Morley Const Co v. Maryland Casualty Co

Decision Date01 February 1937
Docket NumberNo. 325,325
Citation81 L.Ed. 593,57 S.Ct. 325,300 U.S. 185
PartiesMORLEY CONST. CO. et al. v. MARYLAND CASUALTY CO. *
CourtU.S. Supreme Court

[Syllabus from pages 185-187 intentionally omitted] Messrs. M. J. O'Donnell and William Buchholz, both of Kansas City, Mo., for petitioners.

Mr. Spencer F. Harris, of Kansas City, Mo., for respondent.

Mr. Justice CARDOZO delivered the opinion of the Court.

The power of an appellate court to modify a decree in equity for the benefit of an appellee in the absence of a cross-appeal is here to be admeasured.

Morley Construction Company, a petitioner in this Court, made a contract with the United States, acting by the Veterans' Administration Department for the construction of a veterans' hospital at Batavia, New York. In conformity with statute (40 U.S.C. § 270 (40 U.S.C.A. § 270)) it gave a bond for the completion of the contract and for the payment of all bills for material and labor, the respondent Maryland Casualty Company signing the bond as surety. During the progress of the work, the contractor found itself in need of a loan of money to enable it to go on. Accordingly a supplementary agreement was made between the contractor and the surety to relieve the situation. By that agreement, dated April 28, 1933, the contractor agreed to deposit in a designated trust company in Buffalo $5,000 to be used in the performance of the work and to deposit in the same account for the same purpose all moneys received from the United States as payments upon the contract. The surety agreed to deposit in the same account $5,000 as a loan to be secured by the contractor's note, and additional moneys sufficient to pay the present and future bills of plasterers, amounting, as the evidence shows, to $5,700. The contractor and the surety were to have joint control of the account, and no moneys were to be withdrawn therefrom without the approval of the surety by designated representatives, the approval to be indicated upon the check or draft in writing.

Following this supplementary agreement, the contractor went on with the work, and brought it to completion. The surety made the first payment of $5,000 in accordance with its promise but refused to pay the $5,700 owing to the plasterers. In the meantime a series of payments became owing from the Government upon estimates of value in advance of completion and acceptance. Warrants for these payments were forwarded by the Government to the trust company in Buffalo to be placed in the joint account, notice having been given by the contractor to issue them accordingly. However, a different course was followed when the final payment became due. Apparently through inadvertence, the Government sent a warrant for that payment ($59,780.82) to the contractor itself at its office in Kansas City, Missouri. The contractor endorsed the warrant, delivered it to the Merchants Bank of Kansas City, one of the petitioners in this court, and directed the bank to issue a cashier's check for like amount to the order of the contractor's president. The bank made out the check, but held it to await the payment of the warrant, which it deposited in a Federal Reserve Bank to be forwarded, in the usual course of collection, to the Treasury at Washington. Neither check nor warrant has been paid as a consequence of an injunction obtained by the respondent.

Upon learning from the Veterans' Administration Department of the transmission of the warrant, the surety began two suits, one in the District of Columbia, where the payment of the warrant was stayed by an injunction, the other the suit at bar. It recounts in its complaint the facts or most of them already stated in this opinion adding thereto that outstanding bills for more than $100,000 are covered by its bond. It says that it is entitled to the specific performance of the supplementary agreement and to a decree depositing the warrant in the trust company at Buffalo to be applied upon the joint account. It says also that by reason of the unpaid bills of materialmen and laborers there is a duty on the part of the contractor to exonerate the surety from loss or liability and to apply the warrant to that purpose. Finally, it makes claim to a right of subrogation to the position of the contractor over against the Government, a claim which apparently has been abandoned and will not engage us further. The bill of complaint ends with a prayer for relief appropriate to the several theories of liability put forward by the pleader, the theory of specific performance, the theory of exoneration, and the theory of subrogation. To render the relief effectual, the bank in Kansas City was joined as a defendant.

The District Judge held that the surety was not entitled to the specific performance of the agreement, having failed to pay the plasterers and being therefore in default itself. He held, however, that apart from any agreement the contractor was subject to a duty to exonerate the surety from present liabilities. True, there was no purpose on the part of the contractor to divert the proceeds of the warrant from the uses of the contract. As to this the finding is explicit. Even so, a cause of action for exoneration does not include among its elements the presence of a wrongful purpose. Glades County v. Detroit Fidelity Co. (C.C.A.) 57 F.(2d) 449; West Huntsville Cotton Mills Co. v. Alter, 164 Ala. 305, 51 So. 338; Pavarini & Wyne, Inc., v. Title Guaranty & Surety Co., 36 App.D.C. 348, Ann.Cas.1912C, 367; Hutchinson Grocer Co. v. Brand, 79 Kan. 340, 99 P. 592. The decree conforms to the findings in its distribution of relief. It adjudges the complainant to be entitled to exoneration but not to specific performance. The proceeds of the warrant are to be placed in a bank to be chose by the contractor, the deposit to be 'designated as a special trust fund for the payment of bills for labor and material used on the United States Veterans Hospital in Batavia, New York.' No provision is made that the surety, or indeed any one other than the contractor, shall have any control thereof.

From that decree the contractor appealed to the Circuit Court of Appeals for the Eighth Circuit. There was no cross-appeal by the surety. The Court of Appeals states in its opinion, 'We are in grave doubt whether exoneration can properly be granted.' Preferring by reason of that doubt to put its decision on some other ground, it concludes that there should be specific performance of the supplementary agreement. It concedes that the surety is in default for failing to live up to the agreement strictly, but it finds that the default was not unconscionable or fraudulent, and that a court of equity in its discretion may overlook an unsubstantial wrong. Recognizing the necessity of modifying the decree if exoneration is to be exchanged for specific performance, the opinion states that 'an injunction against using the moneys except as agreed upon, and an order to place said moneys when received in the joint account and disburse the same in payment of just claims for labor or materials, would meet the requirements and rights of plaintiff and would not be impossible of performance' and that 'a decree alone such lines should be granted by the trial court.' 84 F.(2d) 522, 526. Accordingly, the...

To continue reading

Request your trial
159 cases
  • Liddell v. State of Mo.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • March 5, 1984
    ...either to enlarge their own rights, or to lessen the rights of their adversary. See Morley Construction Co. v. Maryland Casualty Co., 300 U.S. 185, 190-191, 57 S.Ct. 325, 327-328, 81 L.Ed. 593 (1937); United States v. American Railway Express Co., 265 U.S. 425, 435, 44 S.Ct. 560, 563, 68 L.......
  • Maher v. City of New Orleans
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • July 31, 1975
    ...in order to "urge in support of a decree any matter appearing in the record . . .." Morley Construction Co. v. Maryland Casualty Co., 300 U.S. 185, 57 S.Ct. 325, 81 L.Ed. 593 (1937), quoting United States v. American Railway Express Co., 265 U.S. 425, 44 S.Ct. 560, 68 L.Ed. 1087 (1924); SEC......
  • Scott v. University of Delaware
    • United States
    • U.S. Court of Appeals — Third Circuit
    • June 6, 1979
    ...upon for purposes of complying with the numerosity requirement of subdivision (a)(1).1 Morley Construction Co. v. Maryland Casualty Co., 300 U.S. 185, 191, 57 S.Ct. 325, 327, 328, 81 L.Ed. 593 (1937) (Quoting United States v. American Ry. Express Co., 265 U.S. 425, 435, 44 S.Ct. 560, 68 L.E......
  • Colonial Refrigerated Transportation, Inc. v. Mitchell
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • December 12, 1968
    ...820, 78 N.E.2d 612. 26 3 Wigmore, Evidence §§ 1017-1046. 27 Rule 61, Fed.Rules Civ.Pro. See, e. g., Morley Const. Co. v. Maryland Cas. Co., 1937, 300 U.S. 185, 57 S.Ct. 325, 81 L.Ed. 593; Ex parte Genecov, 1945, 143 Tex. 476, 186 S.W.2d 225, 160 A.L.R. 1099, cert. denied, Genecov v. State o......
  • Request a trial to view additional results
2 books & journal articles
  • The Construction Industry in the U.S. Supreme Court:Part 2, Beyond Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-3, July 2021
    • July 1, 2021
    ...States, 231 U.S. 474 (1913). 20. Hardaway v. Nat’l Sur. Co., 211 U.S. 552 (1909). 21. See, e.g. , Morley Constr. Co. v. Md. Cas. Co., 300 U.S. 185, 193 (1937) (addressing the surety’s right of exoneration); Henning-sen v. U.S. Fid. & Guar. Co., 208 U.S. 404 (1908) (recognizing the surety’s ......
  • Jurisdiction and the federal rules: why the time has come to reform finality by inequitable deadlines.
    • United States
    • University of Pennsylvania Law Review Vol. 157 No. 1, November 2008
    • November 1, 2008
    ...4(b). Neither mentions an extension for cross-appeals. (141) Greenlaw, 128 S. Ct. at 2564 (quoting Morley Constr. Co. v. Md. Casualty Co., 300 U.S. 185, 191 (142) Id. at 2565. (143) Id. at 2569. (144) Id. at 2565. (145) Id. at 2565-66, 2568-69. (146) The history of using "jurisdictional" to......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT