Milwaukee County v. Schmidt, Garden and Erikson

Citation168 N.W.2d 559,43 Wis.2d 445
Decision Date27 June 1969
Docket NumberNo. 340,340
PartiesCOUNTY OF MILWAUKEE, a municipal body corporate, Appellant, v. SCHMIDT, GARDEN & ERIKSON, a partnership, et al., Respondents.
CourtUnited States State Supreme Court of Wisconsin

The critical facts in this matter are undisputed. Milwaukee County, appellant, and Schmidt, Garden & Erickson, a Chicago architectural firm, respondents, entered into a written contract on April 6, 1949, for architectural services.

Among other provisions the contract provided that respondents were to (1) prepare plans and specifications for an addition to Milwaukee County General Hospital, (2) exercise general supervision of constitution, (3) interpret plans and specifications, (4) issue certificates of payment, (5) keep accounts, and (6) assume general administration of the work.

Upon completion of specifications and general working drawings, architectural fees equaling 75 percent of the commission rate, based upon estimated costs, became due. The remaining 25 percent was to be paid from time to time during the execution of the work with the amount thereof computed upon final cost of work.

In July, 1949, respondents, with appellant's approval, associated with Brust & Brust, Milwaukee architects, and the latter by written agreement assumed complete charge of architectural supervision and undertook other responsibilities for which they were to receive 20 percent of the fee paid respondents. Final payment was to become due upon completion of the project.

In June, 1957, the structure was approximately 99.5 percent complete and appellant had taken partial occupancy. On or about August 25, 1957, the building was open to visitors. At this time, operating and recovery rooms of the new addition were in use and had been in use since November 13, 1956. The dietary department and cafeteria opened December 19, 1956; the morgue in January, 1957; first aid in February, 1957; x ray in March, 1957; physiotherapy in April, 1957; and medical records in May, 1957. Resident patients, however, were still confined to the old hospital.

As of December 17, 1957, final certificates of payment had been issued to all contractors except the heating contractor. On October 4, 1957, $541,726.71 had been paid out to the heating contractor but a balance of $2,000 was withheld. The final certificate of payment for $2,000 was not issued to the heating contractor until March 23, 1959.

Beginning in the latter part of 1957 and continuing throughout 1958, the parties corresponded frequently regarding deficiencies. In October, 1957, appellant submitted a list of 32 deficient items to respondents. One of these related to heating. In April and November, 1958, appellant informed respondents that the heating was unacceptable. Ultimately the heating contractor was requested to check the heating and to balance the heating system in certain sections. On March 20, 1959, the contractor informed the associate architect that all outstanding items relating to heating had been completed. Thereafter, on March 23, 1959, the final certificate of payment was issued to the heating contractor. The next day, March 24, 1959, respondents submitted their invoice for final payment of the balance due for architectural fees. In total, respondents received approximately $598,000.

On March 18, 1965, this action was commenced against respondents by service of summons. On April 2, 1965, a complaint was served. That complaint alleged in part as follows:

'7. Notwithstanding the defendants' knowledge, skill and experience, they prepared and furnished plans and specifications which were defective in failing to provide adequate heating for the addition. As a result, substantial areas of the hospital addition were underheated and incapable of occupancy either by patients or personnel. Heating was so inadequate that water service pipes in various areas froze and it became necessary to introduce supplemental heating and other temporary measures to prevent excessive infiltration of cold air. Notwithstanding the efforts exerted by plaintiff to alleviate the conditions, heating and temperature control was inadequate.

'8. Upon information and belief, the defendants, in their performance of the contract:

'(a) Failed to calculate heat losses based upon windows installed in conformity with the drawings, plans and specifications.

'(b) Prepared and furnished drawings, plans and specifications which prescribed air units heating coils improperly sized for capacity and which did not provide final air temperature specified.

'(c) Prepared and furnished plans and specifications which prescribed a system of circulation in which pumps were to connect with common supply and return headers, thereby establishing a common system pressure drop precluding attainment of the pumping conditions in the individual zones, as required by plans and specifications.

'(d) Prepared and furnished plans and specifications which failed to provide for installation of:

'i. Expansion joints in erection of exterior brick walls.

ii. Exhaust fans generating sufficient heat and capacity to properly purge laboratory fume hoods.

'iii. Windows in air conditioned surgical areas requiring sterile conditions adequate and sufficient to provide and maintain such sterile conditions.

'iv. An emergency electrical generator independent in its operation of the central source of supply; that the plans and specifications should have provided for installation of an independent self-sustaining electrical emergency generator.

'9. As a result of the defendants' failure to prepare and furnish adequate and sufficient drawings, plans and specifications and to properly and efficiently supervise and inspect construction, all in breach of its contract, the hospital addition was not fit and suitable for the purpose for which it was designed and erected, and plaintiff was, and will in the future be, required to expend substantial sums of money to remedy the defects. Notwithstanding these deficiencies resulting from the defendants' activities, they issued certificates of payment to various contractors engaged in the construction of the addition.

'10. Upon information and belief the defendants in the preparation of drawings, plans and specifications and inspection and supervision of construction work failed to exercise due diligence and skill and due to their breach of the duties assumed by them, pursuant to the contract provisions and arising from their status as professional architects and engineers, the plaintiff was already expended $74,000.00 to remedy defects and will be required to expend an additional $507,000.00 and accordingly has sustained damages in the amount of $581,000.00.'

Respondents answered, demurred, and set up as an affirmative defense and as grounds for demurrer the statute of limitations. The issue of limitations was tried to the court and judgment was entered dismissing plaintiff-appellant's complaint on its merits on the ground that the cause of action was barred by sec. 893.19(5), Stats., which reads as follows:

'893.19 Within 6 years: * * *

'* * *

'(5) An action to recover damages for an injury to property, or for an injury to the character or rights of another, not arising on contract, except in case where a different period is expressly prescribed.'

The County of Milwaukee appeals from that judgment.

Robert P. Russell, Corp. Counsel, James J. Bonifas, Deputy Corp. Counsel, Milwaukee, for appellant.

Niebler & Herro, Menomonee Falls, Chester J. Niebler, Menomonee Falls, of counsel, for respondents.

WILKIE, Justice.

This appeal turns on the answer to a single question: On March 18, 1959, six years prior to the commencement of this action, had the statute of limitations started to run on such action against the plaintiff?

The trial court correctly saw this as the lone issue in this controversey and in holding that sec. 893.19(5), Stats., rather than sec. 893.19(3), applied in this matter, the trial court necessarily concluded that the cause of action was not in contract but in tort. Since either subsection invokes a six-year statute of limitation, the crucial inquiry must be as to from which event the statute of limitations started to run and this, in turn, depends on the nature of the action.

The trial court, as the respondents here now contend, regarded the cause of action as being in tort, namely, malpractice. The trial court concluded that '(t)he cause of action either arises from an act of omission in design or an act of omission in the supervision of the construction.'

If respondents are correct that plaintiff's cause of action is in tort and as in malpractice the cause of action accrues when the injury caused by the professional malpractice occurs, as distinguished from when the injury is discovered at a later date, 1 then the cause of action would seem to have accrued well before the critical date here, March 18, 1959.

Appellant's only argument that its cause of action, if in tort, survives the six-year statute, is that the respondents committed an act of professional malpractice when they issued the final certificate for the heating contract on March 23, 1959 (such date being later than the crucial date of March 18, 1959). We agree with respondents that the issuance of this certificate was merely an 'administrative' act.

Attached to the certificate of payment was a sworn contractor's statement indicating that the contractor had completed his contract as of January 31, 1959. There was nothing for the architects to do but confirm that completion, which they did. Moreover, respondents correctly contend that even if the issueance of that certificate were a 'supervisory' act, there was no allegation in the complaint that such act was in any way improper; this follows from the fact that in the complaint there is no allegation of improper supervision on or after March 18, 1959, and the design (plans and specifications) was completed long before March 18, 1959.

We must necessarily...

To continue reading

Request your trial
34 cases
  • Peterson v. Roloff
    • United States
    • Wisconsin Supreme Court
    • January 30, 1973
    ...2 Ill.Rev.Stat., ch. 83, sec. 22.1 (1965); Ore.Rev.Stat. sec. 12.110(4) (1967).9 41 Wis.2d at 656, 657, 165 N.W.2d at 186.10 (1969), 43 Wis.2d 445, 168 N.W.2d 559.11 (1970), 48 Wis.2d 528, 180 N.W.2d 521.12 Peppas v. Marshall & Ilsley Bank (1957), 2 Wis.2d 144, 86 N.W.2d 27.13 For good disc......
  • CLL Associates Ltd. Partnership v. Arrowhead Pacific Corp.
    • United States
    • Wisconsin Supreme Court
    • November 30, 1992
    ...320 (1983) (citations omitted); see also Denzer v. Rouse, 48 Wis.2d 528, 531, 180 N.W.2d 521 (1970); Milwaukee County v. Schmidt, Garden & Erikson, 43 Wis.2d 445, 455, 168 N.W.2d 559 (1969); Krueger v. P. Christianson Silo Co., 206 Wis. 460, 462-63, 240 N.W. 145 (1932); Ott v. Hood, 152 Wis......
  • Gates Rubber Co. v. USM Corp.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • February 12, 1975
    ...352 N.Y.S.2d 502 (architect); Denzer v. Rouse, 48 Wis.2d 528, 180 N.W.2d 521 (1970) (attorney); and County of Milwaukee v. Schmidt, Garden & Erikson, 43 Wis.2d 445, 168 N.W.2d 559 (1969) (architect).The discovery rule has also been applied in actions against a contractor for negligent const......
  • Giampapa v. American Family Mut. Ins. Co.
    • United States
    • Colorado Supreme Court
    • February 24, 2003
    ...contract. See, e.g., Brown v. Matthews Mortuary, Inc., 118 Idaho 830, 801 P.2d 37, 45-46 (1990); County of Milwaukee v. Schmidt, Garden & Erikson, 43 Wis.2d 445, 168 N.W.2d 559, 563 (1969). Some states have adopted the rule, usually in conjunction with other exceptions, that emotional and m......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT