Murphy v. City of Lincoln

Decision Date22 April 1994
Docket NumberNo. S-92-949,S-92-949
Citation515 N.W.2d 413,245 Neb. 707
PartiesMark MURPHY, Appellant, v. CITY OF LINCOLN, Nebraska, Appellee.
CourtNebraska Supreme Court

Syllabus by the Court

1. Contracts. In construing contracts, a court as a matter of law must first determine whether the contract is ambiguous.

2. Judgments: Appeal and Error. Regarding a question of law, a reviewing court has an obligation to reach its conclusion independent from the conclusion reached by the court below.

3. Contracts: Words and Phrases. An instrument is ambiguous if a word, phrase, or provision in the instrument has, or is susceptible of, at least two reasonable but conflicting interpretations or meanings.

4. Contracts. A determination as to whether ambiguity exists in a contract is to

be made on an objective basis, not by the subjective contentions of the parties; thus, the fact that the parties to a document have or suggest opposing interpretations of the document does not necessarily, or by itself, compel the conclusion that the document is ambiguous.

5. Contracts. The terms of a contract are to be accorded their plain and ordinary meaning as ordinary, average, or reasonable persons would understand them.

6. Contracts. A contract written in clear and unambiguous language is not subject to interpretation or construction and must be enforced according to its terms.

Jane E. Burke, Lincoln, for appellant.

William F. Austin, Lincoln City Atty., and Don W. Taute, Lincoln, for appellee.

HASTINGS, C.J., and BOSLAUGH, WHITE, CAPORALE, FAHRNBRUCH, LANPHIER, and WRIGHT, JJ.

CAPORALE, Justice.

In this contract action, the plaintiff-appellant, Mark Murphy, seeks to recover overtime pay from the defendant-appellee, City of Lincoln, Nebraska, under the terms of the applicable collective bargaining agreement. The district court affirmed the denial of the grievance Murphy filed with the City of Lincoln Personnel Board. He then appealed to the Nebraska Court of Appeals, asserting that the district court erred in, among other things, determining that the agreement was ambiguous and thus was subject to interpretation. We removed the matter to this court in order to regulate the caseloads of the appellate courts. Murphy's aforesaid claim of error having merit, we reverse the judgment of the district court and remand the cause with direction.

Murphy is a full-time regular employee of the city's emergency communications center. So far as is relevant to our purposes, there are two types of regular city employees under the agreement: exempt and nonexempt. Exempt employees do not receive overtime pay. Nonexempt employees who work in excess of 40 hours per workweek, which extends from Thursday through the following Wednesday, do receive overtime pay and are further divided into shift and nonshift workers. A nonshift employee typically works 8 hours per day on an 8 a.m. to 5 p.m. schedule and does not normally work on Saturdays, Sundays, and specified legal, that is, paid, holidays. In contrast, a shift employee's hours are scheduled in 8-hour shifts, including Saturdays, Sundays, and paid holidays, so that departments which are required to operate around the clock each and every day may be properly staffed. Murphy is a nonexempt shift employee who, during the week in question, worked 40 hours consisting of five 8-hour days, Thursday, May 23, through Monday, May 27, 1991. Being Memorial Day, Monday was a paid holiday under the agreement.

In his grievance, Murphy asserted that under the agreement, he was entitled to overtime pay for the 8 hours he worked on the Memorial Day holiday.

The pertinent provision of the agreement in question reads:

Work performed by non-exempt employees in excess of forty (40) hours per work week (Thursday through the following Wednesday) shall be compensated at the rate of one and one-half (1 1/2) times the hourly rate of the employee. Overtime shall be paid only for those hours actually worked. Any payment for time not worked (i.e., paid leave time) shall not count toward the forty (40) hour work week for overtime purposes, except legal holiday pay, which will count toward hours worked in determining overtime.

Murphy contends that the foregoing language is "clear and precise," brief for appellant at 21, and applies to all nonexempt employees, shift and nonshift alike. On the other hand, the city argues that the provision in question is ambiguous, urging that the language was intended to apply only to nonshift workers.

In construing contracts, a court as a matter of law must first determine whether the contract is ambiguous. Plambeck v. Union Pacific RR. Co., 244 Neb. 780, 509 N.W.2d 17 (1993); Metropolitan Life Ins. Co v. Beaty, 242 Neb. 169, 493 N.W.2d 627 (1993); Professional Serv. Indus. v. J.P. Construction, 241 Neb. 862, 491 N.W.2d 351 (1992); Husen v. Husen, 241 Neb. 10, 487 N.W.2d 269 (1992). Regarding a question of law, a reviewing court has an obligation to reach its conclusion independent from the conclusion reached by the court below. Plambeck, supra; Gables CVF v. Bahr, Vermeer & Haecker Architect, 244 Neb. 346, 506 N.W.2d 706 (1993); Home Fed. Sav. & Loan v. McDermott & Miller, 243 Neb. 136, 497 N.W.2d 678 (1993); Metropolitan Life Ins. Co., supra; Professional Serv. Indus., supra; Husen, supra.

An instrument is ambiguous if a word, phrase, or provision in the instrument has, or is susceptible of, at least two reasonable but conflicting interpretations or meanings. Plambeck, supra; Metropolitan Life Ins. Co., supra; Husen, supra. See, Lone Oak Farm Corp. v. Riverside Fertilizer, 229 Neb. 548, 428 N.W.2d 175 (1988) (contract is ambiguous when, considered as a whole, it is capable of being understood in more senses than one); National Farmers Union Serv. Corp. v. Edwards, 220 Neb. 231, 369 N.W.2d 76 (1985) (document is ambiguous if, after application of pertinent rules for construction, there is uncertainty concerning which of two or more reasonable meanings represents intention of parties). A determination as to whether ambiguity exists in a contract is to be made on an objective basis, not by the subjective contentions of the parties; thus, the fact that the parties to a document have or suggest opposing interpretations of the document does not necessarily, or by itself, compel the conclusion that the document is ambiguous. Metropolitan Life Ins. Co., supra; Bedrosky v. Hiner, 230 Neb. 200, 430 N.W.2d 535 (1988); Lueder Constr. Co. v. Lincoln Electric Sys., 228 Neb. 707, 424 N.W.2d 126 (1988). We have said, in the context of a decree:

[T]he fact is that neither what the parties thought the judge meant nor what the judge thought he or she meant, after time...

To continue reading

Request your trial
15 cases
  • Boss v. Fillmore County School Dist. No. 19
    • United States
    • Nebraska Court of Appeals
    • May 14, 1996
    ...be accorded their plain and ordinary meaning as ordinary, average, or reasonable persons would understand them. Murphy v. City of Lincoln, 245 Neb. 707, 515 N.W.2d 413 (1994); Fritsch v. Hilton Land & Cattle Co., 245 Neb. 469, 513 N.W.2d 534 We are required on appeal to determine whether Bo......
  • Union Ins. Co. v. Land and Sky, Inc.
    • United States
    • Nebraska Supreme Court
    • March 31, 1995
    ...of that of the trial court in a judgment under review. New Light Co. v. Wells Fargo Alarm Servs., supra; Murphy v. City of Lincoln, 245 Neb. 707, 515 N.W.2d 413 (1994). IV. ANALYSIS 1. DUTY TO DEFEND Although an insurance policy may impose an obligation to defend and thereby impose a duty g......
  • Johnson Lakes Development, Inc. v. Central Nebraska Public Power & Irrigation Dist.
    • United States
    • Nebraska Supreme Court
    • April 10, 1998
    ...parties suggesting opposing meanings of the disputed language. Daehnke v. Nebraska Dept. of Soc. Servs., supra; Murphy v. City of Lincoln, 245 Neb. 707, 515 N.W.2d 413 (1994). The terms of a contract are to be accorded their plain and ordinary meaning as ordinary, average, or reasonable per......
  • Bachman v. Easy Parking of America, Inc.
    • United States
    • Nebraska Supreme Court
    • April 24, 1997
    ...251 Neb. 298, 557 N.W.2d 17 (1996); Rains v. Becton, Dickinson & Co., 246 Neb. 746, 523 N.W.2d 506 (1994); Murphy v. City of Lincoln, 245 Neb. 707, 515 N.W.2d 413 (1994). When viewed as a whole, it is clear that the parties intended to lease a surface parking lot, not a building. This inten......
  • Request a trial to view additional results