Paul & Backer Co. v. Newman

Decision Date11 December 1968
Citation252 Or. 66,448 P.2d 511
PartiesPAUL & BACKER CO., a corporation, Appellant, v. Richard NEWMAN, Respondent.
CourtOregon Supreme Court

Phil Cass, Jr., Eugene, argued the cause for appellant. On the briefs were Riddlesbarger, Pederson, Brownhill & Young, Eugene.

Stanley E. Clark, Redmond, argued the cause for respondent. On the brief were Copenhaver, Larkin & Bryant, Redmond.

Before McALLISTER, P.J., and SLOAN, O'CONNELL, GOODWIN, DENECKE, HOLMAN and MENGLER, JJ.

MENGLER, Justice pro tem.

This is an appeal from a judgment for the defendant on a counterclaim. Plaintiff was under contract to construct the U.S. Post Office building in Prineville, Oregon. Defendant was the subcontractor for the masonry construction. The subcontract was terminated by the plaintiff prior to completion. Plaintiff completed the work required under the subcontract. Plaintiff filed an action alleging a breach of the subcontract and damages of $14,186.71 as the sum expended by him to complete the subcontract. Plaintiff admits he is withholding the sum of $7,453 from sums due and owing the defendant and accrued from defendant's work. The defendant denied the breach and counterclaimed for $8,452.71, as the reasonable value of the work performed and not paid for. This is the balance which would have been due under the completed contract. Trial was before the court without a jury. A request for special findings was not made. The court found against the plaintiff on its complaint and for the defendant on his counterclaim for $2,952.34.

The plaintiff assigns as error the court's finding for the defendant on his counterclaim because there was no substantial evidence to support the finding of the reasonable value of the work done. He argues that defendant's only evidence as to the value of the work performed prior to plaintiff's termination related to what defendant thought he had coming to him on the balance of the contract.

The finding of the trial court has the same legal effect as a jury verdict. This court is bound by the finding unless there is no substantial evidence in the record to support the finding. Wagner v. Savage, as Adm'r, 195 Or. 128, 244 P.2d 161 (1952).

It is implicit in the trial court's finding that the defendant did not breach the contract. On appeal the defendant is in the position of a builder who has been prevented from fully performing by the owner's termination of the contract.

A builder who has supplied labor and material under an express contract and is prevented from fully performing by the owner's termination of the contract, may regard the contract as terminated, as distinguished from rescinded, and elect to seek a judgment on a common count for the reasonable value of what the owner received...

To continue reading

Request your trial
4 cases
  • Generaux v. Dobyns
    • United States
    • Oregon Court of Appeals
    • April 26, 2006
    ...See Edwards v. Wilcoxen, 278 Or. 91, 562 P.2d 1207 (1977) (rescission disaffirms an instrument); see also Paul & Backer Co. v. Newman, 252 Or. 66, 69, 448 P.2d 511 (1968) ("termination" differs from "rescission" in that the former preserves the remedy of damages for breach, whereas the latt......
  • City of Portland ex rel. Donohue & Fleskes Corp. v. Hoffman Const. Co.
    • United States
    • Oregon Supreme Court
    • September 5, 1979
    ...entitled to recovery in quantum meruit. This is a well-recognized basis for quantum meruit recovery. See e. g., Paul & Backer Co. v. Newman, 252 Or. 66, 68, 448 P.2d 511 (1968); Mohr v. Lear, 239 Or. 41, 48, 395 P.2d 117 (1964). We do not understand Hoffman to challenge this theory of quant......
  • Hendrix v. McKee
    • United States
    • Oregon Supreme Court
    • January 31, 1978
    ...by a trial court sitting as a trier of fact have the same legal effect as a jury verdict. ORS 17.435. See also Paul & Backer Co. v. Newman, 252 Or. 66, 68, 448 P.2d 511 (1968). In our review of the evidence, we are guided by the well-established principle, most recently iterated in Foster v......
  • Markwart v. Fry
    • United States
    • Oregon Court of Appeals
    • December 1, 1982
    ...owner's termination may seek the reasonable value of what the owner received or the balance due on the contract. Paul & Backer Co. v. Newman, 252 Or. 66, 448 P.2d 511 (1968). In seeking the balances due on the contract, plaintiff must show that he has substantially completed the contract up......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT