Moosman v. Joseph P. Blitz, Inc., 276

Citation358 F.2d 686
Decision Date29 March 1966
Docket NumberNo. 276,Docket 29930.,276
PartiesWilliam MOOSMAN, doing business as William Moosman Company, Plaintiff-Appellee, v. JOSEPH P. BLITZ, INC. and Maryland Casualty Company, Defendants-Appellants, v. AETNA INSURANCE COMPANY, Third-Party Defendant.
CourtUnited States Courts of Appeals. United States Court of Appeals (2nd Circuit)

Jacob D. Zeldes, Bridgeport, Conn. (David Goldstein, Elaine S. Amendola and Robert S. Cooper, Bridgeport, Conn., on the brief), for plaintiff-appellee and third party defendant.

Leo J. McNamara, Norwich, Conn. (Allyn L. Brown, Jr., Norwich, Conn., on the brief), for defendants-appellants.

Before SMITH, HAYS and ANDERSON, Circuit Judges.

J. JOSEPH SMITH, Circuit Judge:

In action by painting subcontractor on 500 unit Capehart Act project at New London, Connecticut, against the general contractor and its surety, the United States District Court for the District of Connecticut, Edward C. McLean, District Judge, entered judgment for the plaintiff on the complaint and for the defendant to recover on the counterclaim. Both parties appeal. We find no error and affirm the judgment.

Moosman brought this action for the balance due under his contract with Blitz, for regular work at the agreed price, and for extra work, which under the contract was to be for reasonable value. The court allowed $29,595.48 of plaintiff's total. Blitz counterclaimed for $47,476.66, for breach of contract. The court allowed $2,407.66. Moosman has cross-appealed from denial of his motion for summary judgment, for increase to $40,348.87 in the judgment.

On the appeal of Blitz and its surety, the first claim is that the findings are inadequate; on the contrary, they are complete and clear. Blitz' difficulty is not with the lack of findings, but with the lack of evidence to support claimed items of its counterclaim. Of Moosman's claim, the amount due on the original contract, $19,513.41 is not in dispute. Of the extras, for which Blitz agreed to pay in accordance with the contract on a time and material basis, the amount due on items 6, 7, 8 and 9, totalling $733.95 was conceded. On items 3, 4, 5 and 11, on sufficient evidence, the court found due respectively $1,542.19, $6,763.00, $525.58 and $517.35; an overall total including the amount due on the original contract, of $29,595.48. On the counterclaim, on items of corrective work on which Blitz kept records of cost, the court allowed $2,407.60. Nothing was allowed on a claim for damages for delay, for lack of proof that Moosman caused the delay. For other corrective work, although some was found to have been required, the award was limited to nominal damages of 6 cents, since no records were kept and no evidence presented which would allow any sort of computation of amount. Blitz can point to nothing in the record to cast doubt on this holding.

The court awarded Moosman interest from the date of suit. This was entirely proper. Under Connecticut law, here applicable, interest was recoverable even though the claim was unliquidated and the amount not fully ascertained before suit. Campbell v. Rockefeller, 134 Conn. 585, 59 A.2d 524 (1948), Bush v. Remington Rand, 213 F.2d 456, 466, 2 Cir. 1954. Since the proof did not show the date of the breach (payment of Blitz by the government) interest from the date of the action was appropriate. Venezia v. Town of Fairfield, 118 Conn. 325, 332, 172 A. 90 (1934).

The cross-appeal is for the full amount of plaintiff's claim, less the allowed counterclaim, on the ground that defendant failed to respond to a request to admit within 10 days as Rule 36 requires, so that the matter is deemed admitted. This sanction is a part of the Rule. Co...

To continue reading

Request your trial
79 cases
  • Teleprompter of Erie, Inc. v. City of Erie, Civ. A. No. 81-17 ERIE.
    • United States
    • United States District Courts. 3th Circuit. United States District Court (Eastern District of Pennsylvania)
    • July 13, 1983
    ...to enter summary judgment, it is not required to do so where the opposing party has not been prejudiced. Moosman v. Joseph P. Blitz, Inc., 358 F.2d 686 (2d The subject matter of the admissions is broad and far reaching and satisfies the first requirement. Admission of the facts at issue wou......
  • In re Group Therapy, Inc., 00-CV-394A.
    • United States
    • United States District Courts. 2nd Circuit. United States District Court of Western District of New York
    • July 16, 2003
    ...McLaughlin v. Richland Shoe Co., 486 U.S. 128, 133-34, 108 S.Ct. 1677, 100 L.Ed.2d 115 (1988); see also Moosman v. Joseph P. Blitz, Inc., 358 F.2d 686, 688 (2d Cir.1966) ("It appears well settled that a failure to respond to a request to admit will permit the District Court to enter summary......
  • An-Port, Inc. v. MBR Industries, Inc., Civ. No. 91-1050 (JP).
    • United States
    • United States District Courts. 1st Circuit. District of Puerto Rico
    • September 11, 1991
    ...(1981); Luick v. Graybar Elec. Co., Inc., 473 F.2d 1360 (8th Cir.1973); Williams v. Krieger, 61 F.R.D. 142 (1973). Moosman v. Blitz, Inc., 358 F.2d 686, 688 (2d Cir. 1966); O'Campo v. Hardisty, 262 F.2d 621 (9th Cir.1958); Mahaney v. Doering, 260 F.Supp. 1006 (D.Penn.1966); Jackson v. Kotze......
  • Pellegrino v. Capital One, 19-CV-851Si(F)
    • United States
    • United States District Courts. 2nd Circuit. United States District Court of Western District of New York
    • July 28, 2021
    ...respond), rejected on other grounds by McLaughlin v. Richland Shoe Co., 486 U.S. 128, 133-34 (1988); Moosman v. Joseph P. Blitz, Inc., 358 F.2d 686, 688 (2d Cir. 1966) (“It appears well settled that a failure to respond to a request to admit will permit the District Court to enter summary j......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT