Morley Const. Co. v. Maryland Casualty Co.
Decision Date | 20 July 1936 |
Docket Number | No. 10477.,10477. |
Citation | 84 F.2d 522 |
Parties | MORLEY CONST. CO. et al. v. MARYLAND CASUALTY CO. |
Court | U.S. Court of Appeals — Eighth Circuit |
Martin J. O'Donnell, of Kansas City, Mo. (William Buchholz, of Kansas City, Mo., on the brief), for appellants.
Spencer F. Harris, of Kansas City, Mo. (Paul G. Koontz, of Kansas City, Mo., on the brief), for appellee.
Before GARDNER, SANBORN, and BOOTH, Circuit Judges.
This is a suit in equity brought by the Maryland Casualty Company against the Morley Construction Company and the Merchants Bank of Kansas City, Mo. Diverse citizenship is alleged and admitted.
It appears that plaintiff executed a surety bond for defendant Morley Construction Company in connection with a construction contract entered into between said Morley Construction Company and the United States. The bond, dated on or about July 28, 1932, was in the standard form of performance bonds.
The term "defendant" hereinafter used means the Morley Construction Company.
Plaintiff seeks by its complaint the following relief: (1) Exoneration by the defendant from payment of any bills for labor and materials furnished under said construction contract; (2) subrogation to defendant's claim against the United States by reason of certain payments alleged to have been made by plaintiff to creditors of the Morley Construction Company; (3) specific performance of a certain contract (Exhibit A) entered into between plaintiff and said defendant subsequent to the making of said bond.
As to Specific Performance of Exhibit A.
It appears that in carrying out the construction contract, the defendant, Morley Construction Company, became involved in financial difficulties, and an agreement (Exhibit A, set out in the margin1) was entered into between it and the Maryland Casualty Company, whereby the Casualty Company agreed to advance to the Construction Company the sum of $5,000 to be placed in a joint account. The Casualty Company also agreed: "Fifth: The Maryland Casualty Company further agrees to place on deposit in said account to the credit of the Morley Construction Company moneys to pay off plasterers' claims which have not been paid by D. Giamberardino & Sons who employed said plasterers and also sufficient money to complete the Giamberardino plastering contract if the amount to be paid to complete said contract is deemed reasonable and satisfactory."
The Construction Company also agreed to place a certain amount in a joint account.
The Casualty Company did not fulfill all of the covenants assumed by it in the agreement. On cross-examination, the witness Herbert F. Morley, president of the Morley Construction Company, testified as follows:
The witness Kelly, an attorney employed in the office of the Casualty Company at Buffalo, N. Y., testified as follows:
The court found as to this matter as follows:
As conclusions of law the court found: "Plaintiff is not entitled to a decree of specific performance of the agreement referred to in finding of fact No. 2. * * *"
We cannot agree with this conclusion of the trial court.
Acquiescence by defendant in a modification of the contract, Exhibit A, which modification was thereafter carried out, deprives the conduct of the plaintiff of any taint of inequity. Becker v. Becker, 250 Ill. 117, 95 N.E. 70, Ann.Cas.1912B, 275; Langley v. Devlin, 95 Wash. 171, 163 P. 395, 4 A.L.R. 32.
Such acquiescence, we think, was shown by the evidence in the case at bar.
We do not wish it to be thought that we are departing from the well-established rules regarding the granting of the remedy of specific performance. Such is not our intention.
This court, in Shubert v. Woodward, 167 F. 47, at page 54, has said:
In Town of Glenwood Springs v. Glenwood Light & Water Co., 202 F. 678, at page 684, L.R.A.1915C, 438, this court lays down the rule: "And courts of equity will not ordinarily compel the specific performance of a contract, either by decree or by an injunction against its violation, at the suit of a party who is guilty of a substantial breach of it." (Italics supplied.)
In Michigan Pipe Co. v. Fremont Ditch, Pipe Line & Reservoir Co. (C.C.A.8) 111 F. 284, 287, the court states the rule as follows: (Italics supplied.)
We think relief can be granted in the case at bar without doing violence to the foregoing rules.
The breach of the contract (Exhibit A) on the part of plaintiff, which defendant alleges precludes plaintiff from obtaining the remedy of specific performance, is the failure by plaintiff Casualty Company to deposit in the joint account agreed upon in said contract, Exhibit A, sufficient moneys to pay for completing the plastering contract. There was deposited in the joint account by plaintiff the sum of $10,700, but this was not sufficient to pay in full the amount due or to become due for plastering.
Defendant makes these allegations in its answer:
To continue reading
Request your trial- Haygood v. Unity Health Sys.
-
Travis Equipment Co. v. D & L Construction Co. & Associates
...rationale has been recognized, applied and followed by the Eighth Circuit numerous times. See for example, Morley Const. Co. v. Maryland Casualty Co., 8th Cir. 1936, 84 F.2d 522, 527; National Surety Corp. v. Wunderlich, 8th Cir. 1940, 111 F.2d 622, 625; and Kansas City, Missouri v. Federal......
-
Fireman's Fund Insurance Co. v. SEK Construction Co., 296-69
...theory is found, Re Anderson Berry 1928 1 Ch. (Eng.) 290, 15 BRC 928. 4 The complete facts are set out in Morley Const. Co. v. Maryland Cas. Co., 84 F.2d 522 (8th Cir. 1936). 5 Butler Paper Co. v. Business Forms, Ltd. Maneke-Kinzie Printing Co., 424 F.2d 247 (10th Cir. 1970); Knauff v. Utah......
-
United States v. Reiten, Civ. No. A-13071.
...McCord, 233 U.S. 157, 162, 34 S.Ct. 550, 58 L.Ed. 893; Stitzer v. United States, 3 Cir., 182 F. 513, 516; Morley Construction Co. v. Maryland Casualty Co., 8 Cir., 84 F.2d 522, 527. The same principle was applied to the limitation of one year after complete performance of the contract and f......