Page v. Willey

Decision Date26 September 1994
Docket NumberNo. 93-186,93-186
Citation139 N.H. 33,648 A.2d 206
PartiesGerald and Janice PAGE v. William WILLEY d/b/a Sleeping Bear Construction.
CourtNew Hampshire Supreme Court

Cooper, Hall, Whittum & Shillaber, P.C., Rochester (Daniel J. Harkinson on the brief and orally), for plaintiffs.

Gary R. Cassavechia, Rochester by brief and orally, for defendant.

THAYER, Justice.

The defendant, William Willey, appeals from an order of the Superior Court (Coffey, J.) finding that his installation of a defectively undersized culvert caused a large section of the plaintiffs' yard to erode during a heavy rain storm. The defendant argues, inter alia, that the trial court erred in allowing the plaintiffs, Gerald and Janice Page, to sue under an implied warranty theory because the defect, if any, was not latent, and in awarding costs associated with preparing the plaintiffs' expert for trial. We reverse.

In 1985, Richard and Angela Gray, prior owners of the lot in question, hired the defendant to fill a large depression on the property and to install a culvert to handle the runoff from a seasonal stream that ran through the depression. The defendant installed a one-hundred-foot section of culvert measuring fifteen inches in diameter, although the upstream culvert measured twenty-four inches in diameter.

In 1988, the plaintiffs purchased the property from the Grays. At the time of the purchase, the plaintiffs hired a home inspector who, on his checklist, indicated that yard drainage was "adequate." On August 19, 1991, during Hurricane Bob, the water level rose several feet above the top of the culvert's mouth, cresting over a land bridge that the defendant had constructed. The overflow cut a one-hundred-foot gully, measuring up to six feet deep and twenty-five feet wide, across the plaintiffs' driveway and front yard. The plaintiffs paid $4600 to repair the damage.

The plaintiffs' expert testified that because the defendant failed to install a culvert of at least the diameter of the twenty-four-inch upstream culvert, his work on the culvert was not up to the standards of the industry, and was not workmanlike in quality. The trial court found, based upon this testimony, that the defendant's work was defective; it further found that the defect was latent and could not have been discovered upon a reasonable inspection by the plaintiffs.

The defendant argues that, even assuming that the erosion was caused by a defectively undersized culvert, the trial court erred in allowing the plaintiffs to sue under an implied warranty of workmanlike quality because the defect was not latent as required by Lempke v. Dagenais, 130 N.H. 782, 547 A.2d 290 (1988). The trial court's determination of the latency of a defect is a mixed question of law and fact. We will overturn the trial court's determination if it is clearly erroneous. See Great Lakes Aircraft Co. v City of Claremont, 135 N.H. 270, 282, 608 A.2d 840, 848 (1992). "If, however, the court misapplies the law to its factual findings, we review the result on appeal independently under a plain error standard." Id.

The applicable law is found in Lempke, where we ruled that the implied warranty of workmanlike quality would extend to subsequent purchasers of the property only in cases of "latent defects which become manifest after the subsequent owner's purchase and which were not discoverable had a reasonable inspection of the structure been made prior to the purchase." Lempke, 130 N.H. at 794, 547 A.2d at 297 (quotation omitted). The defendant contends that to the extent the defective feature of the culvert was its size, such a defect cannot be considered "latent" because the size of both the culvert and upstream culvert could easily have been observed upon a reasonable inspection. We agree. The trial court found that the diameter and length of both culverts were at all times known or discoverable by both the plaintiffs and the defendant. Both the plaintiffs' expert and the trial court relied in part upon the size difference in finding the defendant's work defective. We hold that where all of the relevant facts underlying the alleged defect are known or discoverable to the subsequent purchaser upon reasonable inspection at the time of the purchase, no claim for latent defects can later arise....

To continue reading

Request your trial
2 cases
  • Estate of Plummer, 7446
    • United States
    • Maine Supreme Court
    • 24 Octubre 1995
    ...of the court's application of the legal doctrine to the facts. Pongonis v. Pongonis, 606 A.2d 1055, 1057-58 (Me.1992); Page v. Willey, 139 N.H. 33, 648 A.2d 206 (1994). In Low v. Spellman, 629 A.2d 57, 59 (Me.1993), we addressed three factors to be considered in evaluating the reasonablenes......
  • State v. Bonacorsi
    • United States
    • New Hampshire Supreme Court
    • 26 Septiembre 1994

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT