Nofelco Realty Corp. v. United States

Decision Date11 September 1981
Docket NumberNo. 81 Civ. 0052 (GLG).,81 Civ. 0052 (GLG).
Citation521 F. Supp. 458
PartiesNOFELCO REALTY CORP., Plaintiff, v. UNITED STATES of America: Clifford L. Alexander, Jr., Secretary, Department of the Army; Lt. General John W. Morris, Chief of Engineers, Army Corps of Engineers; Army Corps of Engineers: Col. W. M. Smith, Jr., District Engineer, New York District, Army Corps of Engineers; Maj. Gen. J. Johnson, North Atlantic Division Engineer, Defendants.
CourtU.S. District Court — Southern District of New York

Denham & Vaneria, New York City, for plaintiff; Robert E. Denham, of counsel.

John S. Martin, Jr., U. S. Atty. for the S. D. New York, New York City, for defendants; Richard N. Papper, Asst. U. S. Atty., New York City, of counsel.

MEMORANDUM DECISION

GOETTEL, District Judge.

This action was brought by the plaintiff, Nofelco Realty Corp. ("Nofelco"), seeking judicial review of the action of the Secretary of the Army, through the Army Corps of Engineers ("Corps"), in denying the plaintiff's application for a permit to construct a bulkhead along the shoreline of its property. The action initially came before this Court on a motion for a preliminary injunction — a rather unusual posture for such a case.

Nofelco owns a piece of tidal property, 100 feet wide and 84 feet deep, in Queens, adjacent to Shellbank Basin, which is a waterway flowing into Jamaica Bay. When Nofelco originally bought the property in 1959, only a strip 10 feet deep was dry land. Nofelco gradually filled in the submerged area, and now the property is dry land to a depth of approximately 72 feet, with another 12 feet of embankment area. The northern 30 feet of the shoreline are occupied by a building owned by Nofelco extending out over the water on stilts.1

In August 1977, Nofelco applied to the Corps for a permit to build a sloping riprap bulkhead at the shore edge and to fill in the property landward of the bulkhead and also to erect vertical steel sheet pile bulkheading to secure the side boundary of the property at one corner of the shore edge. The Corps granted the permit in April 1978.

In October 1978, Nofelco applied for permission to run the steel sheet bulkhead, which would rise approximately 6 feet above the mean high water level, along the remaining shore edge of the property. The initial review of Nofelco's application was by the District Engineer of the Corps, who recommended in July 1979 that a permit be issued, despite the objections of the National Marine Fisheries Service and the Fish and Wildlife Service. The Division Engineer, superior to the District Engineer, rejected the recommendation and directed the District Engineer to deny the permit, which he did in May 1980, on the ground that the proposed bulkhead "would increase encroachment upon this heavily stressed waterway for an apparently non-water dependent activity" and was "not in the public interest." While rejecting Nofelco's proposal, the notification letter indicated that the Corps would be willing to issue a permit for a similar bulkhead 8.5 feet landward of the location proposed by Nofelco.2

Nofelco then retained an environmental consultant, who wrote to the Corps on behalf of the plaintiff. Nofelco subsequently requested an adjudicatory hearing, which was denied on the ground that the denial of the permit was the final administrative action, from which no administrative appeal was permitted. Consequently, Nofelco filed the instant action, seeking review of the administrative action and seeking a preliminary injunction against any action by the Corps to remove the parts of the steel bulkhead that were already constructed.

Nofelco asked for injunctive relief because the letter it received from the Corps had referred to allegedly unauthorized construction at the shore edge of its property, leading Nofelco to fear the institution of Corps action to require the removal of that construction. This Court denied the motion for a preliminary injunction in January 1981 on the ground that there was no immediate threat of irreparable harm, since no steps had yet been taken to require removal of the allegedly unauthorized construction. There has still been no enforcement action brought against Nofelco; consequently, there is still no need for a preliminary injunction, and the plaintiff's renewed application for it is denied.

Nofelco has also asked for a trial de novo on the merits, on the ground that the procedures by which the Corps denied Nofelco's October 1978 application violated due process and the Administrative Procedure Act ("APA"), 5 U.S.C. §§ 551 et seq. For the reasons set forth below, this Court has determined that the plaintiff is not entitled to a trial de novo, but rather that the final administrative action taken by the Corps should be reviewed on the basis of the administrative record.

