MW Builders, Inc. v. United States, 13-1023 C

Decision Date18 October 2017
Docket NumberNo. 13-1023 C,13-1023 C
PartiesMW BUILDERS, INC. f/n/a MW BUILDERS OF TEXAS, INC., Plaintiff, v. THE UNITED STATES, Defendant.
CourtU.S. Claims Court

Anti-Deficiency Act, 31 U.S.C. § 1350;

Breach of Contract;

Contract Disputes Act, 41 U.S.C. §§ 7101-7109;

Counterclaims, 28 U.S.C. § 2508;

False Claims Act, 31 U.S.C. §§ 3729-3733;

Federal Acquisition Regulation, 48 C.F.R. §§ 52.211-12 (Liquidated Damages), 52.242-14 (Suspension of Work), 52.249-10 (Contract Default);

Good Faith and Fair Dealing;

Special Plea In Fraud, 28 U.S.C. § 2514;

Tucker Act Jurisdiction, 28 U.S.C. § 1491;

Unreasonable Delay;

Waiver.

Paul Harvey Sanderford, Sanderford and Carroll, P.C., Temple, Texas, Counsel for Plaintiff.

Alexander Orlando Canizares, United States Department of Justice, Washington, D.C., Counsel for the Government.

POST-TRIAL MEMORANDUM OPINION AND FINAL ORDER1

This case concerns the United States Army Corps of Engineers ("Army Corps") attempt to shift its contractual responsibility to make arrangements for permanent electrical utility services that MW Builders, Inc. ("MW Builders") needed to build an Army Reserve Center in Sloan, Nevada. This imposed unnecessary construction delay and costs on MW Builders that the Contracting Officer ("CO") refused to pay. When MW Builders filed a Complaint in the United States Court of Federal Claims, the Government alleged that the contractor's claim was fraudulent.

As discussed herein, the court has determined that the Army Corps breached a September 10, 2010 Contract with MW Builders and violated the duty of good faith and fair dealing for which $418,961.90 is awarded, as compensable delay damages, together with statutoryinterest. The Government's counterclaims for fraud are dismissed, but the Government's affirmative defense of waiver concerning one of MW Builders' subcontractors' alleged pass-through claim is granted.

To facilitate review of this Post-Trial Memorandum Opinion And Final Order, the court has provided the following outline.

I. RELEVANT FACTUAL BACKGROUND.

A. In 2008, The United States Army Corps Of Engineers Began Designing An Army Reserve Center To Be Built In Sloan, Nevada.
B. On June 11, 2010, The United States Army Corps Of Engineers Issued Solicitation No. W912QR-09-R-0104 Requesting Proposals For A Firm, Fixed-Price Contract To Build The Army Reserve Center In Sloan, Nevada.
D. On December 6, 2010, MW Builders, Inc. Entered Into A Subcontract With Bergelectric Corporation To Provide An Electrical System.
E. In 2011, MW Builders, Inc. Executed A Third Party Authorization Form And Design Approval Agreement With NV Energy.

F. In March 2012, MW Builders, Inc. And The United States Army Corps Of Engineers Had A Dispute Over The Execution Of A Line Extension Agreement With NV Energy.

G. On April 6, 2012, MW Builders, Inc. Notified The United States Army Corps Of Engineers That The Construction Schedule Would Be Delayed, Because The Line Extension Agreement With NV Energy Was Not Executed.

H. On April 19, 2012, The United States Army Corps Of Engineers Began To Negotiate A Line Extension Agreement With NV Energy.

I. On July 12, 2012, The United States Army Corps Of Engineers Signed A Line Extension Agreement With NV Energy.

J. On December 27, 2012, MW Builders, Inc. Submitted A Certified Claim To The Contracting Officer For Costs Incurred As A Result Of The United States Army Corps Of Engineers' Failure To Timely Execute A Line Extension Agreement With NV Energy.

K. On June 10, 2013, The Contracting Officer Issued A Final Decision Denying MW Builders, Inc.'s Monetary Claim, But Granting A Non-Compensable Time Extension Of 146 Days For MW Builders, Inc. To Complete Construction Of The Army Reserve Center In Sloan, Nevada.

L. On December 13, 2013, The Completed Army Reserve Center in Sloan, Nevada Was Accepted By The United States Army Corps Of Engineers.

II. PROCEDURAL HISTORY.
III. DISCUSSION.
A. Subject Matter Jurisdiction.
B. Standing.
C. Plaintiff's Claims Against The Government.
1. The September 10, 2010 Contract Required The United States Army Corps Of Engineers To Sign The Line Extension Agreement With NV Energy.
a. Plaintiff's Argument.
b. The Government's Response.
c. The Court's Resolution.
i. The September 10, 2010 Contract Contains A Latent Ambiguity Regarding Which Party Was Responsible For Signing The Line Extension Agreement With NV Energy.
ii. Extrinsic Evidence Of Intent Demonstrates That The United States Army Corps Of Engineers Was Responsible For Signing The Line Extension Agreement With NV Energy.
2. The United States Army Corps Of Engineers Violated The Duty Of Good Faith And Fair Dealing Causing An Unreasonable Delay To The Project.
a. Plaintiff's Argument.
b. The Government's Response.
c. Plaintiff's Reply.
d. The Government's Sur-Reply.
e. The Court's Resolution.
i. The United States Army Corps Of Engineers Violated The Duty Of Good Faith And Fair Dealing.
ii. The United States Army Corps Of Engineers' Conduct Caused An Unreasonable Delay.
D. The Government's Affirmative Defense And Counterclaims.
1. The Government's Affirmative Defense Of Waiver.
a. The Government's Argument.
b. Plaintiff's Response.
c. The Court's Resolution.
2. The Government's Counterclaims.
a. Subject Matter Jurisdiction.
b. Standing.
c. The Government's Argument.
d. Plaintiff's Response.
e. The Government's Reply.
f. The Court's Resolution.
i. Regarding The Anti-Fraud Provision Of The Contract Disputes Act.ii. Regarding The Special Plea In Fraud.
iii. Regarding The False Claims Act.
IV. CALCULATION OF DELAY CAUSED BY THE UNITED STATES ARMY CORPS OF ENGINEERS' BREACH AND DAMAGES.
A. The Parties' Scheduling Experts.
1. Plaintiff's Scheduling Experts.
a. Mr. Neil W. Miltonberger.
b. Mr. Denny Lee.
2. The Government's Scheduling Expert, Mr. Stephen Weathers.
3. The Scheduling Experts' Critiques.
B. Plaintiff's Damages Claim.
1. Plaintiff's Claimed Amount.
2. The Government's Response.
3. The Court's Determination.
a. Regarding The Amount Of Delay.
b. Regarding The Daily Jobsite Overhead Rate.
c. Regarding The Materials And Equipment Costs.
d. Regarding Home Office Overhead.
e. Regarding Profit.
f. Regarding The Bond Fee.
g. Calculation Of Damages.
V. CONCLUSION.

* * *

I. RELEVANT FACTUAL BACKGROUND.2

A. In 2008, The United States Army Corps Of Engineers Began Designing An Army Reserve Center To Be Built In Sloan, Nevada.

In 2008, the United States Army Corps of Engineers (the "Army Corps") began designing an Army Reserve Center in Sloan, Nevada (the "Project") for use by the Army Reserve 63rdRegional Support Command ("63rd RSC"). TR at 16-17 (Probst); TR at 971 (Miller). During the "Design Phase," the Army Corps retained Mason & Hanger, an architecture and engineering firm, to design and prepare construction specifications. Jt. Stip. ¶ 8. Mr. Jonathan Miller also served as Mason & Hanger's Project Manager. TR at 970-71 (Miller). Several Army Corps employees also were involved:

Hans Probst, the Branch Chief of the Instruction Division of the Army Reserve Program Louisville District, served as the Project Manager, TR 15 (Probst);
Robert Caskie, an employee from the Army Corps' Los Angeles District Office, served as the Geographical Administrative Contracting Officer, TR 370 (Caskie);
Johnny Ringstaff, an employee from the Army Corps' Louisville District Office, served as an Administrative Contracting Officer, TR at 1118 (Ringstaff); and
Tara O'Leary, an Army Corps Design Project Engineer, managed the Army Corps' design contract with Mason & Hanger, TR at 1144-45 (O'Leary).

The Sloan, Nevada site selected by the Army Corps did not have any existing electric utilities. Jt. Stip. ¶ 5. Therefore, the local electrical utility, Nevada Power Company, doing business as NV Energy ("NV Energy"), was required to design a new utility line that would connect the Project with existing power lines. PX 4 at 2; see also JX 2 (4/28/09 Meeting Minutes reporting that "[u]tility coordination is critical").

Mason & Hanger was responsible for contacting NV Energy about utility design and, on May 6, 2009, NV Energy provided Mason & Hanger with a draft "Design Initiation Agreement," together with a memorandum that listed all the steps necessary for NV Energy to provide electrical power to the Project. DX 6 at 4. NV Energy's May 6, 2009 draft Design Initiation Agreement provided that, "[p]rior to going to construction, [the applicant must] sign one or more of the following agreements: Line Extension Agreement (LEA); Large Profit Service Agreement (LPS Agreement); Contribution In Aid of Construction Agreement (CIAC Agreement); Non-Refundable Construction Agreement (NRCA)." DX 6 at 5.

On May 14, 2009, a Mason & Hanger employee forwarded the Design Initiation Agreement and attached memorandum to Mark Cutler, an employee of the 63rd RSC. DX 6 at 2. On May 15, 2009, Mr. Cutler forwarded the agreement to Ms. O'Leary, the Army Corps Design Project Engineer for the Project, and stated that the Design Initiation Agreement should "be signed by the [Army] Corps," because it "has a look on it that whoever signs it should really have a warrant or be a contracting officer." DX 6 at 1. But, Ms. O'Leary declined to authorize a representative of the Army Corps to sign the Design Initiation Agreement. DX 6 at 1. Consequently, neither the 63rd RSC, Mason & Hanger, nor the Army Corps signed the Design Initiation Agreement that NV Energy required before it would commence utility work on the Project. JX 4. Instead, Ms. O'Leary suggested that the Army Corps "place that requirement on the construction contractor." DX 6 at 1.

On July 15, 2009, the 63rd RSC, the Army Corps, and Mason & Hanger decided that the solicitation should include a requirement that the winning bidder must sign the Design Initiation Agreement with NV Energy. DX 8 at 1; see also TR at 978 (Miller). The Army Corps and Mason & Hanger, however, did not include any express...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT