Nan Sing Marine Co., Ltd. v. U.S., 86-1453

Decision Date17 February 1987
Docket NumberNo. 86-1453,86-1453
Citation811 F.2d 1495
Parties, 33 Cont.Cas.Fed. (CCH) 75,068 NAN SING MARINE COMPANY, LTD., Appellant, v. The UNITED STATES, Appellee. Appeal
CourtU.S. Court of Appeals — Federal Circuit

Lesli Yu, Kerns and Klimek, P.C., of Washington, D.C., argued for appellant. Christopher M. Kerns and Robert H. Rumizen, Kerns and Klimek, P.C., of Washington, D.C., were on the brief for appellant. Robert A. Klimek, Kerns and Klimek, of Washington, D.C., counsel of record for appellant.

Ronald Schechter, Commercial Litigation Branch, Dept. of Justice, of Washington, D.C., argued for appellee. With him on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director and Robert A. Reutershan, Asst. Director. Stephen J. Narkin, Agency for Intern. Development, of counsel.

Before DAVIS, Circuit Judge, BENNETT, Senior Circuit Judge, and SMITH, Circuit Judge.

DAVIS, Circuit Judge.

Nan Sing Marine Company, Ltd. (Nan Sing) appeals from a decision of the Armed Services Board of Contract Appeals (ASBCA or Board) dismissing appellant's breach of contract claim (before trial) because it had been extinguished by passage of the applicable statute of limitations before the effective date of the Contract Disputes Act of 1978. Nan Sing Marine Company, Ltd., 86-2 BCA p 19,006 (April 29, 1986). We agree and affirm. 1

I.

The Board found the following to be the pertinent facts (see 86-2 BCA at 95,988-89) and they are not now contested. In December 1974 (during the Vietnam hostilities), the United States Agency for International Development (USAID) entered into a charter party with appellant Nan Sing to carry rice in appellant's ship to Phnom Penh, Cambodia, from Saigon, Vietnam. In January 1975 the ship (the Wah On) twice voyaged up the Mekong River to Phnom Penh but on its second trip 2 was attacked from the banks by enemy rocket and machine gun fire; the vessel was damaged and immobilized, and the crew had to abandon ship. As a result, the owner, Nan Sing, lost the vessel. Nan Sing's president traveled in April 1975 to Saigon to discuss the claim for loss of the vessel; while he was there Saigon fell to the Communist forces (on April 30, 1975) and he was detained until May 18, 1977. Shortly after Saigon fell, a formal claim for loss of the vessel was filed with USAID in Washington; the claim was denied by that agency. In May 1977 the claim was resubmitted to USAID after the release of Nan Sing's president from detention in Vietnam; it was again denied. Appellant then unsuccessfully sought assistance from the United States Ambassador in Taiwan and obtained legal counsel in this country. In April 1981 Nan Sing submitted to USAID a Petition for Extraordinary Contractual Relief under Executive Order No. 11223, asking $5,519,038; appellant was granted only some $11,500 on its claim. 3 In March 1982 Nan Sing asked the ASBCA to consider its claim. The Board first dismissed the claim on the ground that it had not been properly certified. Nan Sing then submitted a certified claim to the contracting officer. When no contracting officer's decision was issued, appellant treated its claim as having been denied and again filed an appeal with the ASBCA. The Government moved to dismiss. It is the Board's grant of that motion that is now before us.

The ASBCA held that Nan Sing's claim was a breach of contract claim and a maritime claim which (a) accrued in January 1975, (b) could and should have been brought under the Suits in Admiralty Act but was not, (c) was subject to that Act's two-year statute of limitations which was not tolled, and (d) was wholly extinguished in January 1977, well before the Contract Disputes Act became effective on March 1, 1979. The Board also ruled that the claim was not revived or restored by the Contract Disputes Act. 4

II.

Each element of the portion of the Board's decision now on appeal was correct.

1. The Board rightly held that Nan Sing's claim does not arise "under the contract" but was for breach of the charter party. 86-2 BCA at 95,989. (That seems to have been the common agreement until this appeal.) That breach of contract claim plainly accrued when the vessel was captured and lost to Nan Sing in January 1975. See McMahon v. United States, 342 U.S. 25, 72 S.Ct. 17, 96 L.Ed. 26 (1951). At that time (pre-Contract Disputes Act) there was no requirement that administrative remedies for such breaches be exhausted before suit could be brought in court. Those who claimed that their Government contracts had been breached could sue immediately in the proper court.

2. Though appellant disputes the point, we have no doubt that the claim was a maritime one which could have been (and had to be) brought under the Suits in Admiralty Act, 46 U.S.C. Sec. 741, et seq., rather than the Tucker Act. The former statute applies to cases involving merchant-type vessels owned, possessed, or operated by the United States (46 U.S.C. Secs. 741, 742) and is exclusive where applicable. 46 U.S.C. Sec. 745. Charter parties of such vessels are maritime or marine contracts (Victory Transport Inc. v. Comisaria General, 336 F.2d 354, 364 (2d Cir.1964)), and suits against the Government on such maritime claims must be brought under the Suits in Admiralty Act. New Orleans Stevedoring Co. v. United States, 439 F.2d 89, 91 (5th Cir.1971).

3. The Suits in Admiralty Act embodies a two-year statute of limitations. 46 U.S.C. Sec. 745. 5 That provision is jurisdictional, unlike most limitations legislation applicable to private parties. Todd v. United States, 292 F.2d 841, 844, 155 Ct.Cl. 87 (1961). Nor does the statute contain any provision for tolling limitations. There is a split of authority as to whether tolling of this statutory limitations period may ever be recognized, but even if we assume that possibility arguendo we, like the Board, see nothing in the circumstances presented here to warrant tolling. Nan Sing's president was not under a legal disability when the claim accrued in January 1975 (see De Arnaud v. United States, 151 U.S. 483, 496, 14 S.Ct. 374, 379, 38 L.Ed. 244 (1894)), and, in any event, the claimant is a corporation, not an individual. Nothing prevented the corporation from bringing suit at any time after the claim accrued; in fact, Nan Sing made a demand on USAID for payment while its president was detained in Vietnam. Similarly, there was no tolling by appellant's pursuit of permissive administrative remedies. Benjamin v. United States, 348 F.2d 502, 512, 172 Ct.Cl. 118 (1965). 6

4. The two-year limitation provision of the Suits in Admiralty Act, like that of the Tucker Act, fully extinguishes the claim; the claim is not simply...

To continue reading

Request your trial
3 cases
  • Southwest Marine of San Francisco, Inc. v. U.S., 89-1563
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 12 de fevereiro de 1990
    ...(E.D.La.1987); General Dynamics Corp., ASBCA No. 33633, 87-1 BCA Sec. 19,607 (Feb. 2, 1987). See generally Nan Sing Marine Company, Ltd. v. United States, 811 F.2d 1495 (Fed.Cir.1987), wherein this court held that a claim arising in admiralty, on which the Suits in Admiralty Act's two-year ......
  • Dalton v. Southwest Marine, Inc., 97-1240
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 8 de agosto de 1997
    ...the Contract Disputes Act excludes maritime contracts from the purview of the Contract Disputes Act. See Nan Sing Marine Co. v. United States, 811 F.2d 1495, 1498 n. 7 (Fed.Cir.1987) (the Contract Disputes Act authorizes an administrative determination of a claim involving the breach of a m......
  • Sea-Land Service, Inc. v. US
    • United States
    • U.S. District Court — District of New Jersey
    • 13 de julho de 1988
    ...existed, this Court finds that as a matter of law it would have been unenforceable. See, e.g., Nan Sing Marine Co., Ltd. v. United States, 811 F.2d 1495, 1497-98 (Fed.Cir. 1987) (noting that there exists a split of authority as to whether two-year statute of limitations may be tolled in lig......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT