Montana Power Co. v. Federal Power Commission, 9322.

Decision Date14 June 1940
Docket NumberNo. 9322.,9322.
PartiesMONTANA POWER CO. v. FEDERAL POWER COMMISSION.
CourtU.S. Court of Appeals — Ninth Circuit

W. H. Hoover and J. E. Corette, Jr., both of Butte, Mont., and A. J. G. Priest and Sidman I. Barber, both of New York City (Reid & Priest, of New York City, and Corette & Corette, of Butte, Mont., of counsel), for petitioner.

David W. Robinson, Jr., Gen. Counsel, Willard W. Gatchell, Wallace H. Walker, Louis W. McKernan, William B. Spohn, and William J. Costello, Counsel, Federal Power Commission, all of Washington, D. C., for respondent.

Before GARRECHT, HANEY, and HEALY, Circuit Judges.

HANEY, Circuit Judge.

We are asked to review an order of the Federal Power Commission denying petitioner's application for a license to construct an electric power transmission line.

Missoula, Montana, is about 70 miles northwest of Anaconda, Montana. The Flathead power project is about 50 miles north and slightly west of Missoula. The Thompson Falls, Montana, power project is about 45 miles west of the Flathead project. Petitioner has power facilities at and near Anaconda for serving Anaconda and points easterly and northeasterly therefrom. It has power facilities at Missoula to serve Missoula and points south. It has power facilities at Flathead which it operates under a license from the Commission as Project No. 5. It also has power facilities at Thompson Falls. Petitioner owns no transmission line connecting these points, but has the right to use a line belonging to a railroad upon certain conditions, which line connects some of the points.

On November 20, 1936, petitioner filed an application for a license to construct a transmission line as follows: a line 56 miles long beginning at Thompson Falls and terminating at the Flathead project; and a line 145 miles long, beginning at the Flathead project, through Missoula and terminating at Anaconda, thus connecting all the points mentioned. In accordance with that plan the line was thereafter constructed. A line of about 1500 feet in length connects the line in question with the Flathead project.

The Commission found:

"(1) The line will serve principally as a primary line transmitting energy from the aforesaid Flathead plant to points of junction with the distribution system of the applicant at Thompson Falls, Missoula, and Anaconda, Montana, in addition to serving as an interconnection between those distribution systems;

"(2) When carrying the maximum energy that can be generated at the Flathead plant, after that project has been completed and is operating at its ultimate installed capacity, the transmission line cannot carry any substantial amount of power from other sources either to the aforesaid distribution system at Thompson Falls or to the distribution systems at Missoula or Anaconda;

"(3) The line is properly, therefore, a part of the Flathead project within the meaning of Section 3(11) of the Federal Power Act 16 U.S.C.A. § 796(11) as a necessary adjunct to that complete unit of development;"

It is ordered that the application "for the license for the line as a minor part only of a complete project be and it hereby is denied" and further ordered that upon submission of certain revised and additional exhibits, the license for Project No. 5 would be amended to include the line therein. Application for rehearing was made and denied. Petitioner thereupon filed this petition to review the order.

The only two acts pertinent here are the Act of June 10, 1920, Ch. 285, 41 Stat. 1063, and the Act of August 26, 1935, Ch. 687, 49 Stat. 803, 838.1 By § 30 of the first mentioned act, such act was designated as "The Federal Water Power Act", 16 U.S. C.A. § 791 et seq. The second mentioned act was designated as the "Public Utility Act of 1935" and consisted of two titles, the first of which was designated as the "Public Utility Holding Company Act of 1935", 15 U.S.C.A. § 79 et seq., and is not here pertinent. (§ 33). Title II of the Public Utility Act of 1935, 16 U.S.C.A. § 791a et seq., amended the Federal Water Power Act, and by § 212, 49 Stat. 847, provided that sections 1 to 29, inclusive, of what had been called The Federal Water Power Act, should constitute Part I of that act, the title to which was abandoned by repeal of § 30 of what had been called The Federal Water Power Act. Title II of the Public Utility Act of 1935, also amended, by § 213 thereof, what had been called the Federal Water Power Act, by adding thereto two parts, the last of which contained (in the last section thereof, § 320) the short title for what had been called The Federal Water Power Act as amended, including the amendments made by the Public Utility Act of 1935. Such short title was and is the "Federal Power Act" and the title "The Federal Water Power Act" is no longer the correct title of the act.

Section 3 of the Federal Power Act, provides in part:

"That the words defined in this section shall have the following meanings for the purposes of this Act chapter, to wit: * * *

"(11) `project' means complete unit of improvement or development, consisting of * * * the primary line or lines transmitting power therefrom to the point of junction with the distribution system or with the interconnected primary transmission system * * *

"(12) `project works' means the physical structures of a project * * *."2

Section 4 of the act provides in part:

"That the Commission is hereby authorized and empowered — * * *

"(e) To issue licenses to citizens of the United States * * * or to any corporation organized under the laws of the United States or any State thereof * * * for the purpose of constructing, operating, and maintaining * * * transmission lines * * *."3

Section 10 of the act provides in part:

"That all licenses issued under this Part4 shall be on the following conditions: * * *

"(a) That the project adopted, including the maps, plans, and specifications, shall be such as in the judgment of the Commission will be best adapted to a comprehensive plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, and for other beneficial public uses, including recreational purposes; and if necessary in order to secure such plan the Commission shall have authority to require the modification of any project and of the plans and specifications of the project works before approval. * * *5

"(g) Such further other conditions not inconsistent with the provisions of this Act chapter as the commission may require * * *

"(i) In issuing licenses for a minor part only of a complete project * * * the Commission may in its discretion waive such conditions, provisions, and requirements of this Part6 chapter, except the license period of fifty years, as it may deem to be to the public interest to waive under the circumstances * * *."7

Provision for review of the orders of the Commission is found in § 313(b) of the act.8

Petitioner contends that the Commission based its order on a mistake of law in holding that the Flathead project could include the line in question. It is said that the line in question is an interconnected primary transmission system; that the definition of "project" by § 3(11) of the Federal Power Act limits the Flathead project to the place of connection with the line in question by the line 1500 feet long; that therefore, the Commission has decided that a project may consist of more than "to the point of junction with the distribution system or with the interconnected primary transmission system". This contention is not borne out by the...

To continue reading

Request your trial
7 cases
  • Alabama Power Co. v. Federal Power Commission
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • March 30, 1942
    ...action of the Commission must be sustained."; 1 Pike and Fischer, Admin. Law, Current Text, § 34c.1. 39 Cf. Montana Power Co. v. Federal Power Commission, 9 Cir., 112 F.2d 371, 374. 40 Federal Water Power Act of 1920, § 14, 41 Stat. 1071, as amended by the Federal Power Act of 1935, 49 Stat......
  • U.S. v. Southern California Edison Co.
    • United States
    • U.S. District Court — Eastern District of California
    • February 6, 2006
    ...or appropriate in the maintenance and operation of such unit; 16 U.S.C.A. § 796 (emphasis added); see also Montana Power Co. v. FPC, 112 F.2d 371, 373 (9th Cir.1940). The point of demarcation between licensable and unlicensable equipment is the "point of junction with the distribution syste......
  • Public Utilities Com. v. Energy Resources Conservation & Dev. Com.
    • United States
    • California Court of Appeals Court of Appeals
    • January 4, 1984
    ...the powerplant to the interconnected transmission grid, it falls within the Commission's jurisdiction. (Montana Power Co. v. Federal Power Comm'n. (9th Cir., 1940) 112 F.2d 371, 374.) "[T]he test to be applied is that of the basic purpose of the line in relation to other facilities." (Re We......
  • Joseph Gann, Inc. v. Commissioner
    • United States
    • U.S. Tax Court
    • March 1, 1982
    ... ... following deficiencies in petitioner's Federal income taxes: ...          Taxable year ... Thor Power Tool Co.v. Commissioner 79-1 USTC ¶ 9139, 439 ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT