Morehouse v. Moulding

Decision Date30 September 1874
Citation74 Ill. 322,1874 WL 9133
PartiesPHILO MOREHOUSEv.THOMAS MOULDING et al.
CourtIllinois Supreme Court

OPINION TEXT STARTS HERE

APPEAL from the Superior Court of Cook county; the Hon. THEODORE D. MURPHY, Judge, presiding.

The nature and facts of this case necessary to an understanding of the points decided appear in the opinion of the court. The jury found there was due the petitioners, Kelley, Wood & Co., $330.18, and Moulding & Harlan, $860.50. The defendant, Morehouse, moved for a new trial, which was refused and an exception taken.

Messrs. DENT & BLACK, for the appellant.

Messrs. SCATES & WHITNEY, for the appellees Moulding and Harlan; Mr. G. P. WHITCOMB, for the appellees Kelly, Wood & Co.

Mr. JUSTICE SCOTT delivered the opinion of the Court:

This is a case arising under the mechanic's lien law, as contained in the act of 1869. The facts necessary to an understanding of the merits of the case may be shortly stated. In June, 1870, appellant contracted with W. H. H. Miller to erect for him a double dwelling-house on the premises described in the petition. The contract was in writing, and by its terms Miller was to furnish all the materials and labor necessary to fully complete the buildings according to the plans and specifications, at a total cost of $20,900, which was to be paid, as the work progressed, on the certificate of the architect, less fifteen per cent, which was to be reserved for the security of the owner until the completion of the work.

Appellees furnished materials which were used by the builder in the erection of the buildings under his original contract with appellant, and now seek to establish a lien on the premises for the amount respectively due them. There is no dispute, there was due Moulding and Harlan for brick furnished to Miller, and which were used in the construction of the building, $1,442, and to Kelly, Wood & Co., for lumber furnished and used for the same purpose, $555.85. Each of these firms commenced separate actions, but, by stipulation, the two suits were consolidated in the court below, and have since progressed as one cause.

Proof was made that within twenty days after payment should have been made, these parties gave appellant notice of their claims, and that they would insist upon the lien given by the statute.

The building, when completed, cost something over $30,000, but a large portion of the cost over the contract price, indeed nearly all of it, Miller insists was made up of extra work not indicated on the original plans.

This case has been elaborately argued, and should we discuss all the points made, it would require us to give a construction to almost every clause of the mechanic's lien law. But this will not be necessary. We are of opinion the decree can be maintained on principles about which there can be no controversy.

Great stress is laid on that clause of the first section of the mechanic's lien law, which provides: “In no case shall the owner or lessee be compelled to pay a greater sum for, or on "account of such...

To continue reading

Request your trial
6 cases
  • Fossett v. The Rock Island Lumber & Manufacturing Company
    • United States
    • Kansas Supreme Court
    • November 9, 1907
    ...of the terms and conditions of the original contract except those terms which prescribe the amount the owner is to pay. In Morehouse v. Moulding et al., 74 Ill. 322, where statute at the time provided that in no case should the owner be compelled to pay a greater sum than the price stipulat......
  • Graham v. Meehan
    • United States
    • United States Appellate Court of Illinois
    • October 31, 1879
    ... ... fails to complete his contract, for so much as the work and materials furnished are worth, first deducting all payments rightfully made: Morehouse v. Moulding, 74 Ill. 322; Mehrle v. Dunne, 75 Ill. 239.A sub-contractor has twenty days after completion of his work in which to give the owner ... ...
  • Jarvis v. State Bank of Ft. Morgan
    • United States
    • Colorado Supreme Court
    • March 16, 1896
    ...for the alleged nonperformance by the contractor; and we must uphold the findings of the trial court in this particular. Morehouse v. Moulding, 74 Ill. 322; Wright v. Roberts, Hun, 413; Whittier v. Blakely, 13 Or. 546, 11 P. 305. Upon the whole case, we think the judgment should be affirmed......
  • Prepakt Concrete Co. v. Fidelity and Deposit Co. of Md.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • April 1, 1968
    ...of Prepakt. Consequently the payments did not diminish the amount in Continental's hands subject to the claim of Prepakt. Morehouse v. Moulding et al., 74 Ill. 322. The court erred in failing to award interest on the judgments against Continental and Goethe from July 13, 1961, and in includ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT