Orland Fire Protection Dist. v. Intrastate Piping and Controls, Inc.

Decision Date29 June 1994
Docket NumberNo. 1-93-0936,1-93-0936
CitationOrland Fire Protection Dist. v. Intrastate Piping and Controls, Inc., 637 N.E.2d 641, 266 Ill.App.3d 744, 202 Ill.Dec. 102 (Ill. App. 1994)
Parties, 202 Ill.Dec. 102 ORLAND FIRE PROTECTION DISTRICT, Plaintiff-Appellant, v. INTRASTATE PIPING AND CONTROLS, INC., Defendant-Appellee.
CourtAppellate Court of Illinois

Karl R. Ottosen, Ottosen, Sinson and Trevarthen, Ltd., Wheaton, for appellant.

James E. Mahoney, Griffith & Jacobson, Chicago, for appellee.

Justice GREIMAN delivered the opinion of the court:

Plaintiff Orland Fire Protection District appeals the trial court's rulings finding defendant Intrastate Piping and Controls, Inc. not guilty of violating two local ordinances which require the installation of automatic sprinkler systems with an adequate water supply in buildings of more than 8,000 square feet.

The issue raised by plaintiff on appeal is whether the trial court erred in finding that defendant's facility consists of separate buildings for the purpose of plaintiff's Fire Safety Code (Code). Defendant also challenges whether the ordinance is void for lack of statutory authority and whether the complaints properly charged defendant with violating any ordinance.

We reverse the trial court's finding as contrary to the manifest weight of evidence in that the square footage of the premises exceeds 8,000 square feet as defined by the Code and also find the two issues raised by defendant are without merit.

In 1987 defendant constructed a facility which includes three structures: a warehouse, a garage and an office building. The structures basically stand in a line with the warehouse at one end, the office building at the other end, and the garage in the middle. The two-story office structure is about 6,400 square feet. The garage is about 960 square feet. The size of the warehouse was disputed at trial with plaintiff claiming it measured 8,131 square feet and defendant claiming it measured 7,992 square feet.

The parties do not dispute that (1) the Code requires automatic fire suppression systems to be installed in all buildings or structures with more than 8,000 square feet in the total area; (2) the Code mandates that every automatic sprinkler system have an adequate water supply; (3) defendant's facility includes a warehouse, a garage and an office (although they do not agree whether these structures constitute a single building); (4) the combined square footage of the three structures exceeds 8,000 square feet; (5) defendant has not installed a sprinkler system in its facility; and (6) defendant warranted, by written agreement dated May 18, 1988, that its facility would be in full compliance with the Code by April 5, 1992.

Section F-201.1(6) of the "Definitions" section of the Code provides:

"For purposes of this article, total area means the total area including mezzanines and basements contained within the surrounding exterior walls of a building on all floors and levels added together. The area included within the surrounding exterior walls of a building shall include roof overhangs and extensions and all enclosed extensions. Areas of a building not provided with surrounding walls shall be included within the building area if such areas are included within the horizontal projection of the roof or floor above. Interior walls, including fire walls, fire separation walls, and party walls, shall not be considered as walls which divide a structure into two or more separate buildings, but structures containing such interior walls shall be considered as one building for the purposes of this Section."

On June 25, 1992, plaintiff filed two complaints against defendant. The first complaint (CC 725-530) stated that defendant committed an offense under "chapter 4, section 402.8" by its "failure to install a sprinkler system and supply an adequate supply of water." The second complaint (CC 725-531) stated that defendant violated "chapter 2, section 2-1" because defendant had "no sprinkler system and no water supply."

On August 20, 1992, the trial court conducted a trial where three witnesses testified (Thomas Lia, a fire prevention supervisor for plaintiff; John Nastav, president of defendant; and Edmund Joanis, a civil engineer hired by defendant). Most of the testimony elicited concerned the procedures used to measure the warehouse and the results of the measurements. Plaintiff presented its case maintaining that the warehouse measured 8,131 square feet. Defendant presented its case maintaining that the warehouse measured 7,992 square feet.

Lieutenant Thomas Lia, as the fire prevention supervisor for plaintiff, reviewed defendant's building plans in November 1987 and submitted a report to defendant indicating that the total structure, i.e., "all areas of the building, the office, garage, and warehouse," required a sprinkler fire suppression system. Lia's report was followed by a March 16, 1988, letter which stated that defendant's building measured 8,400 square feet and therefore a sprinkler system must be installed.

In response to these communications, defendant requested and received a variance due to the lack of water supply at its location at that time. The variance allowed defendant until 1990 to install a dry sprinkler system and a subsequent agreement (May 18, 1988) granted defendant until 1992 to bring in the actual water supply. On May 12, 1992, Lia inspected defendant's premises, found no sprinkler systems installed and issued two tickets which became the two complaints later filed by plaintiff.

Lia further testified that no true fire wall stands between the warehouse and the office building. A fire wall is a freestanding structure intended to remain upright to prevent the spread of fire to other structures if the roof falls down on one side. No other structures, such as a roof, can bear on a fire wall which also must protrude a certain height (two feet and eight inches) above the roof. Lia testified that the wall on defendant's property is not freestanding, does bear the roof and does not protrude the necessary height through the roof.

On June 12, 1992, Lia returned to defendant's building with a fire safety consultant and together they measured the interior dimensions of defendant's warehouse to be approximately 8,131 square feet. Lia explained the difference in measurements from March 1988 to May 1992 by testifying that the earlier measurements were based on the exterior of the building from plans only, not based on actual measurements, because the building had not yet been completed in March 1988. Lia testified that the ordinance requires that the building be measured from the interior walls.

John Nastav testified that he entered the May 1988 agreement based on the March 1988 letter from Deputy Chief Buhs representing that the building exceeded 8,400 square feet. Nastav further testified that the buildings at issue were constructed "concurrently" and "built under one permit." Nastav testified that "[w]e built the warehouse, built the office, and then put two walls up." Each of the three structures, according to Nastav, has a separate, independent freestanding wall and none of them would be considered party walls. The garage was built with freestanding walls caulked at both ends. When constructed, the garage was "caulked so that it would not become a solid building. This masonry does not cross-tie in as a combining structure." A "minor air space" exists between the wall of the warehouse and the wall of the garage, and between the wall of the garage and the wall of the office but to reach the air space would require "digging the parking lot."

Nastav further testified that there are two doorways in the garage, i.e., one doorway from the garage into the warehouse and another doorway from the garage into the office area. There is no double wall between the warehouse and the garage to divide the structures into separate units according to following testimony by Nastav.

One solid outside wall surrounds the warehouse. Nastav explained that although there are not two walls, i.e., an exterior wall and a fire wall, "part of the exterior wall became a fire wall because of the way the county made [him] build the building according to their fire code." The type of filler used in a wall determines whether the wall is a fire wall or just an exterior wall. Each of the three buildings has its own separate footing.

Lastly, Edmund Joanis, a civil engineer with Siebert Engineering, testified on behalf of defendant and explained the procedure and the infrared instrument which he used to measure defendant's warehouse and which resulted in a measurement of 7,992.89 square feet. Joanis further opined that plaintiff's consultant could not have rendered an accurate measurement because he used a metal or cloth tape and an improper measuring method.

Thereafter on September 24, 1992, the trial court reviewed the evidence and testimony presented at the August trial and found defendant not guilty as to each of the two charges, i.e., failure to install a sprinkler system and to obtain an adequate water supply for such system. The trial court expressly found that the structures "are not all one building" and that "there are separate footings [and] separate roofs." Regarding the dimensions of the warehouse, the court found that the testimony on behalf of plaintiff was incredible and the testimony on behalf of defendant was "very credible." We do not question the court's finding that defendant's method of measurement of the warehouse was more accurate and therefore was less than 8,000 square feet in area.

The trial court then observed that the first complaint (CC 725-530) charged defendant with violating chapter 4, section 402.8 which is "a housekeeping section saying that this section belongs with 402" and "charges the defendant with violating absolutely nothing." The problem, according to the trial court, is that defendant was never charged with section 402. Due to the erroneous statutory citation, the trial...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
9 cases
  • Alarm Detection Sys., Inc. v. Orland Fire Prot. Dist.
    • United States
    • U.S. District Court — Northern District of Illinois
    • 7 Julio 2016
    ...Fire Prot. Dist., 2014 WL 2601675 (Ill.App.Ct. 2d Dist. June 9, 2014).5 Orland Fire Prot. Dist. v. Intrastate Piping & Controls, Inc., 266 Ill.App.3d 744, 202 Ill.Dec. 102, 637 N.E.2d 641 (1st Dist.1994) ; Wauconda Fire Prot. Dist. v. Stonewall Orchards, LLP, 214 Ill.2d 417, 293 Ill.Dec. 24......
  • Midwest Builder v. Lord and Essex
    • United States
    • Appellate Court of Illinois
    • 9 Noviembre 2007
    ...of fact, but undertake independent analysis of the legal issues involved. Orland Fire Protection District v. Intrastate Piping & Controls, Inc., 266 Ill.App.3d 744, 749, 202 Ill.Dec. 102, 637 N.E.2d 641, 645 (1994). First, Midwest argues that by keeping and later selling the goods that Midw......
  • ADT Sec. Servs., Inc. v. Lisle-Woodridge Fire Prot. Dist.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 27 Febrero 2012
    ...districts to require building owners to install sprinkler systems. See Orland Fire Protection Dist. v. Intrastate Piping & Controls, Inc., 266 Ill.App.3d 744, 202 Ill.Dec. 102, 637 N.E.2d 641, 646 (1994). 3. NFPA 72 defines “Central Station Service Alarm System” as: “A system or group of sy......
  • Branson v. Department of Revenue
    • United States
    • Illinois Supreme Court
    • 30 Noviembre 1995
    ...compensation cases as example of mixed fact and law issue); see also Orland Fire Protection District v. Intrastate Piping & Controls, Inc. (1994), 266 Ill.App.3d 744, 749, 202 Ill.Dec. 102, 637 N.E.2d 641 (recognizing mixed question of law and fact regarding application of facts to legal co......
  • Get Started for Free