2d 274 (1973); International Union v. Fafnir Bearing Co., 151 Conn. 650, 653, 201 A.2d 656 (1964); United Electrical Radio & Machine Workers v. Union Mfg. Co., 145 Conn. 285, 288, 141 A.2d 479 (1958).

The right to review of the award exists only by statute. Thus, if evidence is to be received at all by the trial court, it is to be evidence tending to prove that the award is impeachable under any of the grounds set out in § 52-418. See Board of Education v. Bridgeport Education Assn., supra, 173 Conn. 294, 377 A.2d 323; Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., supra, 164 Conn. 475-76, 325 A.2d 274. The plaintiffs made no claim that the award was procured by corruption or fraud, that the arbitrators acted out of partiality or by corruption, or that the arbitrators wrongfully refused to postpone the hearing or to receive evidence. See General Statutes § 52-418(a) through (c). Therefore, under the facts of this case, the only issue properly raised was whether "the arbitrators ... exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made." General Statutes § 52-418(d). Every reasonable presumption and intendment will be made in favor of the award and, hence, the burden rests upon the plaintiffs to produce evidence sufficient to invalidate or avoid it. Gary Excavating Co. v. North Haven, 160 Conn. 411, 413, 279 A.2d 543 (1971); Von Langendorff v. Riordan, 147 Conn. 524, 527, 163 A.2d 100 (1960); 6 C.J.S. Arbitration § 172. 6

To determine whether the arbitrators exceeded their authority, we look to the submission to see if it conforms to the award. See Ramos Iron Works, Inc. v. Franklin Construction Co., 174 Conn. 583, 587, 392 A.2d 461 (1978); Board of Education v. Waterbury Teachers' Assn., 174 Conn. 123, 127, 384 A.2d 350 (1977); Norwich Roman Catholic Diocesan Corporation v. Southern New England Contracting Co., supra, 164 Conn. 477, 325 A.2d 274. It is apparent that it clearly does so. The submission in this case was unrestricted and the award is therefore final and binding and cannot be reviewed for errors of law or fact. Ibid.; Meyers v. Lakeridge Development Co., 173 Conn. 133, 135, 376 A.2d 1105 (1977). The arbitrators did not exceed their authority 7 and there was no evidence before the court to demonstrate that they imperfectly executed their powers. Their award was a mutual, final and definite award upon the subject matter submitted to them.

Essentially, the plaintiffs claim that the arbitrators' ultimate conclusion of fact, i. e., that the plaintiffs were not wrongfully discharged, may be reviewed because it is entirely against the evidence presented. 8 Thus, the plaintiffs assert that, as a matter of law, the evidence required a conclusion in their favor. See, e. g., Darling v. Burrone Bros., Inc., 162 Conn. 187, 192, 292 A.2d 912 (1972). They sought to have the trial court grant them a full trial on this claim. This our statute does not permit; cf. Pa.Stat.Ann., title 5, § 71(5); Mitchell v. Pittsburgh, 233 Pa.Super. 119, 335 A.2d 403 (1975); and our policy in this area opposes. See Costello Construction Corporation v. Teamsters Local 559, 167 Conn. 315, 317n., 355 A.2d 279 (1974). The parties freely bargained for the remedy of arbitration in the event of a dispute of this nature. Having done so, they are bound by the decision lawfully rendered. Waterbury Board of Education v. Waterbury Teachers Assn., 168 Conn. 54, 62, 357 A.2d 466 (1975).

The plaintiffs also claim that they are entitled to have the arbitration award reviewed on the ground that the arbitrators did not determine whether a provision of the Federal Emergency Employment Act of 1971 was violated. At the time of the plaintiffs' discharge, 42 U.S.C. § 4881(a)(1)(B) prohibited the allocation of funds under the act to stimulate employment where the result would be "the displacement of currently employed workers." 9 This claim has no merit for two reasons. The first is that the record does not disclose that the arbitrators did not consider this provision in coming to their award. The second is that the plaintiffs' theory of wrongful discharge was based upon the alleged violation of this provision, whether expressly so stated or not. The central issue before the board was whether the plaintiffs' positions had been abolished in good faith. The board's conclusion on that issue is dispositive of this claim because no one can displace someone whose position has been abolished in good faith.

There is no error.

In this opinion the other judges concurred.

1 The individual plaintiffs ...

To continue reading

Request your trial
32 cases
  • American Universal Ins. Co. v. DelGreco, 13067
    • United States
    • Connecticut Supreme Court
    • 1 Septiembre 1987
    ...453 A.2d 1158; Bridgeport v. Bridgeport Police Local 1159, 183 Conn. 102, 105-106, 438 A.2d 1171 (1981); Milford Employees Assn. v. Milford, 179 Conn. 678, 683, 427 A.2d 859 (1980); Waterbury v. Waterbury Police Union, supra; Meyers v. Lakeridge Development Co., 173 Conn. 133, 135, 376 A.2d......
  • O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
    • United States
    • Connecticut Supreme Court
    • 14 Abril 1987
    ...IFPTE, supra; Administrative & Residual Employees Union v. State, supra; Schwarzschild v. Martin, supra; Milford Employees Assn. v. Milford, 179 Conn. 678, 682, 427 A.2d 859 (1980); Ramos Iron Works, Inc. v. Franklin Construction Co., supra; Von Langendorff v. Riordan, 147 Conn. 524, 527, 1......
  • State v. AFSCME, Council 4, Local 391.
    • United States
    • Connecticut Supreme Court
    • 6 Agosto 2013
    ...298 (1983). Where the submission is unrestricted, the award cannot be reviewed for errors of law or fact. Milford Employees Assn. v. Milford, 179 Conn. 678, 683, 427 A.2d 859 (1980). There is no dispute that this case involved an unrestricted submission to the arbitrator. The arbitrator was......
  • AFSCME v. Dep't of Children & Families
    • United States
    • Connecticut Supreme Court
    • 23 Junio 2015
    ...of an arbitral award is a far cry from a trial de novo”). This court considered a similar argument in Milford Employees Assn. v. Milford, 179 Conn. 678, 684, 427 A.2d 859 (1980), wherein “the plaintiffs assert[ed] that, as a matter of law, the evidence required a conclusion in their favor.”......