Two statutes govern the permit program under which the plaintiff made its application — section 10 of the Rivers and Harbors Act of 1899, 33 U.S.C. § 403, and section 404 of the Federal Water Pollution Control Act, 33 U.S.C. § 1344 (as added in 1972 and amended in 1977). Issuing permits to build such structures as bulkheads in navigable waters of the United States has long been the responsibility of the Secretary of the Army and the Chief of Engineers. See 33 U.S.C. § 403; 33 C.F.R. § 320.2(b) (1980). The regulations governing the issuance of such permits are found in 33 C.F.R. §§ 325.1 et seq. (1980) and provide for, inter alia, public notice of the permit application, receipt of written comments from interested parties, an opportunity for the applicant to rebut all substantive adverse comments, a public hearing if the district engineer determines that one is needed or if one is requested,3 preparation of findings of fact by the district engineer, and written notification to the applicant of a denial and the reasons for it. The responsibility of issuing permits for dredged or fill material under section 1344 was also given to the Secretary of the Army and the Chief of Engineers. See 33 U.S.C. § 1344(a), (d); 33 C.F.R. § 320.2(g) (1980). The regulations governing the issuance of those permits are found in 33 C.F.R. §§ 325.1 et seq. (1980) and are essentially the same as those for section 403 permits. See 40 C.F.R. § 124.1(a) (1980).

The plaintiff has not alleged that the defendants failed to follow the Corps procedures outlined above. Instead, the plaintiff argues that those procedures are inadequate under the standards of the APA and under the due process standard. The plaintiff complains particularly about the failure of the Corps to conduct a formal adjudicatory hearing, as provided for in the APA for adjudications "required by statute to be determined on the record after opportunity for an agency hearing." 5 U.S.C. § 554(a).

The challenged Corps procedures, however, have been upheld, at least in cases involving permits under section 403 (the Rivers and Harbors Act permit provision). For example, the court in Taylor v. District Engineer, 567 F.2d 1332 (5th Cir. 1978), held that the Corps procedures are not governed by the standards of the APA for formal adjudicatory hearings, id. at 1336-37, and that the Corps procedures "easily satisfy the requirements of due process." Id. at 1338. Accord, Joseph G. Moretti, Inc. v. Hoffman, 526 F.2d 1311 (5th Cir. 1976). Moreover, it is clear from decisions in cases involving statutes other than the Rivers and Harbors Act that the APA does not require formal, trial-type hearings in all adjudications. See United States v. Independent Bulk Transport, Inc., 480 F.Supp. 474, 478-79 (S.D.N.Y.1979), and the cases cited therein.

Nevertheless, the plaintiff argues that a formal adjudicatory hearing was required in the instant case, because the permit program under which it applied is governed by section 1344 (the Federal Water Pollution Control Act permit provision) as well as by section 403, and because courts have held another section of the Federal Water Pollution Control Act to require formal adjudicatory hearings. The cases the plaintiff cites are Seacoast Anti-Pollution League v. Costle, 572 F.2d 872 (1st Cir.), cert. denied, 439 U.S. 824, 99 S.Ct. 94, 58 L.Ed.2d 117 (1978); Marathon Oil Co. v. Environmental Protection Agency, 564 F.2d 1253 (9th Cir. 1977); and United States Steel Corp. v. Train, 556 F.2d 822 (7th Cir. 1977), all of which concerned section 402 of the Federal Water Pollution Control Act, 33 U.S.C. § 1342, which established a national pollutant discharge elimination system.

The starting point for ascertaining whether a certain type of adjudication is "required by statute to be determined on the record after opportunity for an agency hearing" — and thus is governed by the procedural requirements of the APA for formal, trial-type hearings — is the statute that provides for the adjudication. See, e. g., Marathon Oil Co. v. Environmental Protection Agency, supra, 564 F.2d at 1262-63. As is noted above, here there are two statutes, section 403 and section 1344. Section 403 does not mention any type of hearing, but simply forbids, inter alia, the building of structures or filling or excavating in the navigable waters of the United States "unless the work has been recommended by the Chief of Engineers and authorized by the Secretary of the Army." Section 1344, on the other hand, states that permits for the discharge of dredged or fill material may be issued "after notice and opportunity for public hearings." Although this language does not specify what kind of hearing is contemplated and does not track the language of the APA, it is similar to the language of section 1342, which provides that the Administrator of the Environmental Protection Agency ("EPA") may issue permits for the discharge of pollutants, on certain conditions, "after opportunity for public hearing." And, as has been noted, courts have held that formal adjudicatory hearings are required for section 1342 permits. In so holding, however, those courts found the language of ...

To continue reading

Request your trial
8 cases
  • Environmental Encapsulating Corp. v. City of New York
    • United States
    • U.S. District Court — Southern District of New York
    • July 31, 1987
    ...v. Knepper, 801 F.2d 130, 142 (3d Cir.1986); Sucesion Suarez v. Gelabert, 701 F.2d 231 (1st Cir.1983); Nofelco Realty Corp. v. United States, 521 F.Supp. 458, 461-62 (S.D.N.Y.1981). Plaintiffs first contend that the City violated the due process clause by failing to provide adequate notice ......
  • Sierra Club v. U.S. Army Corps of Engineers
    • United States
    • U.S. Court of Appeals — Second Circuit
    • February 25, 1983
    ...an abuse of discretion, or otherwise not in accordance with law." 5 U.S.C. Sec. 706(2)(A) (1976); see Nofelco Realty Corp. v. United States, 521 F.Supp. 458, 462 (S.D.N.Y.1974); cf. Taylor v. District Engineer, 567 F.2d 1332, 1336 (5th Cir.1978). Where the Corps may rely on an EIS previousl......
  • Buttrey v. U.S.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • November 8, 1982
    ...of section 404 with a trial-type hearing requirement, and we decline to do so today. See, e.g., Nofelco Realty Corp. v. United States, 521 F.Supp. 458 (S.D.N.Y.1981) (also construing section 404 not to require trial-type hearings); cf. United States v. Independent Bulk Transport, Inc., 480 ......
  • City of West Chicago, Ill. v. U.S. Nuclear Regulatory Com'n
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • March 1, 1983
    ...hearing provisions of the APA. United States Lines v. FMC, 584 F.2d 519, 536 (D.C.Cir.1978); Nofelco Realty Corp. v. United States, 521 F.Supp. 458, 461-462 (S.D.N.Y.1981); see also United States v. Florida East Coast Ry., 410 U.S. 224, 234-238, 93 S.Ct. 810, 815-18, 35 L.Ed.2d 223; United ......
  • Request a trial to view additional results
5 books & journal articles
  • Beyond Chevron's Domain: Agency Interpretations of Statutory Procedural Provisions
    • United States
    • Seattle University School of Law Seattle University Law Review No. 30-03, March 2007
    • Invalid date
    ...742, 756-58 (1972); U.S. Lines, Inc. v. Fed. Mar. Comm'n, 584 F.2d 519, 536 (D.C. Cir. 1978); Nofelco Realty Corp. v. United States, 521 F. Supp. 458, 461-62 (S.D.N.Y. 75. City of West Chicago, 701 F.2d at 638 n.2 (citing the Atomic Energy Act § 189(a), 42 U.S.C. § 2239(a) (2006)). 76. Id. ......
  • List of Case Citations
    • United States
    • Wetlands Deskbook Appendices
    • November 11, 2009
    ...1998), reh’g denied , 1998 U.S. App. LEXIS 16225 (8th Cir. 1998) ........................... 63 Nofelco Realty Corp. v. United States, 521 F. Supp. 458, 11 ELR 21090 (S.D.N.Y. 1981) ................... 80 Nollan v. Cal. Coastal Comm’n, 483 U.S. 825, 17 ELR 20918 (1987) ...........................
  • Federal Wetlands Law Permits Under §404
    • United States
    • Wetlands deskbook. 4th edition -
    • April 11, 2015
    ...Act); see also Shoreline Assocs. v. Marsh, 555 F. Supp. 169, 174–77, 13 ELR 20421 (D. Md. 1983); Nofelco Realty Corp. v. United States, 521 F. Supp. 458, 11 ELR 21090 (S.D.N.Y. 1981); National Wildlife Federation v. Marsh, 568 F. Supp. 985, 993, 13 ELR 20738 (D.D.C. 1983). 245. 33 C.F.R. §3......
  • List of Case Citations
    • United States
    • Wetlands deskbook. 4th edition Appendices
    • April 11, 2015
    ...Nofelco Realty Corp. v. United States, 521 F. Supp. 458, 11 ELR 21090 (S.D.N.Y. 1981) ...102 Nollan v. Cal. Coastal Comm’n, 483 U.S. 825, 17 ELR 20918 (1987) ............................142-45 List of Case Citations Page 713 Norfolk, Town of v. U.S. Army Corps of Eng’rs, 772 F. Supp. 680, 2......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT